100 TPD Module — Frame and ISO Tank Definition
Two Lines dispatched equally, four Recyclotron™ reactors, SOFC fuel cells on cleaned syngas, 1,500 VDC, closed loop, no grid; rendered section for section from the sub-session's Module file (§1–24), provenance tags kept, OPEN values not filled.
| Document Number | CBT-MOD-DEF-001 |
| Design | Design Zero · 100 TPD Module |
| Document Status | DESIGN ZERO — WORKING DESIGN, UNLOCKED |
| Owner | Carbotura Inc. — Engineering; Allen Witters, Lead Systems Architect |
| Classification | ISC-2 Confidential |
| Authority | CBT-TB-PORTAL-014 (Architect, 2026-11-04) |
| Source of record | CRSRU_HEAT_SOURCE_DESIGN/MODULE_100TPD_DEFINITION.md on main |
| Sub-session | CRSRU heat-source design · |
| Date | 2026-11-02 · |
| Status | DESIGN ZERO — working design, unlocked (Architect, 2026-11-03: "everything can be unlocked, this will be Design Zero as we perfect it, I will lock it when the time is right"); earlier LOCKED records it touches are unlocked, not amended; [RULED] here means ruled for Design Zero |
| Reads with | 00_DESIGN_BASIS_COMMON.md Rev 1, CLEAN_SHEET_H2_CARBON.md, RECYCLOTRON_OPTIMIZATION.md, |
- 1. The Module in one table
- 2. Mass balance per Module [COMPUTED], per day
- 3. Energy balance per Module [COMPUTED], at the bus
- 4. Frame roster per Module
- 5. Failover logic [INFERRED]
- 6. ISO tank containers per Module [PROPOSED]
- 7. Count and footprint [INFERRED]
- 8. What this definition reopens
- 9. Operating posture — 50 percent of ultimate capability, load-foll…
- 10. Consolidated roster — combining equipment to cut frame count (A…
- 11. FAT, insurability and the common interface set (Architect quest…
- 12. SOFC heat recovery (Architect question, 2026-11-02) [INFERRED]
- 13. Lucid drawing
- 14. Physical layout — three sprung halls, drive-through receiving […
- 15. Operating envelope — throughput, power and utilities per Module…
- 16. The 6 to 10 MW of rejected heat — a cascade, not a cooler (Arch…
- 17. Downstream to RC3 — what the Module does and does not include (…
- 18. Batchable loads and parasitic energy (Architect question, 2026-…
- 19. Oils caught through oil-water separation (Architect question, 2…
- 20. Excess hydrogen — how much, and what to do with it (Architect q…
- 21. Overall energy Sankey and the feed-energy reconciliation (Archi…
- 22. Minimum product set — the Day-1 slate (Architect question, 2026…
- 23. Evolution in stages (Architect direction, 2026-11-03: "we need …
- 24. Advanced stages — reaching RevCon™ RC4 and RC5 (Architect direc…
Sub-session: CRSRU heat-source design · Date: 2026-11-02 · For: Allen Witters, Lead Systems Architect
Classification: ISC-2 Confidential · Status: DESIGN ZERO — working design, unlocked (Architect, 2026-11-03: "everything can be unlocked, this will be Design Zero as we perfect it, I will lock it when the time is right"); earlier LOCKED records it touches are unlocked, not amended; [RULED] here means ruled for Design Zero
Direction answered: focus on 100 TPD feedstock input including its ash component; ISO-certified container
tanks; fully define a 100 TPD modular factory with two redundant Lines and failover where appropriate.
Standing constraints from the session: no grid, ever; no solar at York (19 acres); near-zero; everything
frame-contained; magnetrons and most equipment DC-native; black-start hydrogen supplied.
Reads with: 00_DESIGN_BASIS_COMMON.md Rev 1, CLEAN_SHEET_H2_CARBON.md, RECYCLOTRON_OPTIMIZATION.md,
D-REG-SCOPE-02, D-LINE-02, D-FME-01-R10, D-PWR-02, FRAME_MODULE_EQUIPMENT_DOCTRINE.md
Provenance: [RULED] [COMPUTED] [INFERRED] [OPEN]. Frame types not in a locked roster are PROPOSED.
Vocabulary (Architect, 2026-11-03; brand.json terminology, canon 122, applied 2026-11-03: "feedstock receiving bay" replaces the retired receiving-floor term): the Module is a closed-loop system; the retired fuel-cell term is not used in any
sense — fuel cells are "fuel cells" and PWR-FCM frames, tanks two-high are "tiered". Tags follow CBT-ISOFRT-[protocol]-[name]; Line A / Line B are working labels (tag scheme unissued).
Energy figures carry the DC-native chain, PEM balance of plant and the Recyclotron™ organic-sensible and
dissociation terms added on 2026-11-02; they supersede the Rev 1 ledger where they differ.
1. The Module in one table
| Item | Value | Provenance |
|---|---|---|
| Fresh feed | 100 TPD as received, mineral included (23.7 % moisture, 10.2 % mineral, 66.1 % organic on the reference feed) | [RULED] D-FME-01-R10; feed per DEFAULT_MSW |
| Lines | 2 × 50 TPD sustained, both duty, outputs combined; each Line's frames rated for 100 TPD capability | [RULED] D-LINE-02 |
| Failover | A Line's 2× capability carries the Module for a limited period; cross-ties at the cold and dry boundaries only (§5) | [INFERRED] |
| Operating setting | Carbon route W1 is the design point (Architect, 2026-11-03, §17.3); hydrogen-maximum is the energy-emergency setting; frames stay sized on the envelope of the two | [RULED — direction, record pending] |
| Recyclotrons | 4, all duty, 25 TPD each at 300 kW (carbon route) or ~700 kW (hydrogen-maximum, needs the uprate) | [RULED] / RECYCLOTRON_OPTIMIZATION.md |
| Product scope | Day-1 slate of eight (§22): carbon black, bed char, industrial CO₂, ferrous, non-ferrous concentrate, aggregate-grade mineral concentrate, pozzolanic SCM powder, industrial DI water; graphitiser as Phase 2; metals and glass as concentrates | [RULED — direction, record pending] Architect 2026-11-03 |
| Electrical bus | 1,500 VDC zone bus; 800 VDC device links at ≤250 kW; DC-native loads; no AC except inside drives | [RULED] D-PWR-02; Architect 2026-11-02 |
| Power source | the Module's own hydrogen in fuel cells on frames; steam topping turbines and an SOFC steam cycle; no grid | Architect 2026-11-02 |
| CO₂ | captured, liquefied, stored in ISO tank containers, off-taken | Architect 2026-11-02 |
2. Mass balance per Module [COMPUTED], per day
| Stream | Carbon route W1 | Hydrogen-maximum | Note |
|---|---|---|---|
| Fresh feed, as received | 100 t | 100 t | includes 10.2 t mineral |
| Moisture dried off in Pregenesis™ | 19 t | 19 t | to the steam and water loop |
| Dried feed to the reactors (5 % moisture) | 81 t | 81 t | plus recycled admix 10 to 20 t, internal |
| Carbon products | 18.2 t (bed char 9.4, carbon black 8.9) | ~0 | |
| Hydrogen to the fuel cells | 7.8 to 8.9 t | ~14 t | internal fuel, never a product |
| CO₂, captured | 51 to 71 t | ~140 t | the oxygen disposition |
| Mineral (OmniCrude™ Mineral Phase) | 10.2 t plus admix purge | 10.2 t plus admix purge | |
| Water produced in the fuel cells | 70 to 80 t | ~125 t | 9 kg per kg H₂; process steam takes 25 to 50 t; the rest is product water |
| HCl, H₂S, NH₃-derived to acid-gas handling | 0.5 t, 0.2 t, 0.2 t | same | sorbent product |
| N₂ loop make-up (Option C torch) | 2 to 4 t | 2 to 4 t | from an on-site generator frame or a liquid N₂ tank |
| Gaseous outputs | CO₂ product, N₂ purge, fuel cell cathode air and water vapour | same | near-zero on the gas side, conditional on CO₂ off-take |
3. Energy balance per Module [COMPUTED], at the bus
| Carbon route W1 | Hydrogen-maximum | |
|---|---|---|
| Recyclotrons (4), DC-DC HV converters | 1.5 MW | 3.4 MW (organic sensible and bed steam-carbon counted) |
| CRSRU heaters (2), DC torch, N₂ loop | 6.4 MW (after levers) | 7.6 MW (after levers) |
| Booster, gas train, CO₂ separation and liquefaction, drives | 1.6 MW | 2.6 MW |
| Pregenesis™, APS, controls, N₂ generator | 1.1 MW | 1.1 MW |
| Loads | 10.6 MW | 14.7 MW |
| Fuel cells, PEM 55 %, balance of plant and DC-DC deducted | 5.6 MW | 9.4 MW |
| Steam topping turbine | 0.15 MW | 0.4 MW |
| Balance, PEM | −4.2 MW | −4.6 MW |
| Fuel cells, SOFC on syngas, gas train deleted | 7.2 MW, loads −0.8 | 11.9 MW, loads −1.4 |
| Balance, SOFC with the steam cycle (§12.5) | −0.5 MW | +0.3 MW |
The Module does not close on PEM at either setting without a grid; it closes on SOFC at the hydrogen-maximum setting, and on the carbon route it needs a calorific floor on the feed as well. The 8 MW per Module PowerBlock nameplate (ZEP TDS) is below both load figures and must be re-based to 12 to 15 MW of fuel-cell capacity per Module. This is the single ruling the rest of the definition waits on.
