100 TPD Module — Drawings
Frames and flows v5 and plot plan v6, exported from Lucid at full page size; pan and zoom in the full-screen viewer; edit links to the Lucid documents.
| Document Number | CBT-MOD-DRW-001 |
| Design | Design Zero · 100 TPD Module |
| Document Status | DESIGN ZERO — WORKING DESIGN, UNLOCKED |
| Owner | Carbotura Inc. — Engineering; Allen Witters, Lead Systems Architect |
| Classification | ISC-2 Confidential |
| Authority | CBT-TB-PORTAL-014 (Architect, 2026-11-04) |
| Lucid | frames and flows v5 eafcad99-b7c2-4b74-9be4-ff110d0596c1; plot plan v6 f4b0bfee-a0bd-4349-8168-6afe51c42056 |
1. Frames and flows, v5
Every frame of the Module in its band (Pregenesis™, Regenesis™, Regenesis MAX™, energy and utilities, ISO tank containers), with the material, gas, steam, DC and hydrogen flows between them. Design point: carbon route W1. Labels follow the Design Zero vocabulary (fuel cells, PWR-FCM, tiered tanks, feedstock receiving bay).

2. Plot plan, v6
One Module in three sprung (tensioned-membrane) halls in line with 10 m fire gaps: Hall 1 feedstock receiving bay and Pregenesis™ (75 × 40 m), Hall 2 Regenesis™ and Regenesis MAX™ (75 × 50 m, 15 m ridge), Hall 3 PowerBlock (50 × 40 m). ISO tank containers tiered two-high on an 18 × 50 m pad; MEGC at grade. Envelope 253 × 65 m ≈ 1.64 ha per Module; four Modules sharing lanes and one tiered pad about 4.8 ha of 7.7 at York. R1 limits and hydrogen separation distances remain OPEN.

3. Reading the drawings
The drawings are the Module file made visible: the roster of §4 and §10, the layout of §14, and the flows of the envelope's Sankeys (MOD-ENV-001 §4). Where a drawing and the Module file differ, the Module file is the source of record and the drawing is re-issued.