Design Zero · 100 TPD Module — Module Definition

100 TPD Module — Frame and ISO Tank Definition

Two Lines dispatched equally, four Recyclotron™ reactors, SOFC fuel cells on cleaned syngas, 1,500 VDC, closed loop, no grid; rendered section for section from the sub-session's Module file (§1–24), provenance tags kept, OPEN values not filled.

Doc No.CBT-MOD-DEF-001
RevisionDesign Zero
StatusDESIGN ZERO — WORKING DESIGN, UNLOCKED
ClassificationISC-2 Confidential
Baseline100 TPD Module · carbon route W1
Design Zero
DESIGN ZERO — WORKING DESIGN, UNLOCKED. Design Zero is unlocked; the Architect locks it when the time is right. Every earlier locked record this design touches is unlocked by CBT-TB-PORTAL-014, not amended. Provenance tags [RULED] [COMPUTED] [INFERRED] [OPEN] [PROPOSED] are kept; under Design Zero a [RULED] tag means ruled by the Architect for Design Zero, not locked. OPEN values are not filled.
Document Control
Document NumberCBT-MOD-DEF-001
DesignDesign Zero · 100 TPD Module
Document StatusDESIGN ZERO — WORKING DESIGN, UNLOCKED
OwnerCarbotura Inc. — Engineering; Allen Witters, Lead Systems Architect
ClassificationISC-2 Confidential
AuthorityCBT-TB-PORTAL-014 (Architect, 2026-11-04)
Source of recordCRSRU_HEAT_SOURCE_DESIGN/MODULE_100TPD_DEFINITION.md on main
Sub-sessionCRSRU heat-source design ·
Date2026-11-02 ·
StatusDESIGN ZERO — working design, unlocked (Architect, 2026-11-03: "everything can be unlocked, this will be Design Zero as we perfect it, I will lock it when the time is right"); earlier LOCKED records it touches are unlocked, not amended; [RULED] here means ruled for Design Zero
Reads with00_DESIGN_BASIS_COMMON.md Rev 1, CLEAN_SHEET_H2_CARBON.md, RECYCLOTRON_OPTIMIZATION.md,

Sub-session: CRSRU heat-source design · Date: 2026-11-02 · For: Allen Witters, Lead Systems Architect Classification: ISC-2 Confidential · Status: DESIGN ZERO — working design, unlocked (Architect, 2026-11-03: "everything can be unlocked, this will be Design Zero as we perfect it, I will lock it when the time is right"); earlier LOCKED records it touches are unlocked, not amended; [RULED] here means ruled for Design Zero Direction answered: focus on 100 TPD feedstock input including its ash component; ISO-certified container tanks; fully define a 100 TPD modular factory with two redundant Lines and failover where appropriate. Standing constraints from the session: no grid, ever; no solar at York (19 acres); near-zero; everything frame-contained; magnetrons and most equipment DC-native; black-start hydrogen supplied. Reads with: 00_DESIGN_BASIS_COMMON.md Rev 1, CLEAN_SHEET_H2_CARBON.md, RECYCLOTRON_OPTIMIZATION.md, D-REG-SCOPE-02, D-LINE-02, D-FME-01-R10, D-PWR-02, FRAME_MODULE_EQUIPMENT_DOCTRINE.md

Provenance: [RULED] [COMPUTED] [INFERRED] [OPEN]. Frame types not in a locked roster are PROPOSED. Vocabulary (Architect, 2026-11-03; brand.json terminology, canon 122, applied 2026-11-03: "feedstock receiving bay" replaces the retired receiving-floor term): the Module is a closed-loop system; the retired fuel-cell term is not used in any sense — fuel cells are "fuel cells" and PWR-FCM frames, tanks two-high are "tiered". Tags follow CBT-ISOFRT-[protocol]-[name]; Line A / Line B are working labels (tag scheme unissued). Energy figures carry the DC-native chain, PEM balance of plant and the Recyclotron™ organic-sensible and dissociation terms added on 2026-11-02; they supersede the Rev 1 ledger where they differ.


1. The Module in one table

Item Value Provenance
Fresh feed 100 TPD as received, mineral included (23.7 % moisture, 10.2 % mineral, 66.1 % organic on the reference feed) [RULED] D-FME-01-R10; feed per DEFAULT_MSW
Lines 2 × 50 TPD sustained, both duty, outputs combined; each Line's frames rated for 100 TPD capability [RULED] D-LINE-02
Failover A Line's 2× capability carries the Module for a limited period; cross-ties at the cold and dry boundaries only (§5) [INFERRED]
Operating setting Carbon route W1 is the design point (Architect, 2026-11-03, §17.3); hydrogen-maximum is the energy-emergency setting; frames stay sized on the envelope of the two [RULED — direction, record pending]
Recyclotrons 4, all duty, 25 TPD each at 300 kW (carbon route) or ~700 kW (hydrogen-maximum, needs the uprate) [RULED] / RECYCLOTRON_OPTIMIZATION.md
Product scope Day-1 slate of eight (§22): carbon black, bed char, industrial CO₂, ferrous, non-ferrous concentrate, aggregate-grade mineral concentrate, pozzolanic SCM powder, industrial DI water; graphitiser as Phase 2; metals and glass as concentrates [RULED — direction, record pending] Architect 2026-11-03
Electrical bus 1,500 VDC zone bus; 800 VDC device links at ≤250 kW; DC-native loads; no AC except inside drives [RULED] D-PWR-02; Architect 2026-11-02
Power source the Module's own hydrogen in fuel cells on frames; steam topping turbines and an SOFC steam cycle; no grid Architect 2026-11-02
CO₂ captured, liquefied, stored in ISO tank containers, off-taken Architect 2026-11-02

2. Mass balance per Module [COMPUTED], per day

Stream Carbon route W1 Hydrogen-maximum Note
Fresh feed, as received 100 t 100 t includes 10.2 t mineral
Moisture dried off in Pregenesis™ 19 t 19 t to the steam and water loop
Dried feed to the reactors (5 % moisture) 81 t 81 t plus recycled admix 10 to 20 t, internal
Carbon products 18.2 t (bed char 9.4, carbon black 8.9) ~0
Hydrogen to the fuel cells 7.8 to 8.9 t ~14 t internal fuel, never a product
CO₂, captured 51 to 71 t ~140 t the oxygen disposition
Mineral (OmniCrude™ Mineral Phase) 10.2 t plus admix purge 10.2 t plus admix purge
Water produced in the fuel cells 70 to 80 t ~125 t 9 kg per kg H₂; process steam takes 25 to 50 t; the rest is product water
HCl, H₂S, NH₃-derived to acid-gas handling 0.5 t, 0.2 t, 0.2 t same sorbent product
N₂ loop make-up (Option C torch) 2 to 4 t 2 to 4 t from an on-site generator frame or a liquid N₂ tank
Gaseous outputs CO₂ product, N₂ purge, fuel cell cathode air and water vapour same near-zero on the gas side, conditional on CO₂ off-take

3. Energy balance per Module [COMPUTED], at the bus

Carbon route W1 Hydrogen-maximum
Recyclotrons (4), DC-DC HV converters 1.5 MW 3.4 MW (organic sensible and bed steam-carbon counted)
CRSRU heaters (2), DC torch, N₂ loop 6.4 MW (after levers) 7.6 MW (after levers)
Booster, gas train, CO₂ separation and liquefaction, drives 1.6 MW 2.6 MW
Pregenesis™, APS, controls, N₂ generator 1.1 MW 1.1 MW
Loads 10.6 MW 14.7 MW
Fuel cells, PEM 55 %, balance of plant and DC-DC deducted 5.6 MW 9.4 MW
Steam topping turbine 0.15 MW 0.4 MW
Balance, PEM −4.2 MW −4.6 MW
Fuel cells, SOFC on syngas, gas train deleted 7.2 MW, loads −0.8 11.9 MW, loads −1.4
Balance, SOFC with the steam cycle (§12.5) −0.5 MW +0.3 MW

The Module does not close on PEM at either setting without a grid; it closes on SOFC at the hydrogen-maximum setting, and on the carbon route it needs a calorific floor on the feed as well. The 8 MW per Module PowerBlock nameplate (ZEP TDS) is below both load figures and must be re-based to 12 to 15 MW of fuel-cell capacity per Module. This is the single ruling the rest of the definition waits on.

4. Frame roster per Module

4.1 Pregenesis™ [PROPOSED] (one train per Module; failover by buffer)

Frame type Count Rating and duty Failover
PRE-ING ingest, weighing, 0A feedstock receiving bay interface 1 100 TPD, 2 shifts receiving buffer 1 day
PRE-SHR primary shredder + hammermill to 13 mm top size 1 200 TPD capability; 100 TPD target in 16 h spare rotor set; the dried-feed buffer carries 24 h
PRE-SEP ferrous magnet + eddy-current non-ferrous 1 in line with PRE-SHR bypass with manual sort for hours only
PRE-DRY paddle dryer on 3 bar turbine-outlet steam, to 5 % moisture 2 × 50 % 50 TPD each, 0.18 MW thermal each cross-tied: either dryer feeds either Line
PRE-ADX admix pulveriser (VRM) + rotational mixer, EAF by reflected-power setpoint 1 125 TPD blended admix recycle buffer 2 days
PRE-SIL dried-feed live-bottom buffer 4 × 40 ft 24 h = 80 t at 0.3 t/m³ in 4 frames the one item that fights frame containment; a 3-day buffer is a site silo — ruling needed

4.2 Regenesis™ [RULED] D-REG-SCOPE-02, 13 serials, unchanged

Frame type Count Per Line Note
CBT-ISOFRT-REG-MCR Recyclotron™ 4 2 600 kW installed, 800 kW with uprate; DC-DC HV converters on the frame
CBT-ISOFRT-REG-FDS Feed Distribution 1 shared the natural cross-tie: any dryer to any reactor
CBT-ISOFRT-REG-PCY Primary Cyclone 2 1 catch to REG-CCS-001, pristine carbon
CBT-ISOFRT-REG-CRS CRSRU vessel 2 1 rated for 100 TPD vapour
CBT-ISOFRT-REG-PTS Plasma Torch Skid 2 1 2 × 3.4 MW torches, chopper, N₂ loop compressor; no cross-tie (hot, 1,400 °C)
CBT-ISOFRT-REG-QBR Quench Boiler 2 1 40 bar / 400 °C steam; steam topping turbine on the frame; no cross-tie (reaction control)

Hot-gas booster after the PCY: inside the CRS frame as an option.

4.3 Regenesis MAX™ [PROPOSED] (roster not yet drawn in the record)

Frame type Count Rating Failover
MAX-HRS HRSG, 800 → 250 °C 2 × 50 % 0.85 MW thermal each at 50 TPD, 2× capable cross-tie after the HRSG: either Line's gas to either downstream train
MAX-FLT candle filter, carbon black catch 2 × 50 % 110 to 260 m² each at 0.5 atm, half with the booster cross-tied with MAX-HRS
MAX-AGR dry-sorbent acid-gas removal (NaHCO₃ for HCl, ZnO for H₂S) at 350 °C 2 × 50 % 0.5 t/d HCl, 0.2 t/d S cross-tied
MAX-WGS two-stage shift (HT + LT) 2 × 50 % PEM design only; deleted with SOFC cross-tied
MAX-CO2 membrane CO₂ separation + liquefaction 2 × 50 % 1.5 t/h each (H₂-max), 0.15 to 0.35 MW with SOFC: liquefaction only, on the anode outlet
MAX-PSA H₂ PSA, tail gas to the CRSRU 2 × 50 % PEM design only cross-tied
MAX-N2G N₂ generator (membrane) for loop make-up 1 100 to 200 Nm³/h liquid N₂ ISO tank as backup
MAX-CSP carbon/mineral separation (density, magnetic) and carbon black handling 1 18 t/d carbon, 10 t/d mineral 2-day solids buffer
MAX-ACT, MAX-GRA activation, graphitization 1 each product finishing; not sized here OPEN

The Secondary Cyclone has no carbon duty under either setting and is not rostered; a coarse guard can sit inside MAX-HRS if wanted.

4.4 Energy and utilities [PROPOSED] (PowerBlock and NEXUS today)

Frame type Count Rating Failover
PWR-FCM fuel-cell frames, PEM or SOFC, DC out to the zone bus 12 to 15 at 1 MW per 40 ft frame 12 to 15 MW per Module, not 8 failover from the installed headroom (fuel cells sized at target plus swing); no standby frames
PWR-BES BESS, DC-coupled 2 × 20 ft 2.5 MWh and 1 MW each bus stiffness, 1 to 2 h ride-through, pulse-load buffer
PWR-STG steam topping turbine-generator with active rectifier on each REG-QBR 0.15 to 0.25 MW per Line none needed
NXS-Z1 DC distribution board, 1,500 VDC, HVIL, zone-bus taps 1 15 MW duplicated busbar sections
NXS-Z2 thermal: dry coolers, DI loop, steam header 2 × 50 % 3 to 5 MW rejected cross-tied
UTL-APS Atmospheric Processing System 1 process-capture basis —
UTL-WTR water treatment, fuel-cell water to steam quality, product water 1 125 t/d —
UTL-CTL controls, EMS, 48 VDC bus 1 — redundant controllers

5. Failover logic [INFERRED]

Boundary Cross-tie Why
Dryer → FDS yes, inherent REG-FDS is one per Module and feeds all four reactors
Reactor → PCY → CRS → PTS → QBR no hot vapour at 600 °C with tars, a 1,400 °C vessel and a reaction-controlling quench; a Line is a Line here
After the HRSG, ~250 °C, dry gas yes cold, dry, low pressure; either Line's gas to either filter, acid-gas, shift, CO₂ and PSA train
Steam header yes both quench boilers feed one 40 bar header; turbines and process draw from it
N₂ loop yes one loop per Module with two compressors
Zone bus yes one bus, duplicated busbar sections, every fuel-cell frame on it
Fuel cells headroom fuel cells sized at target plus swing; one frame out leaves the Module at target from the installed headroom; no standby frames

Loss of one Line's hot train: the other Line runs toward 100 TPD on its 2× rating for as long as the refractory and electrode life allow; the dried-feed buffer and the gas-train cross-tie carry the rest. Loss of a dryer, HRSG, filter, shift or PSA frame: the paired frame carries 100 percent for the duration. Loss of the torch skid: the Line stops; the vapour is not routable hot. That is the one single point per Line, and it is why the torch skid carries two torches.