4. Frame roster per Module
4.1 Pregenesis™ [PROPOSED] (one train per Module; failover by buffer)
| Frame type | Count | Rating and duty | Failover |
|---|---|---|---|
PRE-ING ingest, weighing, 0A feedstock receiving bay interface |
1 | 100 TPD, 2 shifts | receiving buffer 1 day |
PRE-SHR primary shredder + hammermill to 13 mm top size |
1 | 200 TPD capability; 100 TPD target in 16 h | spare rotor set; the dried-feed buffer carries 24 h |
PRE-SEP ferrous magnet + eddy-current non-ferrous |
1 | in line with PRE-SHR |
bypass with manual sort for hours only |
PRE-DRY paddle dryer on 3 bar turbine-outlet steam, to 5 % moisture |
2 × 50 % | 50 TPD each, 0.18 MW thermal each | cross-tied: either dryer feeds either Line |
PRE-ADX admix pulveriser (VRM) + rotational mixer, EAF by reflected-power setpoint |
1 | 125 TPD blended | admix recycle buffer 2 days |
PRE-SIL dried-feed live-bottom buffer |
4 × 40 ft | 24 h = 80 t at 0.3 t/m³ in 4 frames | the one item that fights frame containment; a 3-day buffer is a site silo — ruling needed |
4.2 Regenesis™ [RULED] D-REG-SCOPE-02, 13 serials, unchanged
| Frame type | Count | Per Line | Note |
|---|---|---|---|
CBT-ISOFRT-REG-MCR Recyclotron™ |
4 | 2 | 600 kW installed, 800 kW with uprate; DC-DC HV converters on the frame |
CBT-ISOFRT-REG-FDS Feed Distribution |
1 | shared | the natural cross-tie: any dryer to any reactor |
CBT-ISOFRT-REG-PCY Primary Cyclone |
2 | 1 | catch to REG-CCS-001, pristine carbon |
CBT-ISOFRT-REG-CRS CRSRU vessel |
2 | 1 | rated for 100 TPD vapour |
CBT-ISOFRT-REG-PTS Plasma Torch Skid |
2 | 1 | 2 × 3.4 MW torches, chopper, N₂ loop compressor; no cross-tie (hot, 1,400 °C) |
CBT-ISOFRT-REG-QBR Quench Boiler |
2 | 1 | 40 bar / 400 °C steam; steam topping turbine on the frame; no cross-tie (reaction control) |
Hot-gas booster after the PCY: inside the CRS frame as an option.
4.3 Regenesis MAX™ [PROPOSED] (roster not yet drawn in the record)
| Frame type | Count | Rating | Failover |
|---|---|---|---|
MAX-HRS HRSG, 800 → 250 °C |
2 × 50 % | 0.85 MW thermal each at 50 TPD, 2× capable | cross-tie after the HRSG: either Line's gas to either downstream train |
MAX-FLT candle filter, carbon black catch |
2 × 50 % | 110 to 260 m² each at 0.5 atm, half with the booster | cross-tied with MAX-HRS |
MAX-AGR dry-sorbent acid-gas removal (NaHCO₃ for HCl, ZnO for H₂S) at 350 °C |
2 × 50 % | 0.5 t/d HCl, 0.2 t/d S | cross-tied |
MAX-WGS two-stage shift (HT + LT) |
2 × 50 % | PEM design only; deleted with SOFC | cross-tied |
MAX-CO2 membrane CO₂ separation + liquefaction |
2 × 50 % | 1.5 t/h each (H₂-max), 0.15 to 0.35 MW | with SOFC: liquefaction only, on the anode outlet |
MAX-PSA H₂ PSA, tail gas to the CRSRU |
2 × 50 % | PEM design only | cross-tied |
MAX-N2G N₂ generator (membrane) for loop make-up |
1 | 100 to 200 Nm³/h | liquid N₂ ISO tank as backup |
MAX-CSP carbon/mineral separation (density, magnetic) and carbon black handling |
1 | 18 t/d carbon, 10 t/d mineral | 2-day solids buffer |
MAX-ACT, MAX-GRA activation, graphitization |
1 each | product finishing; not sized here | OPEN |
The Secondary Cyclone has no carbon duty under either setting and is not rostered; a coarse guard can
sit inside MAX-HRS if wanted.
4.4 Energy and utilities [PROPOSED] (PowerBlock and NEXUS today)
| Frame type | Count | Rating | Failover |
|---|---|---|---|
PWR-FCM fuel-cell frames, PEM or SOFC, DC out to the zone bus |
12 to 15 at 1 MW per 40 ft frame | 12 to 15 MW per Module, not 8 | failover from the installed headroom (fuel cells sized at target plus swing); no standby frames |
PWR-BES BESS, DC-coupled |
2 × 20 ft | 2.5 MWh and 1 MW each | bus stiffness, 1 to 2 h ride-through, pulse-load buffer |
PWR-STG steam topping turbine-generator with active rectifier |
on each REG-QBR |
0.15 to 0.25 MW per Line | none needed |
NXS-Z1 DC distribution board, 1,500 VDC, HVIL, zone-bus taps |
1 | 15 MW | duplicated busbar sections |
NXS-Z2 thermal: dry coolers, DI loop, steam header |
2 × 50 % | 3 to 5 MW rejected | cross-tied |
UTL-APS Atmospheric Processing System |
1 | process-capture basis | — |
UTL-WTR water treatment, fuel-cell water to steam quality, product water |
1 | 125 t/d | — |
UTL-CTL controls, EMS, 48 VDC bus |
1 | — | redundant controllers |
5. Failover logic [INFERRED]
| Boundary | Cross-tie | Why |
|---|---|---|
| Dryer → FDS | yes, inherent | REG-FDS is one per Module and feeds all four reactors |
| Reactor → PCY → CRS → PTS → QBR | no | hot vapour at 600 °C with tars, a 1,400 °C vessel and a reaction-controlling quench; a Line is a Line here |
| After the HRSG, ~250 °C, dry gas | yes | cold, dry, low pressure; either Line's gas to either filter, acid-gas, shift, CO₂ and PSA train |
| Steam header | yes | both quench boilers feed one 40 bar header; turbines and process draw from it |
| N₂ loop | yes | one loop per Module with two compressors |
| Zone bus | yes | one bus, duplicated busbar sections, every fuel-cell frame on it |
| Fuel cells | headroom | fuel cells sized at target plus swing; one frame out leaves the Module at target from the installed headroom; no standby frames |
Loss of one Line's hot train: the other Line runs toward 100 TPD on its 2× rating for as long as the refractory and electrode life allow; the dried-feed buffer and the gas-train cross-tie carry the rest. Loss of a dryer, HRSG, filter, shift or PSA frame: the paired frame carries 100 percent for the duration. Loss of the torch skid: the Line stops; the vapour is not routable hot. That is the one single point per Line, and it is why the torch skid carries two torches.
6. ISO tank containers per Module [PROPOSED]
| Service | Tank type | Working condition | Daily turnover | On-site buffer | Count |
|---|---|---|---|---|---|
| CO₂, liquid product | ISO T50 (pressurised) or T75 (cryogenic), ~24 m³, ~22 t | −20 °C, 20 bar | 51 to 140 t | 2 days | 5 to 13 in rotation with the off-taker |
| H₂ buffer and black-start reserve | MEGC 40 ft tube bundle, at grade | 250 bar, 500 to 800 kg | — | 4 h of fuel for the fuel cells plus one start (600 kg); the batch cycle of §18 and §20 | 4 (was 2; Architect, 2026-11-03, §20.3) |
| N₂ loop backup | ISO T75 cryogenic, 20 m³, ~16 t | liquid | make-up 2 to 4 t | 4 days | 1 |
| Process water and fuel-cell water | ISO T11, 25 m³ | ambient | 25 to 50 t to steam; 20 to 75 t surplus | 1 day | 2 |
| Cold-gas condensate (trace aromatics, returned to feed via the separator of §19; aromatics dropped from scope 2026-11-03) | ISO T11 | ambient | <1 t | — | 1 |
| DI and cooling make-up | ISO T11 | ambient | — | 1 day | 1 |
| Carbon black, bed char, mineral | 20 ft bulk or bulk bags in frames | solids | 18 t, 10 t | 2 days | 3 to 4 |
All tanks are certified units (CSC plate, UN portable tank code) and are delivered, inspected and
swapped as units; they are the frame-contained form of the Tier 3 buffer storage in tds-001.