6. ISO tank containers per Module [PROPOSED]

Service Tank type Working condition Daily turnover On-site buffer Count
CO₂, liquid product ISO T50 (pressurised) or T75 (cryogenic), ~24 m³, ~22 t −20 °C, 20 bar 51 to 140 t 2 days 5 to 13 in rotation with the off-taker
H₂ buffer and black-start reserve MEGC 40 ft tube bundle, at grade 250 bar, 500 to 800 kg — 4 h of fuel for the fuel cells plus one start (600 kg); the batch cycle of §18 and §20 4 (was 2; Architect, 2026-11-03, §20.3)
N₂ loop backup ISO T75 cryogenic, 20 m³, ~16 t liquid make-up 2 to 4 t 4 days 1
Process water and fuel-cell water ISO T11, 25 m³ ambient 25 to 50 t to steam; 20 to 75 t surplus 1 day 2
Cold-gas condensate (trace aromatics, returned to feed via the separator of §19; aromatics dropped from scope 2026-11-03) ISO T11 ambient <1 t — 1
DI and cooling make-up ISO T11 ambient — 1 day 1
Carbon black, bed char, mineral 20 ft bulk or bulk bags in frames solids 18 t, 10 t 2 days 3 to 4

All tanks are certified units (CSC plate, UN portable tank code) and are delivered, inspected and swapped as units; they are the frame-contained form of the Tier 3 buffer storage in tds-001. Separation distances for H₂ and CO₂ are the layout driver, not the frame count.

Tiering (Architect direction, 2026-11-02: "we will tier the tanks"). Tanks are tiered two-high on the pad on their ISO 1161 corner castings with twist-locks, in service, piped from a manifold at grade with flexible drops to the upper unit:

Unit Fuel cell Basis
CO₂ T50, water, condensate and DI T11 two-high ISO 1496-3 tank frames are rated for tiering loaded; two-high in service is the common terminal practice and keeps the upper manway reachable from a fixed platform
N₂ T75 cryogenic at grade vacuum-insulated shell, vent line and fill connections at one end; kept at grade for the fill tanker
H₂ MEGC at grade tube bundles with valve cabinets and the black-start line; at grade for connection, inspection and separation; tiering is OPEN with the hydrogen-code table
Solids bulk units two-high in the hall handled as frames; the upper unit is the empty swap

Three-high is possible for the CO₂ units where the pad slab allows, and would halve the pad again; it is not drawn because the upper manway then needs a crane for every inspection. Tiered pairs turn over together: the full upper and lower unit are swapped as a pair by the off-taker's truck.

7. Count and footprint [INFERRED]

Group Frames ISO tanks
Pregenesis™ 10 —
Regenesis™ (locked) 13 —
Regenesis MAX™ 14 to 16 (PEM) / 10 to 12 (SOFC) —
Energy and utilities 20 to 24 —
Tanks and bulk — 14 to 23
Per Module 57 to 63 14 to 23

At 30 m² per 40 ft frame plus access and separation, a Module is roughly 0.7 to 1.0 ha. York at 19 acres (7.7 ha) holds the initial 4 Modules with the building; the 1,000 and 2,000 TPD phases do not fit on that site in this form.

8. What this definition reopens

PowerBlock sizing per Module (8 → 12 to 15 MW) and the PEM lock; Regenesis MAX™ roster; the dried-feed buffer as frame or silo; the Pregenesis™ moisture target and eddy-current separation; D-MCR-FLOW-01, D-46; the steam topping turbine in the QBR frame specification; CO₂ off-take at York; the expanded-phase land at York; the Line tag scheme. None is ruled here.


9. Operating posture — 50 percent of ultimate capability, load-following (Architect, 2026-11-02)

Direction. The two-Line Module's 100 TPD is 50 percent of its ultimate capability of 200 TPD. It is run like a data centre: target utilisation 50 percent, with the ability to follow loads up and down. [RULED — direction, record pending]; consistent with D-LINE-02 (each Line at 50 percent of capability) and D-MCR-MOD-01 (power capped and modulated; installed above operating is the intended posture).

9.1 Ratings become two numbers on every frame

Target (sustained) Capability (envelope)
Module 100 TPD 200 TPD
Line 50 TPD 100 TPD
Recyclotron™ 25 TPD at 300 kW 50 TPD at 600 kW (800 installed; 1.2 MW uprate ceiling)
Every process frame in §4 the §2 and §3 figures 2× those figures; this is already how §4 rates the Line frames
Pregenesis™ train 100 TPD 200 TPD, not the 150 shown in §4.1 — corrected to 200

9.2 What "follow loads" follows

The Module has no grid, so it does not follow an external demand. It follows three internal states:

Signal Store that buffers it Response
Hydrogen inventory (the H₂ buffer level is the state variable, as battery charge is in a data centre) H₂ MEGC frames, 1 h throughput setpoint rises when the buffer is full, falls when it empties
Feedstock arrival and the dried-feed buffer PRE-SIL, 24 h, plus the receiving bay throughput follows supply within the day
Frame availability 2× frame ratings and the cross-ties of §5 the Module holds 100 TPD with a frame out; it does not hold 200 TPD

The control law is a setpoint on Module throughput between the Line floor (about 15 percent, set by the torch) and 200 TPD, driven by H₂ inventory first and feed inventory second, with the 24:1 reactor envelope and the Line turndown envelope (D-ACM-EMS-01, unwritten) as the rate limits.

9.3 What the posture does to the energy system — the sizing choice [INFERRED]

The plant's energy ratio is fixed: at 200 TPD it makes twice the hydrogen and draws twice the power, so the balance does not improve with utilisation. The fuel cells therefore have to be sized to a chosen point:

Fuel-cell sizing Per Module (SOFC basis, hydrogen-maximum closes at 100 TPD) What it buys Cost
To the 100 TPD target 12 to 15 MW the sustained point; excursions above 100 TPD run on the BESS and H₂ buffer for 1 to 2 h lowest
To target plus swing, 130 to 150 TPD sustained 16 to 22 MW day/night and weekly load-following with margin; the same headroom is the failover reserve +$10–20 M per Module
To capability, 200 TPD 24 to 30 MW sustained operation at the envelope; needed only if 200 TPD is ever a contracted rate +$30–50 M per Module

Recommendation: target plus swing, because the direction is to operate at 50 percent and follow, not to sell the envelope, and because the BESS and H₂ buffer cover the hours-scale excursions more cheaply than fuel cells do.

9.4 The constraint the posture exposes

Reaching 200 TPD on the Recyclotrons needs 600 kW per reactor on the carbon route, which is the ruled capability, but about 1.4 MW per reactor on the hydrogen-maximum route (organic sensible, bed steam-carbon and dissociation terms counted), which is above the 1.2 MW uprate ceiling. The 50-percent-and-follow posture is consistent with the carbon route across the whole envelope and with the hydrogen-maximum route only up to about 85 percent of capability. A mixed setting, water dial between the two, is the practical envelope and is a simulator sweep.

9.5 Redundancy, data-centre terms, as applied

Tier Where Form
2N the two Lines' hot trains each Line's frames at 2× target; no cross-tie hot
Headroom, not standby (Architect, 2026-11-03) fuel-cell frames, BESS frames, dryers, gas-train pairs, cooling every unit runs at 50 percent of its capability; one unit out leaves the Module at target on the others' headroom. No hot or cold standby units anywhere in the Module — the 50-percent capacity overhead is the failover.
N torch skid per Line (two torches inside it), FDS, DC board sections single frame, internal redundancy
Buffers dried feed 24 h, H₂ 1 h plus start reserve, CO₂ 2 days, solids 2 days ride-through and load-following

9.6 Line dispatch — equal, unless failover or surge (Architect, 2026-11-03)

Rule. Both Lines run at the same setpoint at all times. The Module throughput setpoint of §9.2 is split equally between Line A and Line B, and within each Line equally between its two Recyclotrons. The split departs from equal in two cases only:

Case Dispatch Limit
Normal, including every load-following move both Lines at the same setpoint, from the Module floor (both Lines at their 15-percent floor, 30 TPD) to target (50 + 50) neither Line is ever idled while the other runs
Surge above target both Lines rise together, up to 100 + 100 TPD for the 1 to 2 h the BESS and H₂ buffer carry the sustained ceiling of §12.7; the reactor uprate ceiling on the hydrogen-maximum setting
Failover, one Line's hot train out the other Line carries the Module alone on its 2× rating, up to 100 TPD refractory and electrode life (§5); the Line returns to equal dispatch when the outage clears

Why. Equal dispatch halves the thermal cycling and electrode duty on each hot frame compared with running one Line hard and one Line cold, keeps both refractories at temperature so failover is a setpoint change and not a start-up, shares the 2× headroom of §9.5 across both Lines so neither is near its envelope in normal service, and makes the two Lines' wear, inspection and change-out schedules identical. The cross-ties of §5 (dryers to FDS, cold-gas header, steam header, N₂ loop, bus) are what let the downstream trains see one Module while the hot trains run as two equal halves.

Consequences in this package. The Module floor is 30 TPD, not 15 (§15.1 and §15.5 corrected); the batch loads of §18 are also split equally where they are per-Line (the two MAX-GAS trains); the Line-level turndown envelope D-ACM-EMS-01 (unwritten) carries the rule.


10. Consolidated roster — combining equipment to cut frame count (Architect, 2026-11-02)

Rules applied: R1 (one shippable, FAT-certifiable unit within the transport envelope — limits OPEN, so a 40 ft envelope and ~30 t are assumed), R2 (co-package only what is co-located, shares utilities, fits the envelope together, and is kinetic-isolation compatible), R3 (ICDs only at the frame boundary, so every merge deletes ICDs), and D-FME-01-R10 (what was a frame becomes an Assembly inside a frame). [INFERRED] throughout; the Regenesis™ merges need a D-REG-SCOPE-02 amendment.

10.1 Pregenesis™: 10 → 7

Combined frame Assemblies inside Why it combines Note
PRE-RCV receiving and separation ingest conveyor, weigh, ferrous magnet, eddy-current one conveyor line, no heavy rotating mass —
PRE-SHR size reduction shredder, hammermill same isolation class, one dust enclosure, one APS tie-in ~30 t, at the envelope
PRE-DRY ×2 paddle dryer, condensate return, dried-feed discharge 2 × 50 % stays for failover two 100 TPD-capable dryers do not fit one frame
PRE-ADX admix VRM pulveriser, rotational mixer, EAF dosing on reflected power one dust system, one feed path —
PRE-SIL ×2 live-bottom dried-feed buffer, 12 h halves the buffer frames; the rest of the buffer is a site silo needs the frame-or-silo ruling

10.2 Regenesis™: 13 → 9 (requires amending D-REG-SCOPE-02)

Combined frame Assemblies inside Why it combines What it retires
CBT-ISOFRT-REG-MCR ×4 Recyclotron™, its DC-DC HV converters, DI cooling unchanged, converters already on the frame —
CBT-ISOFRT-REG-FDS ×1 feed distribution unchanged —
REG-CRS ×2 (one per Line) Primary Cyclone, hot-gas booster, CRSRU vessel, two torches, chopper, N₂ regulation, torch cooling all hot, all on one gas path, one cooling loop, one HVIL; the torch skid's own reason to be separate (electrode service envelope) is met by a service bay on the frame PCY and PTS as frame types; ~30 t, at the envelope
REG-QBR ×2 (one per Line) quench boiler, steam topping turbine-generator with rectifier, HRSG, candle filter one gas path from 1,400 °C to 250 °C, one steam header, one pressure-part certification package; the boiler keeps its own stamp inside the frame HRSG and filter as separate Regenesis MAX™ frames

The Regenesis™ boundary (quench boiler outlet) is unchanged; the HRSG and filter inside REG-QBR are the first Regenesis MAX™ assemblies and sit on a Regenesis™ frame, which R2 permits and the protocol boundary does not forbid, since the boundary is a process point, not a frame edge.

10.3 Regenesis MAX™: 14 to 16 → 5 (PEM) or 3 (SOFC), plus product finishing

Combined frame Assemblies inside Count
MAX-GAS gas conditioning, per Line dry-sorbent acid-gas removal, two-stage shift (PEM only), membrane CO₂ separation 2
MAX-H2C hydrogen and CO₂, per Line H₂ PSA with tail-gas return (PEM only), CO₂ liquefaction 2 (PEM); with SOFC the liquefaction joins MAX-GAS and this frame is deleted
MAX-CSP solids carbon/mineral separation, carbon black and char handling, bulk-bag station 1
MAX-ACT, MAX-GRA product finishing activation, graphitization — not sized 2, unchanged

10.4 Energy and utilities: 20 to 24 → 15 to 21

Combined frame Assemblies inside Count
PWR-FCM fuel cells 1.2 to 1.5 MW per 40 ft at SOFC density 10 to 15 — the one group that does not compress
PWR-BES 5 MWh and 2 MW in one 40 ft, current product density 1
NXS-ELC electrical and control 1,500 VDC board, HVIL, zone-bus taps, 48 VDC, EMS and controllers 1
NXS-THM thermal DI loop, steam header, condensate; dry coolers roof-mounted on the fuel-cell frames 1
UTL utilities APS, water treatment, N₂ generator and loop compressors 1

10.5 Result

Group Before After Rulings needed
Pregenesis™ 10 7 frame-or-silo for the feed buffer
Regenesis™ 13 9 D-REG-SCOPE-02 amendment: PCY and PTS become Assemblies in REG-CRS
Regenesis MAX™ 14 to 16 5 (PEM) / 3 (SOFC) + 2 finishing roster not yet drawn, so none
Energy and utilities 20 to 24 15 to 21 PowerBlock re-basing
Frames per Module 57 to 63 34 to 44
Process frames excluding fuel cells and finishing ~45 ~22
ISO tank containers 14 to 23 10 to 14 CO₂ on-site buffer cut to 1 day with a committed off-taker; one water tank; solids into MAX-CSP
ICDs at frame boundaries — roughly halved R3

10.6 What the merges cost

Two frames sit at the envelope limit (PRE-SHR, REG-CRS) and depend on the OPEN R1 numbers; a 30 t ceiling is assumed. Merging the torch onto the vessel frame puts the electrode service bay on a frame that is hot in service, so change-out procedure and cooling-down time become a maintenance constraint. The quench boiler frame carries a certified pressure part plus a turbine; its FAT is the longest in the Module. Failover is unchanged: the cross-ties of §5 all sit at frame boundaries that survive the merges.