Separation distances for H₂ and CO₂ are the layout driver, not the frame count.
Tiering (Architect direction, 2026-11-02: "we will tier the tanks"). Tanks are tiered two-high on the pad on their ISO 1161 corner castings with twist-locks, in service, piped from a manifold at grade with flexible drops to the upper unit:
| Unit | Fuel cell | Basis |
|---|---|---|
| CO₂ T50, water, condensate and DI T11 | two-high | ISO 1496-3 tank frames are rated for tiering loaded; two-high in service is the common terminal practice and keeps the upper manway reachable from a fixed platform |
| N₂ T75 cryogenic | at grade | vacuum-insulated shell, vent line and fill connections at one end; kept at grade for the fill tanker |
| H₂ MEGC | at grade | tube bundles with valve cabinets and the black-start line; at grade for connection, inspection and separation; tiering is OPEN with the hydrogen-code table |
| Solids bulk units | two-high in the hall | handled as frames; the upper unit is the empty swap |
Three-high is possible for the CO₂ units where the pad slab allows, and would halve the pad again; it is not drawn because the upper manway then needs a crane for every inspection. Tiered pairs turn over together: the full upper and lower unit are swapped as a pair by the off-taker's truck.
7. Count and footprint [INFERRED]
| Group | Frames | ISO tanks |
|---|---|---|
| Pregenesis™ | 10 | — |
| Regenesis™ (locked) | 13 | — |
| Regenesis MAX™ | 14 to 16 (PEM) / 10 to 12 (SOFC) | — |
| Energy and utilities | 20 to 24 | — |
| Tanks and bulk | — | 14 to 23 |
| Per Module | 57 to 63 | 14 to 23 |
At 30 m² per 40 ft frame plus access and separation, a Module is roughly 0.7 to 1.0 ha. York at 19 acres (7.7 ha) holds the initial 4 Modules with the building; the 1,000 and 2,000 TPD phases do not fit on that site in this form.
8. What this definition reopens
PowerBlock sizing per Module (8 → 12 to 15 MW) and the PEM lock; Regenesis MAX™ roster; the dried-feed buffer as frame or silo; the Pregenesis™ moisture target and eddy-current separation; D-MCR-FLOW-01, D-46; the steam topping turbine in the QBR frame specification; CO₂ off-take at York; the expanded-phase land at York; the Line tag scheme. None is ruled here.
9. Operating posture — 50 percent of ultimate capability, load-following (Architect, 2026-11-02)
Direction. The two-Line Module's 100 TPD is 50 percent of its ultimate capability of 200 TPD. It is run like a data centre: target utilisation 50 percent, with the ability to follow loads up and down. [RULED — direction, record pending]; consistent with D-LINE-02 (each Line at 50 percent of capability) and D-MCR-MOD-01 (power capped and modulated; installed above operating is the intended posture).
9.1 Ratings become two numbers on every frame
| Target (sustained) | Capability (envelope) | |
|---|---|---|
| Module | 100 TPD | 200 TPD |
| Line | 50 TPD | 100 TPD |
| Recyclotron™ | 25 TPD at 300 kW | 50 TPD at 600 kW (800 installed; 1.2 MW uprate ceiling) |
| Every process frame in §4 | the §2 and §3 figures | 2× those figures; this is already how §4 rates the Line frames |
| Pregenesis™ train | 100 TPD | 200 TPD, not the 150 shown in §4.1 — corrected to 200 |
9.2 What "follow loads" follows
The Module has no grid, so it does not follow an external demand. It follows three internal states:
| Signal | Store that buffers it | Response |
|---|---|---|
| Hydrogen inventory (the H₂ buffer level is the state variable, as battery charge is in a data centre) | H₂ MEGC frames, 1 h | throughput setpoint rises when the buffer is full, falls when it empties |
| Feedstock arrival and the dried-feed buffer | PRE-SIL, 24 h, plus the receiving bay |
throughput follows supply within the day |
| Frame availability | 2× frame ratings and the cross-ties of §5 | the Module holds 100 TPD with a frame out; it does not hold 200 TPD |
The control law is a setpoint on Module throughput between the Line floor (about 15 percent, set by the torch) and 200 TPD, driven by H₂ inventory first and feed inventory second, with the 24:1 reactor envelope and the Line turndown envelope (D-ACM-EMS-01, unwritten) as the rate limits.
9.3 What the posture does to the energy system — the sizing choice [INFERRED]
The plant's energy ratio is fixed: at 200 TPD it makes twice the hydrogen and draws twice the power, so the balance does not improve with utilisation. The fuel cells therefore have to be sized to a chosen point:
| Fuel-cell sizing | Per Module (SOFC basis, hydrogen-maximum closes at 100 TPD) | What it buys | Cost |
|---|---|---|---|
| To the 100 TPD target | 12 to 15 MW | the sustained point; excursions above 100 TPD run on the BESS and H₂ buffer for 1 to 2 h | lowest |
| To target plus swing, 130 to 150 TPD sustained | 16 to 22 MW | day/night and weekly load-following with margin; the same headroom is the failover reserve | +$10–20 M per Module |
| To capability, 200 TPD | 24 to 30 MW | sustained operation at the envelope; needed only if 200 TPD is ever a contracted rate | +$30–50 M per Module |
Recommendation: target plus swing, because the direction is to operate at 50 percent and follow, not to sell the envelope, and because the BESS and H₂ buffer cover the hours-scale excursions more cheaply than fuel cells do.
9.4 The constraint the posture exposes
Reaching 200 TPD on the Recyclotrons needs 600 kW per reactor on the carbon route, which is the ruled capability, but about 1.4 MW per reactor on the hydrogen-maximum route (organic sensible, bed steam-carbon and dissociation terms counted), which is above the 1.2 MW uprate ceiling. The 50-percent-and-follow posture is consistent with the carbon route across the whole envelope and with the hydrogen-maximum route only up to about 85 percent of capability. A mixed setting, water dial between the two, is the practical envelope and is a simulator sweep.
9.5 Redundancy, data-centre terms, as applied
| Tier | Where | Form |
|---|---|---|
| 2N | the two Lines' hot trains | each Line's frames at 2× target; no cross-tie hot |
| Headroom, not standby (Architect, 2026-11-03) | fuel-cell frames, BESS frames, dryers, gas-train pairs, cooling | every unit runs at 50 percent of its capability; one unit out leaves the Module at target on the others' headroom. No hot or cold standby units anywhere in the Module — the 50-percent capacity overhead is the failover. |
| N | torch skid per Line (two torches inside it), FDS, DC board sections | single frame, internal redundancy |
| Buffers | dried feed 24 h, H₂ 1 h plus start reserve, CO₂ 2 days, solids 2 days | ride-through and load-following |
9.6 Line dispatch — equal, unless failover or surge (Architect, 2026-11-03)
Rule. Both Lines run at the same setpoint at all times. The Module throughput setpoint of §9.2 is split equally between Line A and Line B, and within each Line equally between its two Recyclotrons. The split departs from equal in two cases only:
| Case | Dispatch | Limit |
|---|---|---|
| Normal, including every load-following move | both Lines at the same setpoint, from the Module floor (both Lines at their 15-percent floor, 30 TPD) to target (50 + 50) | neither Line is ever idled while the other runs |
| Surge above target | both Lines rise together, up to 100 + 100 TPD for the 1 to 2 h the BESS and H₂ buffer carry | the sustained ceiling of §12.7; the reactor uprate ceiling on the hydrogen-maximum setting |
| Failover, one Line's hot train out | the other Line carries the Module alone on its 2× rating, up to 100 TPD | refractory and electrode life (§5); the Line returns to equal dispatch when the outage clears |
Why. Equal dispatch halves the thermal cycling and electrode duty on each hot frame compared with running one Line hard and one Line cold, keeps both refractories at temperature so failover is a setpoint change and not a start-up, shares the 2× headroom of §9.5 across both Lines so neither is near its envelope in normal service, and makes the two Lines' wear, inspection and change-out schedules identical. The cross-ties of §5 (dryers to FDS, cold-gas header, steam header, N₂ loop, bus) are what let the downstream trains see one Module while the hot trains run as two equal halves.
Consequences in this package. The Module floor is 30 TPD, not 15 (§15.1 and §15.5 corrected); the batch loads of §18 are also split equally where they are per-Line (the two MAX-GAS trains); the Line-level turndown envelope D-ACM-EMS-01 (unwritten) carries the rule.