11. FAT, insurability and the common interface set (Architect questions, 2026-11-02)

11.1 Can frames be FAT-tested and insured as units

Yes; it is what the ISO Frame is for. D-FME-01 makes the frame the serialized, FAT-certified, warranty-passported deliverable; the TDS Guarantee Conditionality Statement already makes FAT and the Unitized Warranty Passport conditions of every guarantee. What an insurer needs beyond that, per frame:

Requirement How the roster meets it
A certified unit with a test record shop FAT against a standard test harness (§11.4), FAT record in the passport
Certified pressure parts quench boiler, CRSRU shell, CO₂ and H₂ tanks carry their own stamps inside the frame; ISO tanks carry CSC plates and UN portable-tank codes
Hazardous-area classification H₂ and CO frames classified at the frame boundary; HVIL and gas detection on the frame
No field fabrication all site work is assembly: lift, set, connect at the interface panel; builder's-risk exposure is small
Transit certification ISO 1161 corner castings, CSC-style plate on every frame, lifting per the EDP
A warranty holder the ASI, per frame, per the TDS §18 register

The exception to shop FAT, stated honestly. Hot frames can be fully FAT-tested only if the ASI has a hot test bay: a 7 MW DC supply, an N₂ loop and a vapour simulant for REG-CRS; a steam circuit for REG-QBR; a 1.6 MW supply and admix for a Recyclotron™ frame. Without such a bay those frames get a cold FAT (pressure, vacuum, electrical, controls, interlocks, torch strike on N₂) and a hot SAT on site. The insurer sees the difference; the TPGT in the TDS is the hot test. Recommend the ASI builds one hot bay per hot frame type; it pays for itself at the second Module.

11.2 The common interface set — one kit, every frame a subset

Existing ASI families are kept; the ones the consolidated roster needs and does not have are marked NEW.

Domain Family Spec Carried on Status
Electrical ASI-ZBK-MPC 1,500 VDC zone-bus tap, liquid-cooled busbar, 8 MW per zone NXS-Z1 overhead existing
Electrical ASI-PBK-QC 800 VDC device link ≤250 kW, Amphenol ePower-Lite, <3 m NXS-Z1 drop existing
Electrical ASI-CTL-48 48 VDC controls bus NXS-Z1 NEW (D-48V-01 open)
Safety ASI-HVIL hardwired interlock chain, physically separate tray NXS-Z1 existing practice, unnamed
Data ASI-DAT-MOD-TCP Modbus TCP over shielded Cat6A NXS-Z1 existing
Thermal ASI-THM-HT steam or oil 200–400 °C, 10–40 bar NXS-Z2 existing
Thermal ASI-THM-LP process steam 3 bar from the topping turbines NXS-Z2 NEW
Thermal ASI-THM-DI DI cooling 35/50 °C NXS-Z2 NEW
Thermal ASI-THM-TR 85–95 °C thermal recovery (fuel-cell coolant to dryers) NXS-Z2 existing stream, unnamed
Gas ASI-H2-HPS H₂ high pressure NXS-Z3 existing
Gas ASI-GAS-PRC cold dry process gas ≤2 bar, the cross-tie header after the HRSG NXS-Z3 NEW
Gas ASI-GAS-N2 N₂ loop, 3–5 bar NXS-Z3 NEW
Gas ASI-GAS-CO2 liquid CO₂ to tank NXS-Z3 NEW
Gas, hot ASI-VAP-HT vapour 600 °C, 0.5 atm, Inconel flange with bellows; the one hot frame-to-frame connection (MCR → REG-CRS) adjacent, not overhead NEW; today ICD-MCR-PCY-001, OPEN
Material ASI-RFH-FLG Recyclotron Feed Header NXS-Z4 existing
Material ASI-SOL solids: char, carbon black, mineral, by bulk bag or dense-phase line NXS-Z4 NEW
Material ASI-APS-FLG APS capture duct NXS-Z4 existing
Water ASI-WTR-001 process water NXS-Z2 existing
Mechanical ASI-ISO-* kinetic isolation, by frame frame base existing
Mechanical ISO 1161 castings, twist-locks lifting, tiering two-high where mass allows frame corners standard

Twenty families. Each frame type gets a Frame Interface Schedule: which families, how many of each, at which position on the interface panel. A frame with the right schedule connects to any Module.

11.3 Standardized controllers

One controller family for every frame, with: a standard I/O base and remote I/O; ISA 5.1 tags matching the SCADA tag list (EDP rule); a Modbus register map template per frame type; participation in the HVIL chain by hardwire, never by network; per-channel hardware arc detection on every microwave and torch frame, not SCADA; and a standard energy interface to the EMS — setpoint, turndown range, state, ramp limit — which is the D-ACM-EMS-01 deliverable in concrete form. The frame controller is FAT-tested against the same harness as the hardware.

11.4 Routing rule

All connections are frame to frame or overhead, no trenches: the NEXUS spine carries Z1 electrical and data, Z2 thermal and fluid, Z3 gas, Z4 material and APS, with Z4 physically separate per ARM-2026-002 §5.3. The only direct frame-to-frame connections are hot or gravity ones between adjacent frames: vapour MCR → REG-CRS (ASI-VAP-HT), feed FDS → MCR (gravity and dense phase), solids out of the hot frames. Every frame presents one interface panel at one end, position-coded by family, so the spine drop is identical for every frame of a type and the shop test harness is a copy of the drop.

11.5 What this needs ruled

The eight NEW families and their connector choices; the hot FAT bay at the ASI; the interface-panel position standard; ASI-VAP-HT closing ICD-MCR-PCY-001; and D-48V-01.


12. SOFC heat recovery (Architect question, 2026-11-02) [INFERRED]

12.1 How much heat, per Module, hydrogen-maximum setting

Fuel to the fuel cells about 21 MW LHV (H₂ plus CO); electric 12 to 13 MW at 60 to 62 percent; about 8 MW of heat: cathode air outlet 750 to 850 °C (~5 MW), anode outlet 800 to 900 °C (~2 MW, CO₂ and water with the unconverted fuel), fuel-cell enclosure losses (~1 MW). Usable high-grade heat 6 to 7 MW. At the mixed setting scale by the hydrogen made.

12.2 No afterburner — a specification requirement

Standard SOFC packages oxidise the 15 to 20 percent of unconverted anode fuel in a catalytic afterburner to heat the cathode air. That is oxidation equipment, contrary to the no-oxidation rule, and it would put oxygen into the CO₂ stream. The frame specification instead requires anode off-gas recycle to the anode inlet (system fuel utilisation above 95 percent) with cathode air preheated by recuperation from the cathode outlet; the anode outlet is then CO₂ and water, condensed to liquid CO₂ with no separation step. Capture-ready SOFC designs do this; it must be written into the RFQ because it is not the default.

12.3 Process heat first, then power

Demand per Module, mixed setting Thermal Grade
Feed drying to 5 % 0.7 MW 100 to 150 °C
Bed steam, swept 0 to ruled range 0.5 to 1.5 MW 3 bar steam
Admix, feed and N₂ torch-gas preheat 0.4 MW 150 to 300 °C
CO₂ liquefaction electric, not thermal —
Process heat 1.6 to 2.6 MW
Left for power 4 to 5 MW at 700 to 850 °C

12.4 The steam cycle (supercritical CO₂ cycles dropped by the Architect, 2026-11-02)

Steam cycle
Form HRSG on the SOFC cathode and anode outlets raising 40 bar, 400 °C steam into the same header as the quench boilers; one extraction-condensing turbine per Module; process steam by extraction at 3 bar; air-cooled condenser (no water)
Electric from the 4 to 5 MW 1.2 to 1.5 MW at 25 to 30 percent on this scale
Plus the quench-boiler topping turbines 0.4 MW
Frames per Module HRSG and turbine-generator frame; air-cooled condenser frame or roof-mounted
Maturity TRL 9, catalogue
ROM per Module $2–3 M

12.5 What it does to the balance, per Module (corrected 2026-11-02, later the same day)

With the SOFC fed unshifted syngas (H₂ plus CO, which recovers the shift loss), fuel cells at 62 percent, the gas train deleted, the quench topping turbines and the SOFC steam cycle:

Setting Loads SOFC electric Topping + steam cycle Balance
Hydrogen-maximum 13.3 MW 11.8 MW 0.4 + 1.3 MW +0.3 MW
Mixed (midpoint) ~11.5 MW ~10.0 MW 0.3 + 1.1 MW about zero
Carbon route W1 9.8 MW 8.2 MW 0.15 + 1.0 MW −0.5 MW

The earlier "+2 MW" in this section double-counted; withdrawn. SOFC heat recovery brings the mixed setting to self-sufficiency and the carbon route to within 0.5 MW, which a calorific floor on the feed or 65 percent fuel cells closes.

12.6 Roster effect

Add PWR-HRS (SOFC heat recovery: HRSG, extraction-condensing turbine-generator with rectifier) and PWR-ACC (air-cooled condenser) per Module, 2 frames. Module count 36 to 46 frames.

12.7 What size the Module can support [INFERRED]

The supply-to-load ratio is 0.95 to 1.08 whatever the throughput, so the ceiling is the first hard limit:

Limit Hydrogen-maximum Mixed Carbon route
Fuel cells sized target plus swing, 16 to 22 MW, at ~13 MW of load per 100 TPD 120 to 165 TPD sustained 140 to 190 TPD 165 to 200 TPD
Recyclotron™ power envelope (600 kW cap, 1.2 MW uprate) ~170 TPD (1.4 MW per reactor needed at 200) ~185 TPD 200 TPD
Hot-frame ratings 200 TPD 200 TPD 200 TPD
Peaks above the sustained figure 200 TPD for 1 to 2 h on the BESS and H₂ buffer same same
Sustained, with the chosen fuel cells 120 to 165 TPD 140 to 190 TPD 165 to 200 TPD

Fuel cells at the full 24 to 30 MW would lift every column to 200 TPD except the hydrogen-maximum reactor limit. For York: four Modules on 19 acres are 400 TPD at target and 480 to 660 TPD sustained on the same frames and the same land at the swing rating, 800 TPD at capability on the carbon route with full fuel cells. The 1,000 TPD phase is therefore partly reachable without more land; the 2,000 TPD phase is not.


13. Lucid drawing

The complete dual-Line Module is drawn in Lucidchart, two pages: Carbotura 100 TPD Module - dual Line, frames, flows, balances v5 (2026-11-03, carbon-route design point) — https://lucid.app/lucidchart/eafcad99-b7c2-4b74-9be4-ff110d0596c1/edit (document id eafcad99-b7c2-4b74-9be4-ff110d0596c1). v5 carries the vocabulary rule (PWR-FCM fuel-cell frames, the retired fuel-cell term banned in every sense), the carbon-route design point, no standby units, tiered tanks, graphitisation as the deferrable load, and the heat-cascade balance row. - Page 1, Module - frames and flows: five bands under the NEXUS spine (Pregenesis™; Regenesis™ Lines A and B with the cold-gas and steam headers; Regenesis MAX™ with the solids bulk units; energy and utilities; ISO tank containers). Process flow black, syngas green, steam dashed orange, DC blue, solids brown, black start dashed pink. - Page 2, Mass, energy, storage, utilities: the per-Module mass balance at both settings (§2), the energy balance at the bus (§3 and §12.5), the buffer and product storage register (§6), and the utilities and PowerBlock register (§4.4, §11.2). Earlier versions v1 (39d803ba-…), v2 (6f18a703-…), v3 (4eb09684-…) and v4 (558f2e67-…, old labels) are retitled SUPERSEDED and kept.


14. Physical layout — three sprung halls, drive-through receiving [INFERRED, proposal]

Architect direction, 2026-11-02 (with the simulator's 3D plant view): everything is in a building, sprung structures; drive-through [receiving]; then: [receiving] and Pregenesis can be in a separate building, PowerBlock also, Regenesis and Regenesis MAX in the main hall; then: we will tier the tanks. The layout is therefore three clear-span tensioned-membrane halls per Module, in line, with 10 m fire gaps between them and the frames in rows along their length as the simulator shows them.

Drawn in Lucidchart as plot plan v6 at 20 px per metre: Carbotura 100 TPD Module plot plan v6 - three sprung halls, feedstock receiving bay, tiered ISO tanks (2026-11-03) — https://lucid.app/lucidchart/f4b0bfee-a0bd-4349-8168-6afe51c42056/edit (document id f4b0bfee-a0bd-4349-8168-6afe51c42056); v6 carries the receiving-bay labels (brand.json terminology). v1 (open site), v2 (single hall), v3 (tanks at grade), v4 (old labels) and v5 (retired receiving term) are retitled SUPERSEDED and kept. Footprints: 40 ft frame 12.2 × 2.44 m, 20 ft frame 6.1 × 2.44 m.