10. Consolidated roster — combining equipment to cut frame count (Architect, 2026-11-02)
Rules applied: R1 (one shippable, FAT-certifiable unit within the transport envelope — limits OPEN, so a 40 ft envelope and ~30 t are assumed), R2 (co-package only what is co-located, shares utilities, fits the envelope together, and is kinetic-isolation compatible), R3 (ICDs only at the frame boundary, so every merge deletes ICDs), and D-FME-01-R10 (what was a frame becomes an Assembly inside a frame). [INFERRED] throughout; the Regenesis™ merges need a D-REG-SCOPE-02 amendment.
10.1 Pregenesis™: 10 → 7
| Combined frame | Assemblies inside | Why it combines | Note |
|---|---|---|---|
PRE-RCV receiving and separation |
ingest conveyor, weigh, ferrous magnet, eddy-current | one conveyor line, no heavy rotating mass | — |
PRE-SHR size reduction |
shredder, hammermill | same isolation class, one dust enclosure, one APS tie-in | ~30 t, at the envelope |
PRE-DRY ×2 |
paddle dryer, condensate return, dried-feed discharge | 2 × 50 % stays for failover | two 100 TPD-capable dryers do not fit one frame |
PRE-ADX admix |
VRM pulveriser, rotational mixer, EAF dosing on reflected power | one dust system, one feed path | — |
PRE-SIL ×2 |
live-bottom dried-feed buffer, 12 h | halves the buffer frames; the rest of the buffer is a site silo | needs the frame-or-silo ruling |
10.2 Regenesis™: 13 → 9 (requires amending D-REG-SCOPE-02)
| Combined frame | Assemblies inside | Why it combines | What it retires |
|---|---|---|---|
CBT-ISOFRT-REG-MCR ×4 |
Recyclotron™, its DC-DC HV converters, DI cooling | unchanged, converters already on the frame | — |
CBT-ISOFRT-REG-FDS ×1 |
feed distribution | unchanged | — |
REG-CRS ×2 (one per Line) |
Primary Cyclone, hot-gas booster, CRSRU vessel, two torches, chopper, N₂ regulation, torch cooling | all hot, all on one gas path, one cooling loop, one HVIL; the torch skid's own reason to be separate (electrode service envelope) is met by a service bay on the frame | PCY and PTS as frame types; ~30 t, at the envelope |
REG-QBR ×2 (one per Line) |
quench boiler, steam topping turbine-generator with rectifier, HRSG, candle filter | one gas path from 1,400 °C to 250 °C, one steam header, one pressure-part certification package; the boiler keeps its own stamp inside the frame | HRSG and filter as separate Regenesis MAX™ frames |
The Regenesis™ boundary (quench boiler outlet) is unchanged; the HRSG and filter inside REG-QBR
are the first Regenesis MAX™ assemblies and sit on a Regenesis™ frame, which R2 permits and the
protocol boundary does not forbid, since the boundary is a process point, not a frame edge.
10.3 Regenesis MAX™: 14 to 16 → 5 (PEM) or 3 (SOFC), plus product finishing
| Combined frame | Assemblies inside | Count |
|---|---|---|
MAX-GAS gas conditioning, per Line |
dry-sorbent acid-gas removal, two-stage shift (PEM only), membrane CO₂ separation | 2 |
MAX-H2C hydrogen and CO₂, per Line |
H₂ PSA with tail-gas return (PEM only), CO₂ liquefaction | 2 (PEM); with SOFC the liquefaction joins MAX-GAS and this frame is deleted |
MAX-CSP solids |
carbon/mineral separation, carbon black and char handling, bulk-bag station | 1 |
MAX-ACT, MAX-GRA product finishing |
activation, graphitization — not sized | 2, unchanged |
10.4 Energy and utilities: 20 to 24 → 15 to 21
| Combined frame | Assemblies inside | Count |
|---|---|---|
PWR-FCM fuel cells |
1.2 to 1.5 MW per 40 ft at SOFC density | 10 to 15 — the one group that does not compress |
PWR-BES |
5 MWh and 2 MW in one 40 ft, current product density | 1 |
NXS-ELC electrical and control |
1,500 VDC board, HVIL, zone-bus taps, 48 VDC, EMS and controllers | 1 |
NXS-THM thermal |
DI loop, steam header, condensate; dry coolers roof-mounted on the fuel-cell frames | 1 |
UTL utilities |
APS, water treatment, N₂ generator and loop compressors | 1 |
10.5 Result
| Group | Before | After | Rulings needed |
|---|---|---|---|
| Pregenesis™ | 10 | 7 | frame-or-silo for the feed buffer |
| Regenesis™ | 13 | 9 | D-REG-SCOPE-02 amendment: PCY and PTS become Assemblies in REG-CRS |
| Regenesis MAX™ | 14 to 16 | 5 (PEM) / 3 (SOFC) + 2 finishing | roster not yet drawn, so none |
| Energy and utilities | 20 to 24 | 15 to 21 | PowerBlock re-basing |
| Frames per Module | 57 to 63 | 34 to 44 | |
| Process frames excluding fuel cells and finishing | ~45 | ~22 | |
| ISO tank containers | 14 to 23 | 10 to 14 | CO₂ on-site buffer cut to 1 day with a committed off-taker; one water tank; solids into MAX-CSP |
| ICDs at frame boundaries | — | roughly halved | R3 |
10.6 What the merges cost
Two frames sit at the envelope limit (PRE-SHR, REG-CRS) and depend on the OPEN R1 numbers; a
30 t ceiling is assumed. Merging the torch onto the vessel frame puts the electrode service bay on a
frame that is hot in service, so change-out procedure and cooling-down time become a maintenance
constraint. The quench boiler frame carries a certified pressure part plus a turbine; its FAT is the
longest in the Module. Failover is unchanged: the cross-ties of §5 all sit at frame boundaries that
survive the merges.
11. FAT, insurability and the common interface set (Architect questions, 2026-11-02)
11.1 Can frames be FAT-tested and insured as units
Yes; it is what the ISO Frame is for. D-FME-01 makes the frame the serialized, FAT-certified, warranty-passported deliverable; the TDS Guarantee Conditionality Statement already makes FAT and the Unitized Warranty Passport conditions of every guarantee. What an insurer needs beyond that, per frame:
| Requirement | How the roster meets it |
|---|---|
| A certified unit with a test record | shop FAT against a standard test harness (§11.4), FAT record in the passport |
| Certified pressure parts | quench boiler, CRSRU shell, CO₂ and H₂ tanks carry their own stamps inside the frame; ISO tanks carry CSC plates and UN portable-tank codes |
| Hazardous-area classification | H₂ and CO frames classified at the frame boundary; HVIL and gas detection on the frame |
| No field fabrication | all site work is assembly: lift, set, connect at the interface panel; builder's-risk exposure is small |
| Transit certification | ISO 1161 corner castings, CSC-style plate on every frame, lifting per the EDP |
| A warranty holder | the ASI, per frame, per the TDS §18 register |
The exception to shop FAT, stated honestly. Hot frames can be fully FAT-tested only if the ASI has a
hot test bay: a 7 MW DC supply, an N₂ loop and a vapour simulant for REG-CRS; a steam circuit for
REG-QBR; a 1.6 MW supply and admix for a Recyclotron™ frame. Without such a bay those frames get a
cold FAT (pressure, vacuum, electrical, controls, interlocks, torch strike on N₂) and a hot SAT on site.
The insurer sees the difference; the TPGT in the TDS is the hot test. Recommend the ASI builds one hot
bay per hot frame type; it pays for itself at the second Module.
11.2 The common interface set — one kit, every frame a subset
Existing ASI families are kept; the ones the consolidated roster needs and does not have are marked NEW.
| Domain | Family | Spec | Carried on | Status |
|---|---|---|---|---|
| Electrical | ASI-ZBK-MPC |
1,500 VDC zone-bus tap, liquid-cooled busbar, 8 MW per zone | NXS-Z1 overhead | existing |
| Electrical | ASI-PBK-QC |
800 VDC device link ≤250 kW, Amphenol ePower-Lite, <3 m | NXS-Z1 drop | existing |
| Electrical | ASI-CTL-48 |
48 VDC controls bus | NXS-Z1 | NEW (D-48V-01 open) |
| Safety | ASI-HVIL |
hardwired interlock chain, physically separate tray | NXS-Z1 | existing practice, unnamed |
| Data | ASI-DAT-MOD-TCP |
Modbus TCP over shielded Cat6A | NXS-Z1 | existing |
| Thermal | ASI-THM-HT |
steam or oil 200–400 °C, 10–40 bar | NXS-Z2 | existing |
| Thermal | ASI-THM-LP |
process steam 3 bar from the topping turbines | NXS-Z2 | NEW |
| Thermal | ASI-THM-DI |
DI cooling 35/50 °C | NXS-Z2 | NEW |
| Thermal | ASI-THM-TR |
85–95 °C thermal recovery (fuel-cell coolant to dryers) | NXS-Z2 | existing stream, unnamed |
| Gas | ASI-H2-HPS |
H₂ high pressure | NXS-Z3 | existing |
| Gas | ASI-GAS-PRC |
cold dry process gas ≤2 bar, the cross-tie header after the HRSG | NXS-Z3 | NEW |
| Gas | ASI-GAS-N2 |
N₂ loop, 3–5 bar | NXS-Z3 | NEW |
| Gas | ASI-GAS-CO2 |
liquid CO₂ to tank | NXS-Z3 | NEW |
| Gas, hot | ASI-VAP-HT |
vapour 600 °C, 0.5 atm, Inconel flange with bellows; the one hot frame-to-frame connection (MCR → REG-CRS) |
adjacent, not overhead | NEW; today ICD-MCR-PCY-001, OPEN |
| Material | ASI-RFH-FLG |
Recyclotron Feed Header | NXS-Z4 | existing |
| Material | ASI-SOL |
solids: char, carbon black, mineral, by bulk bag or dense-phase line | NXS-Z4 | NEW |
| Material | ASI-APS-FLG |
APS capture duct | NXS-Z4 | existing |
| Water | ASI-WTR-001 |
process water | NXS-Z2 | existing |
| Mechanical | ASI-ISO-* |
kinetic isolation, by frame | frame base | existing |
| Mechanical | ISO 1161 castings, twist-locks | lifting, tiering two-high where mass allows | frame corners | standard |
Twenty families. Each frame type gets a Frame Interface Schedule: which families, how many of each, at which position on the interface panel. A frame with the right schedule connects to any Module.