14.1 The three halls

Hall Contents Size Height Notes
1 Receiving + Pregenesis™ drive-through receiving lane (6 m, roll-up doors on both long walls, interlocked as an airlock so the bay is enclosed while a truck discharges); 20 × 20 m feedstock receiving bay with push wall; PRE-RCV; two rows of 40 ft frames: PRE-SHR, PRE-DRY 1, PRE-SIL 1 and PRE-ADX, PRE-DRY 2, PRE-SIL 2 75 × 40 m eave 7 m dust and odour contained in one volume; the only hall trucks enter; loader works the floor
2 Main: Regenesis™ + Regenesis MAX™ FDS at the head; Line A north of the spine, Line B south, mirrored: MCR 1, MCR 2, CRS hot frame, QBR recovery frame per Line; MAX-GAS A and B, MAX-CSP, four solids bulk units, MAX-ACT, MAX-GRA 75 × 50 m ridge 15 m, eave 9 m the only hall that needs the height for the 9 m Recyclotron™ frames; gable frame-swap doors; H₂ detection and relief vents at the ridge; powered extraction over the hot bays
3 PowerBlock 15 SOFC fuel-cell frames in two rows, long axis north–south; PWR-HRS, NXS-ELC, PWR-BES and NXS-THM, UTL as 40 ft frames at the west end 50 × 40 m eave 7 m air-cooled condenser and fuel-cell dry coolers outside the south wall; the 1,500 VDC switch frame is here, so the bus leaves this hall to the other two
Tank pad (outside) one column of two-high fuel cells nearest Hall 3: 2 × water T11, condensate over DI T11, N₂ T75 at grade, four pairs of CO₂ T50; two H₂ MEGC at grade in a dashed separation zone beside it 18 × 50 m — tanks tiered per §6; truck access from the fire lane; distances OPEN

Structure for all three: aluminium arches with tensioned membrane; nothing hangs from the membrane. The NEXUS spine, the Z4 feed tray, crane runways and hoists sit on free-standing steel racks inside. Floors are reinforced slab with frame pads on the 2.44 m module; the feedstock receiving bay is the only civil work beyond slab and pads.

14.2 What crosses the gaps

Gap Crossing Form
1, Hall 1 → Hall 2, 10 m NXS-Z4 dried feed from PRE-SIL to the FDS; NEXUS spine (Z1 bus and data to Pregenesis, Z2 thermal for the dryers) enclosed conveyor bridge on the north rack; spine on a pipe bridge over the centre aisle
2, Hall 2 → Hall 3, 10 m Z3 cleaned syngas header to the fuel cells and the cold-gas cross-tie; Z1 1,500 VDC bus from NXS-ELC to the Module; Z2 steam and condensate between QBR, HRSG and NXS-THM pipe bridge over the centre aisle; the bus in its own tray with HVIL continuity across the gap

The spine runs straight through all three halls on one rack line, so the routing rule of §11 (frame to frame or overhead, nothing in trenches) holds across the gaps as well.

14.3 Area

Envelope Dimensions Area
Three halls in line with the two gaps 220 × 50 m 1.00 ha (halls 0.78 ha)
With tiered tank pad (18 × 50 m) and 6 m fire lane 253 × 65 m 1.64 ha per Module
Four Modules at York, halls side by side, shared fire lanes and one tiered pad about 220 × 230 m about 4.8 ha of 7.7
Alternative form Hall 3 parallel south of Hall 2, sharing the gap 170 × 110 m, about 1.9 ha with lanes

Four Modules fit at York in line; the alternative form is more compact in length but wider, and puts the gas and bus bridges across the long wall instead of the gable. The 1,000 and 2,000 TPD phases still do not fit on the site.

14.4 What the three-hall form changes in the design

  • Fire separation by building, not by frame. The feedstock receiving bay (dust, loader fuel), the hot block (1,300 to 1,800 °C vessels, hydrogen) and the fuel cells (hydrogen, 700 °C plus) are in three volumes with 10 m gaps; each hall gets its own strategy (sprinklers over the floor and Pregenesis; extraction, H₂ detection and ridge relief in Hall 2; water mist or inert and H₂ detection in Hall 3).
  • Only Hall 2 is tall. Halls 1 and 3 are standard 7 m eave structures; the 15 m ridge is bought once, for the Recyclotron frames.
  • Weather class drops to indoor for every frame, removing frame roofs and cladding assumed in §11 and helping the R1 weight limit.
  • Crane access from the aisles. Every frame is reachable by a mobile crane in a 6 m aisle through a gable door; the frame-swap rule in §5 holds without a gantry.
  • The feed bridge is a new interface. The dried-feed conveyor across gap 1 is a Z4 link between halls, not between frames; it needs an enclosed, fire-stopped crossing and belongs in the interface set of §11 as a site item.

Everything here is a proposal pending the R1 envelope limits, the hydrogen separation table and a fire-code review of hydrogen and SOFC fuel cells under membrane roofs.


15. Operating envelope — throughput, power and utilities per Module [COMPUTED / INFERRED]

Architect question, 2026-11-03: what are the throughput and power ranges, what are the utilities ranges. Figures are per Module (two Lines), drawn from §2, §3, §9 and §12 and the Option C ledger; ranges run from the carbon route W1 to the hydrogen-maximum setting unless a row says otherwise. Everything scales with throughput from the 100 TPD column except the floors, which are set by the torch and the fuel cells.

15.1 Throughput

Level Module Line Recyclotron™ Set by
Floor 30 TPD (both Lines at their floor; equal dispatch, §9.6) ~15 TPD, about 15 % of capability 6 to 8 TPD torch pilot arc and the N₂ loop minimum; the 24:1 reactor envelope allows lower
Target, sustained 100 TPD 50 25 at 300 kW (carbon) to ~700 kW (H₂-max, uprate) D-LINE-02, the 50-percent posture
Sustained ceiling with fuel cells at target plus swing (16 to 22 MW) 120 to 165 TPD H₂-max · 140 to 190 mixed · 165 to 200 carbon half 30 to 50 fuel-cell capacity (§12.7)
Peak, 1 to 2 h on the BESS and H₂ buffer 200 TPD 100 50 at 600 kW (carbon); H₂-max limited to ~170 TPD by the 1.2 MW uprate ceiling frame ratings and the reactor power cap
One Line out 100 TPD on the remaining Line's 2× rating, duration limited by refractory and electrode life 100 50 §5

15.2 Power at the 1,500 VDC bus

Item At 100 TPD At 200 TPD peak Note
Recyclotrons (4) 1.5 to 3.4 MW 2.4 to 5.6 MW carbon → H₂-max; 2.4 MW is the 600 kW cap × 4; H₂-max at 200 TPD exceeds the uprate
CRSRU torches (2 Lines), N₂ loop 6.4 to 7.6 MW 12.8 to 15.2 MW 2 × 3.4 MW torches per Line; floor ~0.3 MW per Line
Booster, gas conditioning, CO₂ liquefaction, drives 0.8 to 1.2 MW 1.6 to 2.4 MW gas train deleted on the SOFC basis
Pregenesis™, APS, controls, N₂ generator 1.1 MW 1.6 MW partly fixed
Loads 9.8 to 13.3 MW 18 to 25 MW
SOFC electric 8.2 to 11.8 MW up to the installed 16 to 22 MW at 62 percent on syngas
Topping turbines + SOFC steam cycle 1.15 to 1.7 MW 2.3 to 3.4 MW
Balance −0.5 to +0.3 MW the deficit above the sustained ceiling comes from the BESS and H₂ buffer
BESS 2 × 2.5 MWh, 2 × 1 MW ride-through 1 to 2 h, pulse loads
H₂ buffer 2 MEGC, 1 to 1.6 t 1 h of fuel-cell fuel plus one black start (600 kg)
Bus floor (both Lines at their floor, 30 TPD) ~3.5 to 4.5 MW two torch pilots, one dryer, controls; fuel cells at ~20 percent turndown

15.3 Utilities

Utility At 100 TPD At 200 TPD peak Form and note
Heat rejected to air 6 to 10 MW 12 to 20 MW dry coolers on NXS-Z2 (3 to 5 MW), air-cooled condenser of the steam cycle (3 to 3.5 MW), torch cooling 0.75 to 1.3 MW per Line; no cooling towers, no water consumed
Steam 40 bar / 400 °C from two quench boilers and the SOFC HRSG; process draw 25 to 50 t/d at 3 bar (1 to 2 t/h) 50 to 100 t/d drying 0.7 MW thermal, bed steam 0.5 to 1.5 MW (swept), preheats 0.4 MW
Water net producer: 70 to 125 t/d made in the fuel cells, 25 to 50 t/d to steam, 20 to 75 t/d surplus product water 140 to 250 t/d made no raw-water intake at steady state; DI make-up only for the closed loops; fuel-cell water polished in UTL-WTR (125 t/d)
N₂ loop 1,500 Nm³/h circulating (700 to 3,800 across the enthalpy sensitivity); make-up 80 to 150 Nm³/h, 2 to 4 t/d loop 3,000 Nm³/h; make-up 4 to 8 t/d membrane generator 100 to 200 Nm³/h, liquid T75 as backup
CO₂ out 51 to 140 t/d liquid, −20 °C / 20 bar 100 to 280 t/d 0.3 to 0.7 MW electric for liquefaction, counted in the loads; 2 days in four tiered T50 pairs
Hydrogen 7.8 to 14 t/d made and consumed internally 16 to 28 t/d never a product; buffer 1 h
Solids out carbon 0 to 18 t/d; mineral 10.2 t/d plus admix purge; acid-gas sorbent product ~1 t/d double 2-day buffers in 20 ft bulk units
Admix recycle 10 to 20 t/d internal 20 to 40 bottom solids or WTE-derived Enhancement Admix, 0 to 25 %
Compressed and instrument air, APS process-capture basis, not sized OPEN, with the APS sizing
Controls 48 VDC bus, redundant controllers D-48V-01 pending

15.4 Reading the ranges

  • The ratio is fixed. Supply to load stays at 0.95 to 1.08 at every throughput, so the ranges above are a single line scaled by tonnes; the floors and the fuel cell ceiling are the only non-linear points.
  • Water and heat are the two utilities that change sign. The Module makes water and rejects heat; it draws neither from the site at steady state. The site needs a product-water outlet (or a use for it) and air for the coolers, not a water supply.
  • N₂ and CO₂ are the two that leave the fence: N₂ as a small make-up in, CO₂ as the one bulk gaseous product out, 51 to 140 t/d, which is the off-take question at York.
  • The utility that is not yet sized is instrument and process air with the APS; it is carried OPEN.

15.5 Average applied power by tonnage [COMPUTED]

Loads at the bus and generation from the fuel cells plus the steam cycle, per Module, for each operating setting, both Lines dispatched equally (§9.6); fixed load 0.8 MW (controls, APS, one dryer idling, torch pilot arcs) plus a variable load per tonne; fuel cells capped at the 22 MW target-plus-swing installation; fuel-cell frames are modular, so there is no practical minimum. "With cascade" adds the heat-cascade credit of §16. Hydrogen-maximum rows above about 170 TPD and mixed rows above about 185 TPD exceed the Recyclotron™ uprate ceiling and are shown in parentheses.

TPD Carbon: load / gen / balance / with cascade Mixed: load / gen / balance / with cascade H₂-max: load / gen / balance / with cascade Heat rejected before cascade, MW
30 (floor, both Lines) 3.5 / 2.8 / -0.7 / -0.5 4.0 / 3.4 / -0.6 / -0.3 4.6 / 4.1 / -0.5 / -0.1 1.8 to 3.0
25 3.0 / 2.3 / -0.7 / -0.5 3.5 / 2.9 / -0.6 / -0.3 3.9 / 3.4 / -0.5 / -0.2 1.5 to 2.5
50 5.3 / 4.7 / -0.6 / -0.2 6.1 / 5.7 / -0.4 / +0.1 7.0 / 6.8 / -0.3 / +0.4 3.0 to 5.0
75 7.5 / 7.0 / -0.5 / +0.1 8.8 / 8.6 / -0.3 / +0.5 10.2 / 10.1 / -0.1 / +1.0 4.5 to 7.5
100 9.8 / 9.4 / -0.4 / +0.4 11.5 / 11.4 / -0.1 / +1.0 13.3 / 13.5 / +0.2 / +1.6 6.0 to 10.0
125 12.1 / 11.7 / -0.4 / +0.6 14.2 / 14.2 / +0.1 / +1.4 16.4 / 16.9 / +0.4 / +2.2 7.5 to 12.5
150 14.3 / 14.0 / -0.3 / +0.9 16.9 / 17.1 / +0.2 / +1.9 19.6 / 20.2 / +0.7 / +2.8 9.0 to 15.0
175 16.6 / 16.4 / -0.2 / +1.2 19.5 / 19.9 / +0.4 / +2.4 (22.7 / 23.6 / +0.9 / +3.4) 10.5 to 17.5
200 18.8 / 18.7 / -0.1 / +1.5 (22.2 / 22.8 / +0.6 / +2.8) (25.8 / 25.2 / -0.6 / +2.0) 12.0 to 20.0

Reading: the balance stays within ±0.7 MW across the whole range. Below about 50 TPD the fixed 0.8 MW dominates and every setting runs slightly negative (the BESS and H₂ buffer carry it, which is why the floor is a transient, not a dwelling point); from 75 TPD up the balance is a near-constant fraction of load (−4 to +4 percent); at the fuel-cell cap (22 MW, reached only by the hydrogen-maximum setting near 200 TPD) every added tonne is paid from the stores. With the heat cascade the carbon route turns positive from 75 TPD and the Module carries 0.4 to 3.4 MW of margin at 100 TPD and above for load-following, instead of running at zero.