11.3 Standardized controllers
One controller family for every frame, with: a standard I/O base and remote I/O; ISA 5.1 tags matching the SCADA tag list (EDP rule); a Modbus register map template per frame type; participation in the HVIL chain by hardwire, never by network; per-channel hardware arc detection on every microwave and torch frame, not SCADA; and a standard energy interface to the EMS — setpoint, turndown range, state, ramp limit — which is the D-ACM-EMS-01 deliverable in concrete form. The frame controller is FAT-tested against the same harness as the hardware.
11.4 Routing rule
All connections are frame to frame or overhead, no trenches: the NEXUS spine carries Z1 electrical
and data, Z2 thermal and fluid, Z3 gas, Z4 material and APS, with Z4 physically separate per
ARM-2026-002 §5.3. The only direct frame-to-frame connections are hot or gravity ones between adjacent
frames: vapour MCR → REG-CRS (ASI-VAP-HT), feed FDS → MCR (gravity and dense phase), solids out of
the hot frames. Every frame presents one interface panel at one end, position-coded by family, so
the spine drop is identical for every frame of a type and the shop test harness is a copy of the drop.
11.5 What this needs ruled
The eight NEW families and their connector choices; the hot FAT bay at the ASI; the interface-panel
position standard; ASI-VAP-HT closing ICD-MCR-PCY-001; and D-48V-01.
12. SOFC heat recovery (Architect question, 2026-11-02) [INFERRED]
12.1 How much heat, per Module, hydrogen-maximum setting
Fuel to the fuel cells about 21 MW LHV (H₂ plus CO); electric 12 to 13 MW at 60 to 62 percent; about 8 MW of heat: cathode air outlet 750 to 850 °C (~5 MW), anode outlet 800 to 900 °C (~2 MW, CO₂ and water with the unconverted fuel), fuel-cell enclosure losses (~1 MW). Usable high-grade heat 6 to 7 MW. At the mixed setting scale by the hydrogen made.
12.2 No afterburner — a specification requirement
Standard SOFC packages oxidise the 15 to 20 percent of unconverted anode fuel in a catalytic afterburner to heat the cathode air. That is oxidation equipment, contrary to the no-oxidation rule, and it would put oxygen into the CO₂ stream. The frame specification instead requires anode off-gas recycle to the anode inlet (system fuel utilisation above 95 percent) with cathode air preheated by recuperation from the cathode outlet; the anode outlet is then CO₂ and water, condensed to liquid CO₂ with no separation step. Capture-ready SOFC designs do this; it must be written into the RFQ because it is not the default.
12.3 Process heat first, then power
| Demand per Module, mixed setting | Thermal | Grade |
|---|---|---|
| Feed drying to 5 % | 0.7 MW | 100 to 150 °C |
| Bed steam, swept 0 to ruled range | 0.5 to 1.5 MW | 3 bar steam |
| Admix, feed and N₂ torch-gas preheat | 0.4 MW | 150 to 300 °C |
| CO₂ liquefaction | electric, not thermal | — |
| Process heat | 1.6 to 2.6 MW | |
| Left for power | 4 to 5 MW at 700 to 850 °C |
12.4 The steam cycle (supercritical CO₂ cycles dropped by the Architect, 2026-11-02)
| Steam cycle | |
|---|---|
| Form | HRSG on the SOFC cathode and anode outlets raising 40 bar, 400 °C steam into the same header as the quench boilers; one extraction-condensing turbine per Module; process steam by extraction at 3 bar; air-cooled condenser (no water) |
| Electric from the 4 to 5 MW | 1.2 to 1.5 MW at 25 to 30 percent on this scale |
| Plus the quench-boiler topping turbines | 0.4 MW |
| Frames per Module | HRSG and turbine-generator frame; air-cooled condenser frame or roof-mounted |
| Maturity | TRL 9, catalogue |
| ROM per Module | $2–3 M |
12.5 What it does to the balance, per Module (corrected 2026-11-02, later the same day)
With the SOFC fed unshifted syngas (H₂ plus CO, which recovers the shift loss), fuel cells at 62 percent, the gas train deleted, the quench topping turbines and the SOFC steam cycle:
| Setting | Loads | SOFC electric | Topping + steam cycle | Balance |
|---|---|---|---|---|
| Hydrogen-maximum | 13.3 MW | 11.8 MW | 0.4 + 1.3 MW | +0.3 MW |
| Mixed (midpoint) | ~11.5 MW | ~10.0 MW | 0.3 + 1.1 MW | about zero |
| Carbon route W1 | 9.8 MW | 8.2 MW | 0.15 + 1.0 MW | −0.5 MW |
The earlier "+2 MW" in this section double-counted; withdrawn. SOFC heat recovery brings the mixed setting to self-sufficiency and the carbon route to within 0.5 MW, which a calorific floor on the feed or 65 percent fuel cells closes.
12.6 Roster effect
Add PWR-HRS (SOFC heat recovery: HRSG, extraction-condensing turbine-generator with rectifier) and
PWR-ACC (air-cooled condenser) per Module, 2 frames. Module count 36 to 46 frames.
12.7 What size the Module can support [INFERRED]
The supply-to-load ratio is 0.95 to 1.08 whatever the throughput, so the ceiling is the first hard limit:
| Limit | Hydrogen-maximum | Mixed | Carbon route |
|---|---|---|---|
| Fuel cells sized target plus swing, 16 to 22 MW, at ~13 MW of load per 100 TPD | 120 to 165 TPD sustained | 140 to 190 TPD | 165 to 200 TPD |
| Recyclotron™ power envelope (600 kW cap, 1.2 MW uprate) | ~170 TPD (1.4 MW per reactor needed at 200) | ~185 TPD | 200 TPD |
| Hot-frame ratings | 200 TPD | 200 TPD | 200 TPD |
| Peaks above the sustained figure | 200 TPD for 1 to 2 h on the BESS and H₂ buffer | same | same |
| Sustained, with the chosen fuel cells | 120 to 165 TPD | 140 to 190 TPD | 165 to 200 TPD |
Fuel cells at the full 24 to 30 MW would lift every column to 200 TPD except the hydrogen-maximum reactor limit. For York: four Modules on 19 acres are 400 TPD at target and 480 to 660 TPD sustained on the same frames and the same land at the swing rating, 800 TPD at capability on the carbon route with full fuel cells. The 1,000 TPD phase is therefore partly reachable without more land; the 2,000 TPD phase is not.
13. Lucid drawing
The complete dual-Line Module is drawn in Lucidchart, two pages:
Carbotura 100 TPD Module - dual Line, frames, flows, balances v5 (2026-11-03, carbon-route design point) —
https://lucid.app/lucidchart/eafcad99-b7c2-4b74-9be4-ff110d0596c1/edit (document id
eafcad99-b7c2-4b74-9be4-ff110d0596c1). v5 carries the vocabulary rule (PWR-FCM fuel-cell frames,
the retired fuel-cell term banned in every sense), the carbon-route design point, no standby units, tiered tanks, graphitisation
as the deferrable load, and the heat-cascade balance row.
- Page 1, Module - frames and flows: five bands under the NEXUS spine (Pregenesis™; Regenesis™ Lines A
and B with the cold-gas and steam headers; Regenesis MAX™ with the solids bulk units; energy and
utilities; ISO tank containers). Process flow black, syngas green, steam dashed orange, DC blue, solids
brown, black start dashed pink.