16. The 6 to 10 MW of rejected heat — a cascade, not a cooler (Architect, 2026-11-03) [INFERRED]

Direction: we need to use the 6 to 10 MW of heat being vented, be smart about it, do not fall back on tradition. The tradition is a bottoming cycle and dry coolers. §12 already takes the high-grade heat (process heat first, then the steam cycle). What is still rejected is medium and low grade, and the smart uses of it are the ones that displace electric loads the Module already carries, because on a no-grid Module a megawatt of load displaced is worth more than a megawatt of heat recovered.

16.1 Where the rejected heat is, per Module at 100 TPD

Stream Grade MW Today
SOFC cathode air after the recuperator and HRSG 150 to 250 °C 1 to 1.5 cathode air outlet, recuperated
SOFC fuel cell coolant and enclosure loop (NXS-Z2) 85 to 95 °C 3 to 5 dry coolers
Steam-cycle condenser 50 to 60 °C 3 to 3.5 air-cooled condenser
Torch and power-electronics cooling 35 to 50 °C 1.5 to 2.6 dry coolers
Total 6 to 10 (overlaps at the extremes)

16.2 The cascade, ranked by electric value

# Use Heat taken Grade needed Electric displaced or made, per 100 TPD Why it is not tradition
1 Absorption refrigeration for CO₂ liquefaction (ammonia–water, −25 °C evaporator) and for BESS and power-electronics cooling 1.2 to 2.8 MW 90 to 150 °C: fuel-cell coolant plus the cathode tail 0.3 to 0.7 MW (the whole liquefaction compressor load) turns the largest electric utility load into a heat load; the CO₂ product becomes free to liquefy
2 N₂ torch-gas, admix and dried-feed preheat to 300 to 500 °C from the cathode tail 0.3 to 0.5 MW 150 to 500 °C 0.15 to 0.3 MW (torch electric at 58 percent to gas) every joule put into the plasma feed gas thermally is a joule the torch does not have to make
3 Anode outlet as Recyclotron™ bed gas (chemistry lever, simulator sweep): 850 °C CO₂ and H₂O into the bed drives C + CO₂ → 2 CO and C + H₂O → CO + H₂ up to 2 MW sensible plus the reactants 800 to 900 °C shifts energy from the magnetrons to the fuel-cell outlet; moves the carbon/hydrogen split toward hydrogen uses the heat and the CO₂ chemically, inside the fence; it consumes carbon, so it is a setting, not a default
4 Organic Rankine cycle on what is left of the 85 to 95 °C loop 2 to 3 MW 85 to 95 °C 0.2 to 0.3 MW at 8 to 10 percent the traditional item, kept because it is cheap on this grade; last in the cascade, not first
5 Thermal storage (hot-water or packed-bed, 90 to 400 °C, 10 to 20 MWh) between the HRSG and the turbine buffers, does not consume — makes the steam cycle's 1.2 to 1.5 MW dispatchable against the H₂ inventory the data-centre posture needs a dispatchable source; this is the cheapest one on site
6 Feed pre-conditioning: warm air from the condenser through the 24 h dried-feed buffer and under the receiving-bay slab 0.2 to 0.3 MW 50 to 60 °C 0.1 MW off the dryers; frost-free receiving bay the lowest grade finds its only useful sink in the feed
7 Sprung-hall heating in winter (York), unit heaters on the 85 °C loop 0.5 to 1 MW seasonal 85 °C no electric heating of three halls the halls are the one new heat sink the building decision created

16.3 What the cascade does

Carbon route Mixed Hydrogen-maximum
Electric displaced or made, per 100 TPD 0.8 MW 1.1 MW 1.4 MW
Balance of §12.5 −0.5 MW ≈ 0 +0.3 MW
Balance with the cascade +0.3 MW +1.1 MW +1.7 MW
Heat still rejected 4.5 MW 6 MW 7.5 MW, at lower grade

The carbon route closes without a calorific floor on the feed, and every setting carries margin for load-following. The heat is still rejected in the end, as all heat is; the point is that it is rejected after it has done the liquefaction and the preheating that electricity was doing.

16.4 Roster and rulings

  • PWR-HRS gains the absorption chiller and the thermal store; MAX-CO2 loses its compressor (liquefaction by absorption) — net zero frames.
  • NXS-Z2 becomes a cascaded loop (95 → 60 → 40 °C) rather than one dry-cooler circuit.
  • Item 3 is a chemistry setting for the simulator sweep commissioned by the decision form (Q2); it touches the carbon product and is not adopted here.
  • Hall heating is a specification line for the three halls.
  • No hot standby (Architect, 2026-11-03): every frame runs at 50 percent of its capability and the headroom is the failover; nothing is held warm and idle. The hot FAT bay at the ASI is a test bay, not a standby, and is unaffected.

The same tables are rendered as a standalone page, OPERATING_ENVELOPE.html in this folder (not linked from the portal sidebar, not deployed).


17. Downstream to RC3 — what the Module does and does not include (Architect question, 2026-11-03) [INFERRED]

Question: have we included downstream processes to RC3? No. This definition, its balances (§2, §3, §15) and the plot plan stop at the Module boundary set by the brief: carbon black and bed char, OmniCrude™ Mineral Phase, liquid CO₂, product water, hydrogen as internal fuel. MAX-ACT and MAX-GRA are rostered as placeholders "not sized" (§4.3). The RC3 tier of the RevCon™ ladder (Optimized Circular Materials, the catalog's bankable baseline: 26 products, about 69.4 TPD per 100 TPD: the 80.6 TPD and 30 products of the catalog session's note of 2026-09-08, less the four aromatics products and their 11.25 TPD, which left the catalog at Release 126) needs finishing trains that are not in the roster, the power balance or the halls.

17.1 RC3 floor by family, and where the Module stops

Family RC3 products Module stream today Finishing to RC3 not yet rostered Added load per Module at 100 TPD
CRB carbon CRB-006, 007, 008 high-purity graphite, 019 pristine carbon black 8.9 t/d from the candle filter (vapour-derived, per the 2026-08-27 ruling); bed char 9.4 t/d graphitisation of the pristine carbon (continuous induction or Acheson, 2,800 °C, 3 to 5 kWh/kg) → MAX-GRA; steam activation of char (900 °C) → MAX-ACT; classification and pelletising 1.1 to 1.9 MW electric (graphitiser) + 0.3 to 0.5 MW thermal
MTL metals and REE MTL-010, 012, 013, 014, 015, 033, 050 Mineral Phase 10.2 t/d, ferrous and non-ferrous removed in Pregenesis™ doré, REE-oxide and minor-metal concentrates: leach, solvent extraction, precipitation (MTL-CON-A/B/C in the catalog's terms); 2 to 3 frames, reagents, 20 to 40 t/d water 0.3 to 0.5 MW
GLS glass GLS-005, 006, 007, 012 in the Mineral Phase optical and density sort, cullet wash, silica polish; 1 frame 0.1 MW
GAS industrial gases GAS-006, 007, 008, 016, 017 liquid CO₂ 51 to 140 t/d (an RC2/RC3 gas product in its own right); N₂ from a membrane generator for the loop only the catalog's GAS products are air-separation products, drawn from air not feedstock; an ASU frame, 100 to 300 Nm³/h class 0.3 to 0.6 MW
WTR water WTR-004, 005, 006 and WTR-FC-001 fuel-cell water 20 to 75 t/d surplus product water; UTL-WTR polishes 125 t/d of fuel-cell water polishing to the RC3 grades is a membrane and resin addition inside UTL-WTR 0.05 MW
MTL minerals (MIN merged) MIN-003, 004 Mineral Phase bulk in MAX-CSP grading and bagging; largely included —
Total 26 products 6 to 9 frames, one of them hot (graphitiser) 2 to 3.5 MW electric, 0.5 to 0.8 MW thermal

17.2 What that does to the balances

Carbon route Mixed Hydrogen-maximum
Balance with the heat cascade (§16.3) +0.3 MW +1.1 MW +1.7 MW
RC3 finishing load −2.0 to −3.5 MW −1.5 to −2.5 MW (less carbon) −0.8 to −1.2 MW (no graphite: there is no carbon)
Balance with RC3 finishing −1.7 to −3.2 MW −0.4 to −1.4 MW +0.5 to +0.9 MW, but no CRB products

Two levers close the carbon route again:

  • Graphitisation is the Module's deferrable load. It is batch, it tolerates interruption, and its product keeps. Run it when the H₂ inventory is high and stop it when it is low: it is the natural "follow loads" sink of §9.2, the one the data-centre posture was missing. Sized at 2× average and run half the hours, it draws the fuel-cell margin that §15.5 shows above 100 TPD instead of new fuel cells.
  • The graphitiser is a heat source for the cascade, not only a load: it rejects most of its input above 1,000 °C, of which 0.8 to 1.2 MW is recoverable to the 40 bar header, 0.25 to 0.35 MW electric back through the steam cycle.

With both, the carbon route sits at about −1 MW with the full RC3 slate, which 65-percent fuel cells or a calorific floor on the feed closes; the mixed setting closes on its own.

17.3 The conflict to rule on

The dissociation direction (hydrogen and carbon priority; hydrogen as internal fuel) and the RC3 catalog pull in different directions on two families:

Family Share of gross elemental value (catalog, York basis) Under hydrogen-maximum Under the carbon route
CRB, graphite and the RC4 products it feeds (graphene oxide, spheroidised graphite: ~$85 M/yr at 400 TPD in the catalog session's figures) 34 % gone: the carbon goes to the fuel cells as fuel kept, 18 t/d
ARM, BTX and derivatives 14 % gone: reformed to C and H₂ gone, by ruling (2026-11-03): dropped from the product scope at every setting

The hydrogen-maximum setting therefore removes about half of the catalog's gross elemental value to close an energy balance that the carbon route plus the heat cascade can close by other means.

Ruled by the Architect, 2026-11-03: "Yes, carbon route." The carbon route W1 is the design point; hydrogen-maximum is the energy-emergency setting only. Amended the same day, "Yes, drop aromatics": the ARM family is dropped from the Module's product scope (retired catalog-wide at Release 126); the CRSRU runs at full dissociation severity at every setting; no aromatic pass-through setting in the simulator sweep; the trace cold-gas condensate is a return-to-feed stream through the separator of §19, not a product; the aromatics' carbon and hydrogen report to carbon black and hydrogen. Consequences carried in this package: §1 operating setting; §3 and §15.5 read on the carbon-route column; the fuel cells stay sized at target plus swing (16 to 22 MW) because the emergency setting still has to run; graphitisation is rostered as the deferrable load; the RC3 finishing frames of §17.1 go to the Doc Portal for D-FME-01. The Q2 record (decision form, operating setting) is amended in ARCHITECT_ANSWERS_2026-11-02.md.

17.4 What changes if RC3 finishing is included

  • Roster: +6 to 9 frames (graphitiser, activation, carbon classification, three hydromet frames, glass sort, ASU, water polish), Module count 42 to 55.
  • Halls: the finishing frames fit in Hall 2's MAX bays with a 15 m extension, or in a fourth hall (finishing, 50 × 40 m) between Hall 2 and Hall 3 on the spine; the graphitiser is a hot frame and wants the Hall 2 extraction.
  • Interfaces: reagent supply and spent-reagent return (hydromet) are a new utility family; the ASU adds air intake and vent lines.
  • Product storage: finished RC3 products in 20 ft bulk units and big-bag frames, 2 days, on the tiered pad or in Hall 2.
  • The catalog session owns the product definitions and yields; mapping to frame IDs is the Doc Portal's under D-FME-01. This section is the flag, not the ruling.

17.5 Refining lines defined, by family, and the RC tier each reaches (Architect question, 2026-11-03) [INFERRED]

The five are the catalog's five families, each on its own refining line (Deployment Architecture Canon §7.10 as rewritten at Release 126): Water, Gas, Carbon, Metal (minerals merged) and Glass. Aromatics, dropped from the Module by ruling on 2026-11-03, left the catalog at Release 126. "Defined" means a frame in the roster of §4 or §10 with a rating; "placeholder" means rostered and not sized. RC tiers follow the catalog session's entry-point note of 2026-09-08; the product-ID mapping is the catalog session's to confirm.

Family Refining line defined in this package Product it makes RC tier reached What RC3 needs
CRB carbon MAX-CSP separation and bagging of pristine carbon black (candle filter) and bed char; MAX-ACT activation and MAX-GRA graphitisation as placeholders carbon black CRB-002; bed char CRB-001 RC2 (carbon black), RC1 (char) graphitisation sized (MAX-GRA, 1.1 to 1.9 MW, the deferrable load) → high-purity graphite CRB-008 RC3, which feeds the RC4 graphene and spheroidised products; activation sized → CRB-003 RC2 and CRB-020 RC4
MTL metals and minerals (MIN merged) PRE-SEP ferrous magnet and eddy-current; MAX-CSP density and magnetic separation of the Mineral Phase; grading and bagging recovered ferrous and non-ferrous MTL-001/002; mineral aggregate and SCM MIN-003/004 RC1 for metals; RC3 for the mineral aggregate and SCM, which is the one RC3 reached today doré, REE-oxide and minor-metal concentrates (leach, solvent extraction, precipitation; 2 to 3 frames, 0.3 to 0.5 MW) → the seven MTL RC3 products
GLS glass none; glass stays in the Mineral Phase glass feedstock GLS-001 at best RC1 optical and density sort, cullet wash, silica polish; 1 frame, 0.1 MW → GLS-005/006/007/012
GAS industrial gases MAX-GAS liquefaction of the SOFC anode-outlet CO₂ (by absorption refrigeration on recovered heat, §16); membrane N₂ for the loop only liquid industrial CO₂, 51 to 140 t/d RC2, industrial grade (tier to be confirmed by the catalog session); not the RC3 GAS products, which are air-separation products an ASU frame (0.3 to 0.6 MW) for GAS-006/007/008/016/017; CO₂ purification to beverage or medical grade if an RC3 CO₂ product is wanted
WTR water UTL-WTR 125 t/d polishing of fuel-cell water (the SOFC anode outlet condensate) and product water; membrane and resin polish per §17.1 fuel-cell water WTR-FC-001; product water RC3 with the polish; RC1 without nothing beyond the polish already in §17.1 (0.05 MW); WTR-FC-002 semiconductor grade is a 97-percent-yield RC4 pull-in

Reading. Of the five families, the package defines refining to RC3 for water and the mineral aggregate; to RC2 for carbon black and CO₂; and to RC1 for metals and glass. The carbon line is the one that matters: it is the only family where the RC3 step (graphitisation) is already on the roster as a placeholder, carries most of the catalog's value, and is the Module's deferrable load. Sizing MAX-GRA and MAX-ACT moves CRB from RC2 to RC3 and opens the RC4 carbon products; the hydromet, glass-sort and ASU frames are the rest of the 6 to 9 frames of §17.1.


18. Batchable loads and parasitic energy (Architect question, 2026-11-03) [INFERRED]

Question: what else can we batch to modulate power, what parasitic energy can we harvest. Per Module at 100 TPD on the carbon-route design point. The short answer: about a third of the electric load can be moved within the day, which is the modulation lever that matters; the parasitic heat pool is 1.4 to 2.5 MW more than §16.1 counts, but it is low grade and worth a few hundred kilowatts, not megawatts.

18.1 Deferrable loads, ranked by the swing they give

# Load Average MW Buffer that lets it batch Batch window Swing available
1 Graphitisation of the pristine carbon (§17) 1.1 to 1.9 product keeps; 2-day carbon buffer hours to days the whole load, sized at 2× and run half the hours: up to 3.8 MW
2 Shredder and hammermill (PRE-SHR), already a 16-hour duty at 200 TPD capability 0.3 to 0.5 24 h dried-feed buffer (PRE-SIL) plus the receiving bay hours 0.6 to 1.0 MW when run at full rate in the H₂-rich hours
3 Hydromet metals finishing (§17, leach, SX, precipitation) 0.3 to 0.5 Mineral Phase 2-day buffer; liquor tanks days the whole load
4 CO₂ liquefaction, where it stays electric 0.3 to 0.7 a low-pressure CO₂ gas holder gives 1 to 2 h; with absorption refrigeration (§16) it becomes thermal and batches against the thermal store instead 1 to 2 h 0.3 to 0.7 MW
5 H₂ buffer compression to the 250 bar MEGC (only the buffer flow is compressed; the fuel cells take low-pressure H₂) 0.15 to 0.3 the buffer itself hours the whole load, and it is the natural sink when H₂ inventory is high
6 Admix pulveriser (PRE-ADX VRM) 0.15 to 0.25 2-day admix buffer days the whole load
7 N₂ generator (membrane) 0.1 to 0.2 liquid T75 and the loop receiver hours the whole load
8 Carbon activation, classification, pelletising 0.1 to 0.2 2-day solids buffers days the whole load
9 Water treatment and DI polishing (UTL-WTR) 0.05 to 0.1 T11 tanks, 1 day hours the whole load
10 Dry-cooler and condenser fans 0.2 to 0.4 none; but ambient sets the duty, so the condenser gives more at night and the fans draw less continuous ±0.1 MW, and it argues for night batching
Deferrable within the day 2.7 to 4.9 MW of a 9.8 MW load 25 to 40 percent of load movable, hours-scale

Items 1 and 3 do not exist until RC3 finishing is rostered (§17); without them the deferrable share is 1.3 to 2.4 MW, 13 to 25 percent, which is still more than most industrial plants can offer and is why the Module can be run like a data centre at all.

18.2 The modulation hierarchy that results

Timescale What moves Range Signal
Seconds BESS (2 MW, 5 MWh); fan speeds ±2 MW bus voltage, HVIL
Minutes Recyclotron throughput and the torches that follow the vapour (the 24:1 reactor envelope, the Line floor at 15 percent) 5 to 7 MW between the Line floor and target H₂ inventory first, feed inventory second (§9.2)
Minutes to an hour SOFC fuel cells, electrochemically fast but thermally limited to about 2 to 5 percent per minute; the steam cycle via the thermal store (§16) 3 to 5 MW H₂ inventory
Hours the deferrable loads of §18.1 2.7 to 4.9 MW a day-ahead schedule against the H₂ and feed inventories and the ambient forecast
Days feed buffer (24 h), admix, solids and CO₂ buffers (2 days) throughput ±20 percent across the week feedstock arrivals

The control law of §9.2 gains one line: batch loads run when the H₂ buffer is above its setpoint and stop when it is below, before the throughput setpoint is touched, so the reactors and torches see the slowest and smallest excursions.

18.3 Parasitic energy not yet in the ledger

Heat the Module makes as a by-product of doing work and currently sends to the dry coolers without being counted in §16.1:

Source Grade MW at 100 TPD What it is worth Harvest
Magnetron anode cooling, Gen 1 at 60 to 70 percent efficiency, 4 reactors 50 to 70 °C 0.4 to 1.0 feed pre-conditioning, hall heat; too cool for the chiller unless the return is run at 80 °C, which costs magnetron life one loop with the torch cooling; feed-buffer warm air and the receiving-bay slab
Dryer vapour latent heat: 19 t/d of water evaporated in PRE-DRY 100 °C condensing 0.5 the one parasitic stream warm enough for the absorption chiller; or hall heat in winter condensing coil on the dryer off-gas to the 85 to 95 °C loop; mechanical vapour recompression does not pay on a steam-rich Module
DC-DC converters, drives, BESS round trip (2 to 4 percent of 10 to 13 MW) 40 to 60 °C 0.2 to 0.5 low; same sink as the magnetrons liquid-cooled electronics on the same loop
Reflected microwave power in the circulator loads, EAF 0.10 to 0.15 60 °C 0.1 to 0.3 best harvested by not making it: the reflected-power tuning loop of RECYCLOTRON_OPTIMIZATION.md tuning first; dummy-load coolant to the same loop
Hot solids: bed char and Mineral Phase leaving the reactors at 600 °C, carbon black at 250 °C 250 to 600 °C 0.15 small but high grade: a solids cooler preheats the admix or the N₂ torch gas screw cooler on the bottom-solids outlet
H₂ buffer let-down, 250 bar to fuel-cell pressure through an expander — 0.02 to 0.05 not worth a frame leave
Thermoelectric generators on the hot-frame shells 200 to 300 °C 0.03 to 0.05 at 3 to 5 percent not worth a frame; the water-cooled wall already takes it leave
Total new to the ledger 40 to 100 °C 1.4 to 2.5 MW of heat about 0.15 to 0.3 MW electric-equivalent (drying offset, chiller feed, hall heat)

Two honest notes. First, the parasitic pool is real but low grade: it roughly doubles the 40 to 70 °C heat the Module has, and the only sinks for that grade are the feed, the halls and, through the dryer vapour, the chiller. Second, the largest single "parasitic" item is not a heat stream but the reflected microwave power and the water in the feed: the parasitic ledger of RECYCLOTRON_OPTIMIZATION.md shows most of the microwave energy on as-received feed going to water and inerts, which is why the Module dries to 5 percent and doses admix by the reflected-power loop. Those two levers are worth more than every harvest in this table.

18.4 What this adds to the package

  • §9.2 control law: the batch-load line.
  • UTL-CTL scope: a day-ahead batch scheduler against H₂, feed and ambient.
  • NXS-Z2: one 50 to 70 °C loop collecting magnetron, electronics, BESS and torch cooling, feeding the feed buffer, the receiving-bay slab and the halls; a condensing coil on the dryer off-gas into the 85 to 95 °C loop.
  • REG-MCR bottom-solids outlet: a screw cooler with the heat to admix or N₂ preheat.
  • A CO₂ gas holder (1 to 2 h) if liquefaction stays electric; none if it goes to absorption.

19. Oils caught through oil-water separation (Architect question, 2026-11-03) [INFERRED]

Question: any oils we catch through OWS? Yes, in two places, and on the closed-loop basis the oil caught is returned to the process as feed, not sent out as a residue.

19.1 Where oily water arises, per Module at 100 TPD

Stream Source Flow What is in it Oil caught
Dryer condensate PRE-DRY paddle dryers evaporate 19 t/d of feed moisture at 100 to 150 °C; the condensing coil of §18.3 recovers the latent heat and condenses the vapour 19 t/d water with the steam-distillable organics of the feed: fats, oils and greases from the food fraction, terpenes, light hydrocarbons, dissolved VOCs 50 to 300 kg/d of light oil and grease, floating; the one stream large enough to need a separator
Receiving-bay liquids receiving-bay leachate from as-received feed, floor wash-down, the loader's area 1 to 3 m³/d leachate (organic acids, dissolved organics), suspended solids, fats, oils and greases, drips from the trucks and the loader 5 to 30 kg/d
Drive-through lane and fire-lane drainage rain on the lane through Hall 1 and the paved lanes rain events road hydrocarbons from trucks trace; a standard interceptor
Cold-gas condensate the quench and gas-conditioning train, on the dissociation basis <1 t/d trace aromatics (BTX, naphthalene) that survive the CRSRU; water with aromatics dropped from scope (2026-11-03) this is a return-to-feed stream: through the separator, the organic phase to PRE-ADX, the water to the polish; the condensate T11 of §6 is its buffer
Machinery shredder hydraulics, N₂ loop compressors, drives none by design specify oil-free compressors on the N₂ loop and the H₂ buffer; hydraulic units with drip trays maintenance only

19.2 Where the separator sits and what it does with the oil

Item Proposal
Separator one coalescing-plate oil-water separator, 2 to 5 m³/h, with a sump and a dissolved-air flotation stage for the fats and greases, as an Assembly inside UTL-WTR (§4.4) with a collection sump and lift in Hall 1 under the dryers and the feedstock receiving bay; the lane interceptor is site drainage, outside the frames
Oil and grease caught to the feed: the skimmed oil and the flotation float go to PRE-ADX with the admix and back into the Recyclotrons, where they are hydrocarbons like the rest of the feed and are dissociated to carbon and hydrogen; 50 to 300 kg/d against 81 t/d of dried feed is 0.1 to 0.4 percent and changes nothing in the balances
Water to UTL-WTR polishing with the fuel-cell water and out as product water, or to the steam loop; the dissolved organics in the dryer condensate are the reason the polish of §17.1 has a biological or activated-carbon stage ahead of the membranes, with the activated carbon from MAX-ACT
Separator sludge and solids to PRE-ADX with the oil; nothing leaves the fence from the separator
Near-zero accounting the oil is feed returned, the water is product water; the separator has no outlet other than the process and the water register

19.3 Roster and ruling

  • UTL-WTR gains the separator and flotation Assembly (no new frame); Hall 1 gains a sump and lift; the activated-carbon polish stage is a specification line tying UTL-WTR to MAX-ACT.
  • The dryer off-gas condensing coil (§18.3) is what makes the dryer condensate a liquid stream to separate rather than a vapour to vent; the two decisions go together.
  • Oil-free compressors on the N₂ loop and H₂ buffer are a specification line for REG-CRS and UTL.
  • The receiving-floor leachate collection is a site item for the Hall 1 slab design (§14.1).

20. Excess hydrogen — how much, and what to do with it (Architect question, 2026-11-03) [INFERRED]

Question: as we accumulate excess hydrogen can we not use it to increase capacities, or what is your call; a table of excesses and a matrix of uses. Standing rule: hydrogen is Island-Mode internal fuel, never a product (Engineering Doctrine Canon); nothing below sells, exports or derivatises it.

20.1 Table of excesses, per Module

Conversion used: 1 t of H₂ is 33.3 MWh LHV and about 20.6 MWh electric through the fuel cells at 62 percent; a 1 MW electric surplus for a day is therefore about 1.2 t of H₂ not needed.

Setting, 100 TPD H₂ made Electric balance (§15.5, §16.3, §17.2) H₂ surplus (+) or deficit (−) Share of H₂ made
Carbon route, design point, no cascade 7.8 to 8.9 t/d −0.5 MW −0.6 t/d −7 %
Carbon route, with the heat cascade (§16) 7.8 to 8.9 t/d +0.3 MW +0.35 t/d +4 %
Carbon route, cascade, RC3 finishing on (§17.2, graphitisation as the deferrable load) 7.8 to 8.9 t/d about −1 MW −1.2 t/d −14 %
Mixed, cascade ~11 t/d +1.1 MW +1.3 t/d +12 %
Mixed, cascade, RC3 finishing on ~11 t/d about 0 ≈ 0 —
Hydrogen-maximum (emergency), cascade ~14 t/d +1.7 MW +2.0 t/d +14 %
At 200 TPD surge, carbon route, cascade 15.6 to 17.8 t/d +1.5 MW +1.8 t/d +11 %, for the 1 to 2 h the frames allow

Within the day, under batch scheduling (§18): on the carbon route with the cascade and graphitisation sized at 2× and run 12 hours, the Module runs about +1.4 MW surplus in the off-hours and about −0.8 MW in the on-hours. Surplus accumulates at 70 kg/h for 12 hours, 0.8 to 1.1 t, and is drawn down in the next 12. The two MEGC buffer (1 to 1.6 t, §6) is therefore just large enough for the batch cycle and leaves nothing for black start or a surge; two more MEGC, tiered, give the 4 h buffer the batch posture wants.

Reading. The steady-state excess is a few percent of production in every column, and it is negative on the design point once RC3 finishing runs. The Module's supply-to-load ratio is fixed at 0.95 to 1.08 (§12.7), so an extra tonne of feed brings its own load with it: a 0.35 t/d surplus of hydrogen supports about 3 TPD more throughput, not 30. Excess hydrogen does not buy tonnage. It buys the things in the matrix.