- Page 2, Mass, energy, storage, utilities: the per-Module mass balance at both settings (§2), the energy
balance at the bus (§3 and §12.5), the buffer and product storage register (§6), and the utilities and
PowerBlock register (§4.4, §11.2).
Earlier versions v1 (39d803ba-…), v2 (6f18a703-…), v3 (4eb09684-…) and v4 (558f2e67-…, old labels) are retitled SUPERSEDED and kept.
14. Physical layout — three sprung halls, drive-through receiving [INFERRED, proposal]
Architect direction, 2026-11-02 (with the simulator's 3D plant view): everything is in a building, sprung structures; drive-through [receiving]; then: [receiving] and Pregenesis can be in a separate building, PowerBlock also, Regenesis and Regenesis MAX in the main hall; then: we will tier the tanks. The layout is therefore three clear-span tensioned-membrane halls per Module, in line, with 10 m fire gaps between them and the frames in rows along their length as the simulator shows them.
Drawn in Lucidchart as plot plan v6 at 20 px per metre:
Carbotura 100 TPD Module plot plan v6 - three sprung halls, feedstock receiving bay, tiered ISO tanks (2026-11-03) —
https://lucid.app/lucidchart/f4b0bfee-a0bd-4349-8168-6afe51c42056/edit (document id f4b0bfee-a0bd-4349-8168-6afe51c42056); v6 carries the
receiving-bay labels (brand.json terminology). v1 (open site), v2 (single hall), v3 (tanks at grade), v4 (old labels) and
v5 (retired receiving term) are retitled SUPERSEDED and kept. Footprints: 40 ft frame 12.2 × 2.44 m, 20 ft frame 6.1 × 2.44 m.
14.1 The three halls
| Hall | Contents | Size | Height | Notes |
|---|---|---|---|---|
| 1 Receiving + Pregenesis™ | drive-through receiving lane (6 m, roll-up doors on both long walls, interlocked as an airlock so the bay is enclosed while a truck discharges); 20 × 20 m feedstock receiving bay with push wall; PRE-RCV; two rows of 40 ft frames: PRE-SHR, PRE-DRY 1, PRE-SIL 1 and PRE-ADX, PRE-DRY 2, PRE-SIL 2 | 75 × 40 m | eave 7 m | dust and odour contained in one volume; the only hall trucks enter; loader works the floor |
| 2 Main: Regenesis™ + Regenesis MAX™ | FDS at the head; Line A north of the spine, Line B south, mirrored: MCR 1, MCR 2, CRS hot frame, QBR recovery frame per Line; MAX-GAS A and B, MAX-CSP, four solids bulk units, MAX-ACT, MAX-GRA | 75 × 50 m | ridge 15 m, eave 9 m | the only hall that needs the height for the 9 m Recyclotron™ frames; gable frame-swap doors; H₂ detection and relief vents at the ridge; powered extraction over the hot bays |
| 3 PowerBlock | 15 SOFC fuel-cell frames in two rows, long axis north–south; PWR-HRS, NXS-ELC, PWR-BES and NXS-THM, UTL as 40 ft frames at the west end | 50 × 40 m | eave 7 m | air-cooled condenser and fuel-cell dry coolers outside the south wall; the 1,500 VDC switch frame is here, so the bus leaves this hall to the other two |
| Tank pad (outside) | one column of two-high fuel cells nearest Hall 3: 2 × water T11, condensate over DI T11, N₂ T75 at grade, four pairs of CO₂ T50; two H₂ MEGC at grade in a dashed separation zone beside it | 18 × 50 m | — | tanks tiered per §6; truck access from the fire lane; distances OPEN |
Structure for all three: aluminium arches with tensioned membrane; nothing hangs from the membrane. The NEXUS spine, the Z4 feed tray, crane runways and hoists sit on free-standing steel racks inside. Floors are reinforced slab with frame pads on the 2.44 m module; the feedstock receiving bay is the only civil work beyond slab and pads.
14.2 What crosses the gaps
| Gap | Crossing | Form |
|---|---|---|
| 1, Hall 1 → Hall 2, 10 m | NXS-Z4 dried feed from PRE-SIL to the FDS; NEXUS spine (Z1 bus and data to Pregenesis, Z2 thermal for the dryers) | enclosed conveyor bridge on the north rack; spine on a pipe bridge over the centre aisle |
| 2, Hall 2 → Hall 3, 10 m | Z3 cleaned syngas header to the fuel cells and the cold-gas cross-tie; Z1 1,500 VDC bus from NXS-ELC to the Module; Z2 steam and condensate between QBR, HRSG and NXS-THM | pipe bridge over the centre aisle; the bus in its own tray with HVIL continuity across the gap |
The spine runs straight through all three halls on one rack line, so the routing rule of §11 (frame to frame or overhead, nothing in trenches) holds across the gaps as well.
14.3 Area
| Envelope | Dimensions | Area |
|---|---|---|
| Three halls in line with the two gaps | 220 × 50 m | 1.00 ha (halls 0.78 ha) |
| With tiered tank pad (18 × 50 m) and 6 m fire lane | 253 × 65 m | 1.64 ha per Module |
| Four Modules at York, halls side by side, shared fire lanes and one tiered pad | about 220 × 230 m | about 4.8 ha of 7.7 |
| Alternative form | Hall 3 parallel south of Hall 2, sharing the gap | 170 × 110 m, about 1.9 ha with lanes |
Four Modules fit at York in line; the alternative form is more compact in length but wider, and puts the gas and bus bridges across the long wall instead of the gable. The 1,000 and 2,000 TPD phases still do not fit on the site.
14.4 What the three-hall form changes in the design
- Fire separation by building, not by frame. The feedstock receiving bay (dust, loader fuel), the hot block (1,300 to 1,800 °C vessels, hydrogen) and the fuel cells (hydrogen, 700 °C plus) are in three volumes with 10 m gaps; each hall gets its own strategy (sprinklers over the floor and Pregenesis; extraction, H₂ detection and ridge relief in Hall 2; water mist or inert and H₂ detection in Hall 3).
- Only Hall 2 is tall. Halls 1 and 3 are standard 7 m eave structures; the 15 m ridge is bought once, for the Recyclotron frames.
- Weather class drops to indoor for every frame, removing frame roofs and cladding assumed in §11 and helping the R1 weight limit.
- Crane access from the aisles. Every frame is reachable by a mobile crane in a 6 m aisle through a gable door; the frame-swap rule in §5 holds without a gantry.
- The feed bridge is a new interface. The dried-feed conveyor across gap 1 is a Z4 link between halls, not between frames; it needs an enclosed, fire-stopped crossing and belongs in the interface set of §11 as a site item.
Everything here is a proposal pending the R1 envelope limits, the hydrogen separation table and a fire-code review of hydrogen and SOFC fuel cells under membrane roofs.
15. Operating envelope — throughput, power and utilities per Module [COMPUTED / INFERRED]
Architect question, 2026-11-03: what are the throughput and power ranges, what are the utilities ranges. Figures are per Module (two Lines), drawn from §2, §3, §9 and §12 and the Option C ledger; ranges run from the carbon route W1 to the hydrogen-maximum setting unless a row says otherwise. Everything scales with throughput from the 100 TPD column except the floors, which are set by the torch and the fuel cells.