20.2 Matrix of uses, ranked

# Use H₂ it takes What it yields In fence, no oxidation, not a product Verdict
1 Refining depth: electricity for the RC3 finishing loads (graphitisation 1.1 to 1.9 MW, hydromet 0.3 to 0.5, ASU, activation), run as the batch loads of §18 the whole surplus and more 1 t of surplus H₂ is 20.6 MWh, which graphitises 4 to 7 t of pristine carbon to high-purity graphite CRB-008 (RC3) and feeds the RC4 carbon products yes first call. The surplus is worth more as graphite than as anything else, and the sink is deferrable so it absorbs the surplus when it exists
2 Replenish the black-start reserve (600 kg, §6) from the Module's own hydrogen, instead of supplied H₂ 0.6 t once, then top-ups removes an external supply from the no-grid Module; the supplied reserve becomes a commissioning item only yes do it; the first 0.6 t of any surplus goes here
3 Derate the fuel cells: at a given electric output, run more frames at lower current density, consuming slightly more H₂ per kWh 0.2 to 0.4 t/d at 100 TPD fuel-cell efficiency 62 → 64 to 65 percent at the lower current density, and a longer life (degradation scales with current density); the data-centre "run at 50 percent" play applied to the PowerBlock yes do it with the headroom of §9.5; it turns a surplus into frame life
4 Extend the buffer to 4 h with two more tiered MEGC, and schedule the batch loads against it 0.15 to 0.3 MW of compression (§18.1) deeper load-following, a surge that outlasts the BESS, a black start that does not touch the reserve yes do it; it is the enabler of item 1
5 Hydrogen as the Recyclotron™ bed carrier and sweep gas instead of N₂ (the recycled-H₂ carrier of RECYCLOTRON_OPTIMIZATION.md) circulates; not consumed suppresses tar, cuts N₂ make-up and the inert fraction in the syngas, raises vapour quality to the CRSRU yes adopt as the carrier; it is a circulation, not a sink, and it is already in the optimisation file
6 Hydrogen as the CRSRU plasma gas instead of the N₂ loop (Gen 2) circulates; joins the syngas deletes the N₂ loop, the 27 percent inert fraction at the GPU, the N₂ generator and the T75; hydrogen plasma reforms harder than nitrogen plasma; electrode erosion in H₂ plasma is the risk to test yes Gen 2 test target alongside A2; D-65-C confirmed N₂ for the first Modules and this does not reopen it
7 Direct hydrogen reduction of the Mineral Phase oxides (iron, copper, nickel oxides at 700 to 900 °C) as the front end of the MTL finishing line 0.1 to 0.3 t/d metal from oxide inside the fence with water as the only by-product; lifts the MTL line from RC1 toward the RC3 refined metals with less hydromet reagent yes worth a line in the §17.1 hydromet frame; the catalog session to say which MTL products it reaches
8 Raise throughput all of it about +3 TPD per 0.35 t/d, because every tonne brings its own load yes not a use; the ratio is fixed
9 Catalytic hydrogen heaters for process heat — water only, but it is oxidation equipment and the fuel cell already does the job at twice the value no rejected
10 Ammonia from loop N₂, methane from captured CO₂ (Sabatier), hydrogenated products — marketed hydrogen derivatives no: hydrogen as a product in disguise; methanation also returns captured CO₂ to a fuel rejected under the hydrogen rule and the CO₂ capture basis
11 Export to a neighbouring Module through a facility H₂ header pooled at York, four Modules pool their surplus into one finishing hall (one graphitiser line at 4×), which is item 1 at facility scale yes the facility form of item 1; a NEXUS Z3 facility header is the interface
12 Grid, sale, pipeline — — no never

20.3 The call — adopted by the Architect, 2026-11-03 ("Yes, adopt")

Excess hydrogen does not increase capacity in tonnes; it increases capacity in refining depth. Send it to the RC3 finishing loads as the deferrable load, with a 4 h buffer so the batch cycle and a black start both fit, and let the fuel cells run derated on the headroom in between. Use hydrogen as the Recyclotron carrier now and test it as the CRSRU plasma gas for Gen 2, which is a circulation gain rather than a sink. Replenish the black-start reserve from the Module's own hydrogen so the no-grid Module has no external energy supply at all after commissioning. Everything that makes hydrogen a product or a derivative, or oxidises it outside the fuel cell, stays rejected.

Roster effect, now carried in this package: 4 MEGC per Module (4 h buffer, §6 corrected); the H₂ buffer compressor rated for the batch cycle (0.3 MW, oil-free); the fuel cells dispatched derated on the headroom of §9.5 (a control line for UTL-CTL beside the batch scheduler); the black-start reserve replenished from the Module's own hydrogen after commissioning; hydrogen as the Recyclotron™ carrier gas (a specification line for REG-MCR and REG-FDS, from RECYCLOTRON_OPTIMIZATION.md); hydrogen as the CRSRU plasma gas carried as a Gen 2 test target beside A2 in the D-65-C memo; a facility Z3 H₂ header as a NEXUS interface item at York; the MTL hydrogen-reduction step as a line in the §17.1 hydromet frame. Items 8 to 10 and 12 of §20.2 are closed as rejected.

20.4 Graphitisation batch cycle schedule (Architect question, 2026-11-03) [INFERRED]

Basis: carbon route design point, 100 TPD, both Lines equal (§9.6); pristine carbon black 8.9 t/d from the candle filters; one continuous vertical induction graphitiser (MAX-GRA) at 2,800 to 3,000 °C, residence 1 to 3 h, sized at 2× the average duty: 750 kg/h, 2.6 to 3.8 MW at the bus; the H₂ buffer at 4 MEGC (4 h); BESS 2 MW / 5 MWh for the block transients.

Why a block, not a cycle to cold. An induction graphitiser cycled from 2,800 °C to ambient every day destroys its graphite susceptor and insulation in months. The schedule is therefore one production block per day with the hot zone held at about 1,200 °C between blocks on 0.1 to 0.15 MW (4 to 5 percent of rated). That hold is the running state of a deferrable load, not a standby unit under §9.5: the graphitiser is the Module's batch sink and has no duplicate.

Time Block Graphitiser Other batch loads Module balance H₂ buffer
22:00 to 06:00 Production, first 8 h 750 kg/h, 2.6 to 3.8 MW; feed from the 2-day carbon buffer shredder off (22:00 to 06:00); hydromet off; dryers and reactors steady; fans at night duty about −2.2 MW discharging, 1.3 t over the block
06:00 to 10:00 Production, last 4 h, or stop early on the gate as above shredder on at 06:00 (0.6 to 1.0 MW at full rate) about −2.8 MW discharging to the 25 percent gate
10:00 to 18:00 Hold 1,200 °C hold, 0.1 to 0.15 MW; lot cooling and classification shredder on; hydromet day shift (0.3 to 0.5 MW); activation block 10:00 to 18:00 on steam about +0.8 MW charging
18:00 to 22:00 Hold hold; next lot staged shredder on to 22:00; hydromet off at 18:00 about +1.4 MW charging to the 60 percent gate

Quota and block length are the control variables. The gate is in the §9.2 control law: a block starts at 22:00 if the H₂ buffer is above 60 percent and the dried-feed buffer above 12 h, and ends at 10:00 or when the buffer falls to 25 percent, whichever is first. The block length then sets how much of the day's carbon reaches RC3:

Energy available for graphitisation Block Graphitised per day Of the 8.9 t/d
Surplus of the design point with the cascade alone, +0.3 MW (7 MWh/d) 3 h 1.5 to 2 t 20 percent; the rest leaves as carbon black at RC2
Plus 65-percent fuel cells and the graphitiser's own heat recovery to the steam cycle (+0.4 and +0.3 MW, §17.2) 7 to 8 h 5 to 6 t 60 to 70 percent
Full 12 h block, all 8.9 t/d to RC3 12 h 8.9 t 100 percent; needs about 1 MW more than the Module makes at 100 TPD: the calorific floor on the feed, or a Module running above target in the swing band (§12.7), where the same ratio gives the same deficit but the carbon buffer lets blocks be skipped on low-feed days

So at 100 TPD on the design point the Module graphitises roughly two-thirds of its pristine carbon from its own energy and ships the rest at RC2, unless the feed carries the calorific floor. That is the honest position; §17.2 already carries the −1 MW.

Week. Six blocks and one 24 h maintenance window (susceptor inspection, lot QC), with the 2-day carbon buffer absorbing the gap. The block is the first load shed in surge and in Line failover (§9.6), and the hold state means it restarts in under an hour when the gate reopens.

Roster and control lines. MAX-GRA as a continuous vertical induction graphitiser, 750 kg/h, hold state specified; its off-gas heat to the 40 bar header (§17.2); lot handling by the 2-day carbon buffer and a classification step after cooling; the block gate and the hold setpoint in UTL-CTL's batch scheduler (§18.4).


21. Overall energy Sankey and the feed-energy reconciliation (Architect request, 2026-11-03) [COMPUTED]

The Architect asked for one Sankey combining materials, energy and the utilities. The only basis that carries all of them is energy, so the combined diagram (HTML page, section 3, first figure) draws every mass stream at its chemical energy on the lower-heating-value basis and every utility at its heat or electric power, in MW, at the design point.

21.1 The closed ledger behind it, carbon route at 100 TPD with the cascade

Node In Out
Recyclotrons™ feed chemical 19.4; electric 1.5 bed char 3.6; vapour 16.8; magnetron cooling 0.5
CRSRU and quench vapour 16.8; torch electric 6.4; preheat 0.4 carbon black 3.4; syngas 13.2; quench heat and torch cooling 6.6 (3.7 recovered to steam, 2.7 cooling, 0.2 shell and solids)
Fuel cells syngas 13.2 electric 8.2; heat 5.0
Heat pool and cascade 5.0 + 6.6 + 0.5 + 0.8 (drives) + 1.1 (electronics) + 0.55 (dryer vapour) = 14.55 process heat 1.1; electric 1.95 (steam cycle 1.0, topping 0.15, cascade 0.8); rejected to air 11.3
1,500 VDC bus 8.2 + 1.95 = 10.15 reactors 1.5; torches 6.4; gas conditioning and CO₂ 0.8; APS, controls, Pregenesis™ 1.1; margin 0.35
Products carbon 6.9 MW of chemical energy kept (char 3.6, carbon black 3.4); CO₂, water and Mineral Phase carry none

Electricity put into the reactors and the torches is stored in the syngas as chemical energy by the endothermic dissociation, which is why the syngas (13.2) carries more than the feed's share after the carbon is taken out.

21.2 The finding

Closing the ledger needs 19.4 MW of feed chemical energy, which is 25 MJ/kg on the 66.1 t/d of dry, ash-free organics. The reference feed of 00_DESIGN_BASIS_COMMON.md (DAF C57 H7.8 O32.9) sits at 20 to 23 MJ/kg by the usual correlations. The energy ledger of §3 therefore assumes a feed 10 to 25 percent richer than the elemental basis supports, or equivalently it credits the hydrogen yield of §2 in full while the oxygen in the organics takes some of that hydrogen to water in the CRSRU.

Feed LHV, DAF Feed chemical energy Syngas to the fuel cells Fuel-cell electric Design-point balance with the cascade
25 MJ/kg (the ledger as it stands) 19.4 MW 13.2 MW 8.2 MW +0.3 MW
23 MJ/kg 17.6 MW 12.0 MW 7.5 MW −0.4 MW
22 MJ/kg 16.8 MW 11.4 MW 7.1 MW −0.8 MW
20 MJ/kg 15.3 MW 10.2 MW 6.3 MW −1.6 MW

This is the calorific floor on the feed in numbers. The design point closes at +0.3 MW only if the feed carries about 25 MJ/kg DAF; at the reference 22 MJ/kg it is −0.8 MW before RC3 finishing and about −2 MW with it. The levers already in the package carry it: 65-percent fuel cells (+0.4 MW), the graphitiser's heat recovery (+0.3), the parasitic harvest (+0.15 to 0.3), and the feed specification itself (admix of char-rich recycled bottom solids raises the DAF heating value of the blend). It goes to the simulator sweep as the first thing to settle: the CRSRU zone's hydrogen yield against the feed's oxygen, which decides whether §2's hydrogen or §3's electric figure is the one to trust. Until then the carbon-route balance should be read as −0.8 to +0.3 MW, not +0.3.


22. Minimum product set — the Day-1 slate (Architect question, 2026-11-03) [RULED — direction, record pending]

Question: should we do a minimum set of products to deliver? We have not defined all the modules to handle metals, glass, etc.; we will probably be selling a concentrate. Yes, and the answer falls out of the roster as it stands: the Module as rostered delivers eight products, two of them concentrates, with no finishing frame added. Everything beyond the eight is a frame decision, and the first of those is the graphitiser.

22.1 The eight

# Product (catalog ID) Tier t/d at 100 TPD, design point Made by Form sold
1 Carbon black, pristine (CRB-002) RC2 8.9 candle filters on the quench outlet; MAX-CSP classification and bagging bulk bags or 20 ft bulk unit
2 Bed char (CRB-001) RC1 9.4 Recyclotron™ bottom solids after MAX-CSP density and magnetic separation bulk; part recycled as admix, the rest sold
3 Liquid CO₂, industrial (GAS-003) RC2 51 to 71 fuel-cell anode outlet, absorption liquefaction tiered ISO T50, swapped with the off-taker
4 Ferrous (MTL-001) RC1 2 to 7 (feed-dependent) PRE-SEP magnet baled or bulk, to a steel mill
5 Non-ferrous metal concentrate (MTL-002, the catalog's MTL-CON concentrates) RC1 1 to 3 (feed-dependent) PRE-SEP eddy-current plus the heavy fraction of the Mineral Phase from MAX-CSP density separation bulk bags, to a refiner on a payables basis
6 Mineral concentrate, aggregate grade (MIN-001) RC1 6 to 8 light fraction of the Mineral Phase, screened bulk, to cement or construction
7 Pozzolanic SCM powder (MIN-002) RC2 2 to 4 fines of the Mineral Phase, milled in the admix VRM (PRE-ADX) bulk, to cement
8 Industrial DI water (WTR-FC-001) RC3 20 to 75 fuel-cell water through UTL-WTR polish tanker or pipe

Hydrogen is made and consumed; it is not on the list and never will be.

22.2 Why concentrates, not metals and glass products

  • Scale. At 100 TPD the refined-metal volumes are tiny: chromium 0.5 t/d, silver 0.75 kg/d, gold 75 g/d, platinum 10 g/d. A hydromet train (leach, solvent extraction, precipitation, reagents, water treatment of its own) is a chemical plant with operators; it does not pay at one Module and is marginal at four. A refiner pays for the metal in a concentrate at 60 to 90 percent payables with no plant on our side.
  • Feed. The 13 mm hammermill puts glass into the mineral fraction as grit; separating glass as a product at that top size is sorting sand. Glass goes to the aggregate-grade concentrate, where it is a valid pozzolanic and aggregate component, and the GLS family is left to the catalog.
  • Chemistry. The Mineral Phase leaves the Recyclotron at 600 °C, not vitrified; density and magnetic separation is enough to split it into a heavy, metal-bearing concentrate and a light aggregate fraction. That is exactly what MAX-CSP is rostered to do; nothing is missing for the concentrate route.
  • Rare earths and heavies. The catalog's REE and heavy-metal products are sourced from legacy ash and electronics fractions, not from the reference feed; they stay out of scope until a feed with those fractions is contracted.

22.3 What it costs and what it leaves

Day-1 slate (eight) With the graphitiser (Phase 2) Full RC3 finishing (§17)
Frames added 0 (a bagging and baling line inside MAX-CSP) +1 to 2 (MAX-GRA and classification) +6 to 9
Added load 0 1.1 to 1.9 MW, the deferrable load 2 to 3.5 MW
Balance on the design point −0.8 to +0.3 MW (§21) about −1 MW −1.7 to −3.2 MW
Catalog tiers reached RC1 and RC2, water at RC3 adds CRB-005 and CRB-008 at RC3 and opens the RC4 carbon products the RC3 floor less the ash-derived products
Products 8 10 about 50

Ruled by the Architect, 2026-11-03: "Yes, rule it." The eight products of §22.1 are the Module's product scope at Day 1; metals and glass are sold as concentrates; the graphitiser (MAX-GRA with its classification step) is Phase 2, the one finishing decision carried forward, as the Module's deferrable load; the remaining RC3 finishing frames of §17.1 (hydromet, glass sort, ASU, activation beyond char) are out of the Module's scope until a four-Module facility and a feed that justifies them are contracted. Consequences in this package: §1 products row; §17.5 reads with the slate; the RC3 finishing load of §17.2 is replaced by the Phase 2 column above; §20 and §20.4 (hydrogen and the graphitisation schedule) stand as the Phase 2 plan; the product table on the HTML page outlines the eight.

22.4 For the catalog session and Corpus Zone

The Day-1 slate sells concentrates where the catalog lists refined products: the non-ferrous concentrate replaces the MTL RC2 and RC3 metals, the aggregate concentrate absorbs the GLS family, and the catalog's per-facility revenue needs a concentrate line priced on payables, not product prices. That is a commercial model change and it is theirs; the engineering package is consistent either way.


23. Evolution in stages (Architect direction, 2026-11-03: "we need to show evolution in stages") [PROPOSED]

The package is one design read at four points in time. Each stage is reached by a decision already on the record or named below; nothing in a later stage is assumed by an earlier one.

Stage 1 — Day-1 Module Stage 2 — Phase 2, graphitiser Stage 3 — four-Module facility (York) Stage 4 — Gen 2 heat source
Trigger the rulings of 2 and 3 November (§1) the Phase 2 ruling of §22; MAX-GRA sized the 400 TPD contract at York; a finishing hall shared by four Modules the Gen 2 tests: H₂ as plasma gas, A2 microwave, 65-percent fuel cells
Throughput 100 TPD target, both Lines equal; 120 to 165 TPD sustained on the swing rating; 200 TPD peak same 400 TPD target; 480 to 660 TPD sustained on the same frames and land same frames, higher margin
Products 8 (§22.1): carbon black, bed char, industrial CO₂, ferrous, non-ferrous concentrate, aggregate concentrate, SCM powder, industrial DI water 12: adds standard and high-purity graphite (CRB-005, CRB-008) and the classified carbon-black grades (CRB-006, CRB-007) about 50: the RC3 floor less the ash-derived products, through a shared finishing hall (hydromet, glass sort, ASU, activation, water grades) same slate; the RC4 carbon products become reachable from the graphite line when a market justifies them
Catalog tiers RC1 and RC2; water at RC3 adds carbon at RC3 RC3 floor across five families —
Frames per Module 36 to 46 +1 to 2 (MAX-GRA, classification) +6 to 9 in the finishing hall, shared, so +2 per Module-equivalent −2 to −3 (N₂ loop, generator and T75 deleted)
Added electric load 0 +1.1 to 1.9 MW, deferrable (§18, §20.4) +2 to 3.5 MW per Module-equivalent, batched −0.3 MW (no N₂ compression) and +0.4 MW of fuel-cell output
Balance on the design point (§21 range) −0.8 to +0.3 MW about −1 MW; closed by 65-percent fuel cells or the calorific floor on the feed −1.7 to −3.2 MW per Module-equivalent; needs the Stage 4 levers or the calorific floor about +0.5 to +1 MW with H₂ plasma, 65-percent cells and the cascade
Hydrogen internal fuel; 4 MEGC, 4 h; surplus to the black-start reserve and derated fuel cells surplus to the graphitisation block, 22:00 to 10:00 facility Z3 H₂ header pooling four Modules into the finishing hall H₂ as Recyclotron™ carrier and as the CRSRU plasma gas; no N₂ loop
Heat cascade items 1 to 7 (§16) plus the graphitiser's recovery to the 40 bar header (+0.3 MW) shared steam header and thermal store across Modules —
Buildings three sprung halls per Module, tiered tank pad, 1.64 ha the graphitiser in Hall 2's MAX bays four Modules in line sharing fire lanes, one tiered pad, one finishing hall; about 4.8 to 5.5 ha of 7.7 —
What it needs ruled D-65-C, Q2 amendments, D-REG-SCOPE-02, PowerBlock re-basing, D-ACM-EMS-01, product-scope record MAX-GRA specification (continuous induction, hold state) under D-FME-01 finishing-hall frames under D-FME-01; the concentrate-to-refined decision per family; catalog concentrate pricing D-65-C Gen 2 addendum; fuel-cell specification at 65 percent

Reading the stages. Stage 1 is complete on paper and is what this package defines. Stage 2 is one frame and one control line, and it is where the hydrogen surplus and the batch posture go to work. Stage 3 is a facility decision, not a Module decision: the finishing frames only pay when four Modules feed one hall. Stage 4 is the heat-source programme already in the D-65-C memo, and it is the stage that turns the design-point balance positive without a calorific floor on the feed. Stages 5 and 6, the RC4 and RC5 tiers, are facility stages on the shared finishing hall and are set out in §24.


24. Advanced stages — reaching RevCon™ RC4 and RC5 (Architect direction, 2026-11-03) [PROPOSED]

Stages 1 to 4 (§23) take the Module to the RC3 floor. Two further stages reach the catalog's RC4 "Specialized Circular Material" and RC5 "Premium Circular Product" tiers. Both are facility stages built on the shared finishing hall of Stage 3; neither changes the Module, its balances or its halls. Product IDs, chains and volumes are the catalog's (E:/revcon/data/products.json, 100 TPD basis); the lines, units and loads are this package's estimates.

24.1 Stage 5 — RC4 Specialized Circular Material (34 products, 24.2 t/d on the catalog basis)

Line Products Built on Unit operations added Load, frames Dependence
Advanced carbon spheroidised graphite CRB-018, synthetic graphite grades CRB-012, graphene oxide CRB-010, carbon-fibre precursor CRB-009, multi-walled CNTs CRB-011, nanoporous activated carbon CRB-020, mesoporous templated carbon CRB-021 Stage 2 high-purity graphite and conductive carbon; Stage 3 activation spheroidisation mills and carbon coating; graphite grade classification; a graphene-oxide chemical line (controlled exfoliation of HPG, reagent recovery); a CVD line for CNTs with the Module's own CO as the carbon source (CO disproportionation, in fence); chemical activation (KOH) and silica-templating (the template from the glass line) 1.2 to 1.8 MW; 5 to 7 units in the finishing hall none beyond Stage 2; the catalog session's figures put the RC4 carbon products at about $85 M/yr at 400 TPD, most of the catalog's upgrade value
Battery metals black-mass concentrate MTL-045, lithium carbonate MTL-044, lithium hydroxide MTL-048, cobalt sulfate MTL-046, nickel sulfate MTL-047, battery-grade lead MTL-051 Stage 3 hydromet frame a battery pick in the receiving bay ahead of the hammermill (a safety line, not only a product line), black-mass leach and crystallisation, lead refining 0.2 to 0.3 MW; 1 to 2 units feed-fraction dependent: a battery fraction in the feed contract; the reference feed carries little
Ash-derived REE and heavies cerium, lanthanum, neodymium, yttrium, praseodymium, gadolinium MTL-016 to 021; mercury, cadmium, arsenic, antimony, boron MTL-028 to 032 the Mineral Phase, when WTE-derived Enhancement Admix is run at up to 25 percent (§RECYCLOTRON_OPTIMIZATION) a REE-oxide concentrate step and a heavies capture step on the hydromet frame; the heavies step is an environmental duty on the Mineral Phase product in any case, so "capture, then sell" 0.1 to 0.2 MW; 1 unit admix dependent; grams per day, sold as concentrates to a refiner
Glass and silica high-quality cullet GLS-008, specialty glass powder GLS-009, photocatalytic silica-TiO₂ GLS-011 Stage 3 glass sort optical re-sort, fine milling, a coating step 0.1 MW; 1 unit none
Water, deeper polish deionised WTR-007, semiconductor-grade WTR-008 and WTR-FC-002 Stage 3 polish electrodeionisation, ultrafiltration, UV; the cheapest pull-ins in the catalog (95 to 97 percent yield) 0.1 to 0.2 MW none
Specialty gases and CO₂ specialty mixtures GAS-010, beverage-grade CO₂ GAS-017, neon GAS-011 the Stage 1 CO₂ product and the Stage 3 ASU CO₂ purification to beverage grade (the one RC product that sits on a Day-1 stream), a gas blending panel; neon only from a facility-scale ASU residual 0.1 to 0.2 MW; 1 to 2 units neon is ASU-scale dependent
Minerals specialty mineral filler MIN-005 Stage 1 SCM powder air classification and milling 0.05 MW none
Stage 5 total 34 +8 to 12 units in the shared hall +1.8 to 2.7 MW at Module scale, shared across four Modules

24.2 Stage 6 — RC5 Premium Circular Product (17 products, 5.8 t/d on the catalog basis)

Line Products Built on Unit operations added Load, frames Dependence
Graphene and nanocarbon reduced graphene oxide CRB-013, multi-layer CRB-014 and single-layer graphene CRB-015, single-walled CNTs CRB-016, fullerenes CRB-017 Stage 5 graphene oxide and CVD line hydrogen-assisted thermal reduction of GO (the Module's hydrogen as the reductant, internal use); exfoliation and substrate CVD for graphene; precision CVD for SWCNT; fullerenes from a plasma slipstream of the CRSRU vapour, the one RC5 product that comes straight from the heat source and belongs to the Gen 2 programme 0.4 to 0.6 MW; 2 to 3 units kilograms per day; research and specialty scale on the catalog's own basis
Ultra-pure metals tungsten MTL-040, bismuth MTL-041, gallium MTL-042, indium MTL-043 Stage 5 battery and electronics fractions zone refining and electro-refining at grams per day 0.1 MW; 1 unit feed-fraction dependent (electronics, LED and LCD, pharma fractions); a facility toll line with a dedicated feed, not a Module line
Ultra-pure silica and aggregate ultra-pure silica GLS-010, low-activation aggregate MIN-006 Stage 5 glass line and SCM acid leach and classification; aggregate selection by composition 0.1 MW; 1 unit none
Ultra-high-purity gases UHP nitrogen GAS-013, xenon GAS-014, krypton GAS-015 Stage 3 ASU purification train and rare-gas recovery columns; xenon and krypton are parts-per-million of the air processed and only pay on a facility ASU 0.2 MW; 1 unit ASU-scale dependent
Pharmaceutical and ultra-pure water WTR-009, WTR-010, WTR-FC-003 Stage 5 polish cleanroom-class final polish, validation and QC 0.1 MW; 1 unit certification, not engineering
Stage 6 total 17 +6 to 8 units, a cleanroom-class bay in the finishing hall, QC laboratory +0.9 to 1.1 MW at Module scale, shared

24.3 What the advanced stages do and do not change

  • The Module is unchanged. Stages 5 and 6 draw from Stage 1 to 3 streams; the halls, the balances of §15, the dispatch rule and the hydrogen rule stand. Hydrogen is used in fence as a reductant and a CVD atmosphere; it is still never a product.
  • Energy. Together the two stages add about 2.7 to 3.8 MW at Module scale, shared across four Modules; the facility's hydrogen surplus (§20) and the Stage 4 levers carry it, with the calorific floor on the feed as the fallback already recorded in §21.
  • Feed decides the metals. The battery, electronics and ash-derived lines are only as real as the feed fractions and the admix setting behind them; on the reference feed they are concentrate volumes in grams to tens of kilograms per day. The carbon, water, glass and gas lines do not depend on feed.
  • Never delivered, whatever the stage: the mixed gas GAS-001 and pure CO GAS-016, which are the Module's fuel and would cost electricity to sell.
  • What needs ruling before either stage is drawn as frames: the facility finishing-hall partition under D-FME-01, the battery pick in the receiving bay as a safety specification, the admix setting that brings ash REE into scope, and a market pull for each RC5 line before its unit is bought; the catalog session to confirm tiers and the per-unit yields.