15.1 Throughput
| Level | Module | Line | Recyclotron™ | Set by |
|---|---|---|---|---|
| Floor | 30 TPD (both Lines at their floor; equal dispatch, §9.6) | ~15 TPD, about 15 % of capability | 6 to 8 TPD | torch pilot arc and the N₂ loop minimum; the 24:1 reactor envelope allows lower |
| Target, sustained | 100 TPD | 50 | 25 at 300 kW (carbon) to ~700 kW (H₂-max, uprate) | D-LINE-02, the 50-percent posture |
| Sustained ceiling with fuel cells at target plus swing (16 to 22 MW) | 120 to 165 TPD H₂-max · 140 to 190 mixed · 165 to 200 carbon | half | 30 to 50 | fuel-cell capacity (§12.7) |
| Peak, 1 to 2 h on the BESS and H₂ buffer | 200 TPD | 100 | 50 at 600 kW (carbon); H₂-max limited to ~170 TPD by the 1.2 MW uprate ceiling | frame ratings and the reactor power cap |
| One Line out | 100 TPD on the remaining Line's 2× rating, duration limited by refractory and electrode life | 100 | 50 | §5 |
15.2 Power at the 1,500 VDC bus
| Item | At 100 TPD | At 200 TPD peak | Note |
|---|---|---|---|
| Recyclotrons (4) | 1.5 to 3.4 MW | 2.4 to 5.6 MW | carbon → H₂-max; 2.4 MW is the 600 kW cap × 4; H₂-max at 200 TPD exceeds the uprate |
| CRSRU torches (2 Lines), N₂ loop | 6.4 to 7.6 MW | 12.8 to 15.2 MW | 2 × 3.4 MW torches per Line; floor ~0.3 MW per Line |
| Booster, gas conditioning, CO₂ liquefaction, drives | 0.8 to 1.2 MW | 1.6 to 2.4 MW | gas train deleted on the SOFC basis |
| Pregenesis™, APS, controls, N₂ generator | 1.1 MW | 1.6 MW | partly fixed |
| Loads | 9.8 to 13.3 MW | 18 to 25 MW | |
| SOFC electric | 8.2 to 11.8 MW | up to the installed 16 to 22 MW | at 62 percent on syngas |
| Topping turbines + SOFC steam cycle | 1.15 to 1.7 MW | 2.3 to 3.4 MW | |
| Balance | −0.5 to +0.3 MW | the deficit above the sustained ceiling comes from the BESS and H₂ buffer | |
| BESS | 2 × 2.5 MWh, 2 × 1 MW | ride-through 1 to 2 h, pulse loads | |
| H₂ buffer | 2 MEGC, 1 to 1.6 t | 1 h of fuel-cell fuel plus one black start (600 kg) | |
| Bus floor (both Lines at their floor, 30 TPD) | ~3.5 to 4.5 MW | two torch pilots, one dryer, controls; fuel cells at ~20 percent turndown |
15.3 Utilities
| Utility | At 100 TPD | At 200 TPD peak | Form and note |
|---|---|---|---|
| Heat rejected to air | 6 to 10 MW | 12 to 20 MW | dry coolers on NXS-Z2 (3 to 5 MW), air-cooled condenser of the steam cycle (3 to 3.5 MW), torch cooling 0.75 to 1.3 MW per Line; no cooling towers, no water consumed |
| Steam | 40 bar / 400 °C from two quench boilers and the SOFC HRSG; process draw 25 to 50 t/d at 3 bar (1 to 2 t/h) | 50 to 100 t/d | drying 0.7 MW thermal, bed steam 0.5 to 1.5 MW (swept), preheats 0.4 MW |
| Water | net producer: 70 to 125 t/d made in the fuel cells, 25 to 50 t/d to steam, 20 to 75 t/d surplus product water | 140 to 250 t/d made | no raw-water intake at steady state; DI make-up only for the closed loops; fuel-cell water polished in UTL-WTR (125 t/d) |
| N₂ | loop 1,500 Nm³/h circulating (700 to 3,800 across the enthalpy sensitivity); make-up 80 to 150 Nm³/h, 2 to 4 t/d | loop 3,000 Nm³/h; make-up 4 to 8 t/d | membrane generator 100 to 200 Nm³/h, liquid T75 as backup |
| CO₂ out | 51 to 140 t/d liquid, −20 °C / 20 bar | 100 to 280 t/d | 0.3 to 0.7 MW electric for liquefaction, counted in the loads; 2 days in four tiered T50 pairs |
| Hydrogen | 7.8 to 14 t/d made and consumed internally | 16 to 28 t/d | never a product; buffer 1 h |
| Solids out | carbon 0 to 18 t/d; mineral 10.2 t/d plus admix purge; acid-gas sorbent product ~1 t/d | double | 2-day buffers in 20 ft bulk units |
| Admix recycle | 10 to 20 t/d internal | 20 to 40 | bottom solids or WTE-derived Enhancement Admix, 0 to 25 % |
| Compressed and instrument air, APS | process-capture basis, not sized | OPEN, with the APS sizing | |
| Controls | 48 VDC bus, redundant controllers | D-48V-01 pending |
15.4 Reading the ranges
- The ratio is fixed. Supply to load stays at 0.95 to 1.08 at every throughput, so the ranges above are a single line scaled by tonnes; the floors and the fuel cell ceiling are the only non-linear points.
- Water and heat are the two utilities that change sign. The Module makes water and rejects heat; it draws neither from the site at steady state. The site needs a product-water outlet (or a use for it) and air for the coolers, not a water supply.
- N₂ and CO₂ are the two that leave the fence: N₂ as a small make-up in, CO₂ as the one bulk gaseous product out, 51 to 140 t/d, which is the off-take question at York.
- The utility that is not yet sized is instrument and process air with the APS; it is carried OPEN.
15.5 Average applied power by tonnage [COMPUTED]
Loads at the bus and generation from the fuel cells plus the steam cycle, per Module, for each operating setting, both Lines dispatched equally (§9.6); fixed load 0.8 MW (controls, APS, one dryer idling, torch pilot arcs) plus a variable load per tonne; fuel cells capped at the 22 MW target-plus-swing installation; fuel-cell frames are modular, so there is no practical minimum. "With cascade" adds the heat-cascade credit of §16. Hydrogen-maximum rows above about 170 TPD and mixed rows above about 185 TPD exceed the Recyclotron™ uprate ceiling and are shown in parentheses.
| TPD | Carbon: load / gen / balance / with cascade | Mixed: load / gen / balance / with cascade | H₂-max: load / gen / balance / with cascade | Heat rejected before cascade, MW |
|---|---|---|---|---|
| 30 (floor, both Lines) | 3.5 / 2.8 / -0.7 / -0.5 | 4.0 / 3.4 / -0.6 / -0.3 | 4.6 / 4.1 / -0.5 / -0.1 | 1.8 to 3.0 |
| 25 | 3.0 / 2.3 / -0.7 / -0.5 | 3.5 / 2.9 / -0.6 / -0.3 | 3.9 / 3.4 / -0.5 / -0.2 | 1.5 to 2.5 |
| 50 | 5.3 / 4.7 / -0.6 / -0.2 | 6.1 / 5.7 / -0.4 / +0.1 | 7.0 / 6.8 / -0.3 / +0.4 | 3.0 to 5.0 |
| 75 | 7.5 / 7.0 / -0.5 / +0.1 | 8.8 / 8.6 / -0.3 / +0.5 | 10.2 / 10.1 / -0.1 / +1.0 | 4.5 to 7.5 |
| 100 | 9.8 / 9.4 / -0.4 / +0.4 | 11.5 / 11.4 / -0.1 / +1.0 | 13.3 / 13.5 / +0.2 / +1.6 | 6.0 to 10.0 |
| 125 | 12.1 / 11.7 / -0.4 / +0.6 | 14.2 / 14.2 / +0.1 / +1.4 | 16.4 / 16.9 / +0.4 / +2.2 | 7.5 to 12.5 |
| 150 | 14.3 / 14.0 / -0.3 / +0.9 | 16.9 / 17.1 / +0.2 / +1.9 | 19.6 / 20.2 / +0.7 / +2.8 | 9.0 to 15.0 |
| 175 | 16.6 / 16.4 / -0.2 / +1.2 | 19.5 / 19.9 / +0.4 / +2.4 | (22.7 / 23.6 / +0.9 / +3.4) | 10.5 to 17.5 |
| 200 | 18.8 / 18.7 / -0.1 / +1.5 | (22.2 / 22.8 / +0.6 / +2.8) | (25.8 / 25.2 / -0.6 / +2.0) | 12.0 to 20.0 |
Reading: the balance stays within ±0.7 MW across the whole range. Below about 50 TPD the fixed 0.8 MW dominates and every setting runs slightly negative (the BESS and H₂ buffer carry it, which is why the floor is a transient, not a dwelling point); from 75 TPD up the balance is a near-constant fraction of load (−4 to +4 percent); at the fuel-cell cap (22 MW, reached only by the hydrogen-maximum setting near 200 TPD) every added tonne is paid from the stores. With the heat cascade the carbon route turns positive from 75 TPD and the Module carries 0.4 to 3.4 MW of margin at 100 TPD and above for load-following, instead of running at zero.
16. The 6 to 10 MW of rejected heat — a cascade, not a cooler (Architect, 2026-11-03) [INFERRED]
Direction: we need to use the 6 to 10 MW of heat being vented, be smart about it, do not fall back on tradition. The tradition is a bottoming cycle and dry coolers. §12 already takes the high-grade heat (process heat first, then the steam cycle). What is still rejected is medium and low grade, and the smart uses of it are the ones that displace electric loads the Module already carries, because on a no-grid Module a megawatt of load displaced is worth more than a megawatt of heat recovered.
16.1 Where the rejected heat is, per Module at 100 TPD
| Stream | Grade | MW | Today |
|---|---|---|---|
| SOFC cathode air after the recuperator and HRSG | 150 to 250 °C | 1 to 1.5 | cathode air outlet, recuperated |
| SOFC fuel cell coolant and enclosure loop (NXS-Z2) | 85 to 95 °C | 3 to 5 | dry coolers |
| Steam-cycle condenser | 50 to 60 °C | 3 to 3.5 | air-cooled condenser |
| Torch and power-electronics cooling | 35 to 50 °C | 1.5 to 2.6 | dry coolers |
| Total | 6 to 10 (overlaps at the extremes) |
16.2 The cascade, ranked by electric value
| # | Use | Heat taken | Grade needed | Electric displaced or made, per 100 TPD | Why it is not tradition |
|---|---|---|---|---|---|
| 1 | Absorption refrigeration for CO₂ liquefaction (ammonia–water, −25 °C evaporator) and for BESS and power-electronics cooling | 1.2 to 2.8 MW | 90 to 150 °C: fuel-cell coolant plus the cathode tail | 0.3 to 0.7 MW (the whole liquefaction compressor load) | turns the largest electric utility load into a heat load; the CO₂ product becomes free to liquefy |
| 2 | N₂ torch-gas, admix and dried-feed preheat to 300 to 500 °C from the cathode tail | 0.3 to 0.5 MW | 150 to 500 °C | 0.15 to 0.3 MW (torch electric at 58 percent to gas) | every joule put into the plasma feed gas thermally is a joule the torch does not have to make |
| 3 | Anode outlet as Recyclotron™ bed gas (chemistry lever, simulator sweep): 850 °C CO₂ and H₂O into the bed drives C + CO₂ → 2 CO and C + H₂O → CO + H₂ | up to 2 MW sensible plus the reactants | 800 to 900 °C | shifts energy from the magnetrons to the fuel-cell outlet; moves the carbon/hydrogen split toward hydrogen | uses the heat and the CO₂ chemically, inside the fence; it consumes carbon, so it is a setting, not a default |
| 4 | Organic Rankine cycle on what is left of the 85 to 95 °C loop | 2 to 3 MW | 85 to 95 °C | 0.2 to 0.3 MW at 8 to 10 percent | the traditional item, kept because it is cheap on this grade; last in the cascade, not first |
| 5 | Thermal storage (hot-water or packed-bed, 90 to 400 °C, 10 to 20 MWh) between the HRSG and the turbine | buffers, does not consume | — | makes the steam cycle's 1.2 to 1.5 MW dispatchable against the H₂ inventory | the data-centre posture needs a dispatchable source; this is the cheapest one on site |
| 6 | Feed pre-conditioning: warm air from the condenser through the 24 h dried-feed buffer and under the receiving-bay slab | 0.2 to 0.3 MW | 50 to 60 °C | 0.1 MW off the dryers; frost-free receiving bay | the lowest grade finds its only useful sink in the feed |
| 7 | Sprung-hall heating in winter (York), unit heaters on the 85 °C loop | 0.5 to 1 MW seasonal | 85 °C | no electric heating of three halls | the halls are the one new heat sink the building decision created |
16.3 What the cascade does
| Carbon route | Mixed | Hydrogen-maximum | |
|---|---|---|---|
| Electric displaced or made, per 100 TPD | 0.8 MW | 1.1 MW | 1.4 MW |
| Balance of §12.5 | −0.5 MW | ≈ 0 | +0.3 MW |
| Balance with the cascade | +0.3 MW | +1.1 MW | +1.7 MW |
| Heat still rejected | 4.5 MW | 6 MW | 7.5 MW, at lower grade |
The carbon route closes without a calorific floor on the feed, and every setting carries margin for load-following. The heat is still rejected in the end, as all heat is; the point is that it is rejected after it has done the liquefaction and the preheating that electricity was doing.
16.4 Roster and rulings
PWR-HRSgains the absorption chiller and the thermal store;MAX-CO2loses its compressor (liquefaction by absorption) — net zero frames.NXS-Z2becomes a cascaded loop (95 → 60 → 40 °C) rather than one dry-cooler circuit.- Item 3 is a chemistry setting for the simulator sweep commissioned by the decision form (Q2); it touches the carbon product and is not adopted here.
- Hall heating is a specification line for the three halls.
- No hot standby (Architect, 2026-11-03): every frame runs at 50 percent of its capability and the headroom is the failover; nothing is held warm and idle. The hot FAT bay at the ASI is a test bay, not a standby, and is unaffected.
The same tables are rendered as a standalone page, OPERATING_ENVELOPE.html in this folder (not linked
from the portal sidebar, not deployed).
17. Downstream to RC3 — what the Module does and does not include (Architect question, 2026-11-03) [INFERRED]
Question: have we included downstream processes to RC3? No. This definition, its balances (§2, §3,
§15) and the plot plan stop at the Module boundary set by the brief: carbon black and bed char,
OmniCrude™ Mineral Phase, liquid CO₂, product water, hydrogen as internal fuel. MAX-ACT and MAX-GRA
are rostered as placeholders "not sized" (§4.3). The RC3 tier of the RevCon™ ladder (Optimized
Circular Materials, the catalog's bankable baseline: 26 products, about 69.4 TPD per 100 TPD: the 80.6 TPD and 30 products of the catalog session's note of 2026-09-08, less the four aromatics products and their 11.25 TPD, which left the catalog at Release 126) needs finishing trains that are not in the roster, the power balance or
the halls.
17.1 RC3 floor by family, and where the Module stops
| Family | RC3 products | Module stream today | Finishing to RC3 not yet rostered | Added load per Module at 100 TPD |
|---|---|---|---|---|
| CRB carbon | CRB-006, 007, 008 high-purity graphite, 019 | pristine carbon black 8.9 t/d from the candle filter (vapour-derived, per the 2026-08-27 ruling); bed char 9.4 t/d | graphitisation of the pristine carbon (continuous induction or Acheson, 2,800 °C, 3 to 5 kWh/kg) → MAX-GRA; steam activation of char (900 °C) → MAX-ACT; classification and pelletising |
1.1 to 1.9 MW electric (graphitiser) + 0.3 to 0.5 MW thermal |
| MTL metals and REE | MTL-010, 012, 013, 014, 015, 033, 050 | Mineral Phase 10.2 t/d, ferrous and non-ferrous removed in Pregenesis™ | doré, REE-oxide and minor-metal concentrates: leach, solvent extraction, precipitation (MTL-CON-A/B/C in the catalog's terms); 2 to 3 frames, reagents, 20 to 40 t/d water |
0.3 to 0.5 MW |
| GLS glass | GLS-005, 006, 007, 012 | in the Mineral Phase | optical and density sort, cullet wash, silica polish; 1 frame | 0.1 MW |
| GAS industrial gases | GAS-006, 007, 008, 016, 017 | liquid CO₂ 51 to 140 t/d (an RC2/RC3 gas product in its own right); N₂ from a membrane generator for the loop only | the catalog's GAS products are air-separation products, drawn from air not feedstock; an ASU frame, 100 to 300 Nm³/h class | 0.3 to 0.6 MW |
| WTR water | WTR-004, 005, 006 and WTR-FC-001 fuel-cell water | 20 to 75 t/d surplus product water; UTL-WTR polishes 125 t/d of fuel-cell water |
polishing to the RC3 grades is a membrane and resin addition inside UTL-WTR |
0.05 MW |
| MTL minerals (MIN merged) | MIN-003, 004 | Mineral Phase bulk in MAX-CSP |
grading and bagging; largely included | — |
| Total | 26 products | 6 to 9 frames, one of them hot (graphitiser) | 2 to 3.5 MW electric, 0.5 to 0.8 MW thermal |
17.2 What that does to the balances
| Carbon route | Mixed | Hydrogen-maximum | |
|---|---|---|---|
| Balance with the heat cascade (§16.3) | +0.3 MW | +1.1 MW | +1.7 MW |
| RC3 finishing load | −2.0 to −3.5 MW | −1.5 to −2.5 MW (less carbon) | −0.8 to −1.2 MW (no graphite: there is no carbon) |
| Balance with RC3 finishing | −1.7 to −3.2 MW | −0.4 to −1.4 MW | +0.5 to +0.9 MW, but no CRB products |
Two levers close the carbon route again:
- Graphitisation is the Module's deferrable load. It is batch, it tolerates interruption, and its product keeps. Run it when the H₂ inventory is high and stop it when it is low: it is the natural "follow loads" sink of §9.2, the one the data-centre posture was missing. Sized at 2× average and run half the hours, it draws the fuel-cell margin that §15.5 shows above 100 TPD instead of new fuel cells.
- The graphitiser is a heat source for the cascade, not only a load: it rejects most of its input above 1,000 °C, of which 0.8 to 1.2 MW is recoverable to the 40 bar header, 0.25 to 0.35 MW electric back through the steam cycle.
With both, the carbon route sits at about −1 MW with the full RC3 slate, which 65-percent fuel cells or a calorific floor on the feed closes; the mixed setting closes on its own.
17.3 The conflict to rule on
The dissociation direction (hydrogen and carbon priority; hydrogen as internal fuel) and the RC3 catalog pull in different directions on two families:
| Family | Share of gross elemental value (catalog, York basis) | Under hydrogen-maximum | Under the carbon route |
|---|---|---|---|
| CRB, graphite and the RC4 products it feeds (graphene oxide, spheroidised graphite: ~$85 M/yr at 400 TPD in the catalog session's figures) | 34 % | gone: the carbon goes to the fuel cells as fuel | kept, 18 t/d |
| ARM, BTX and derivatives | 14 % | gone: reformed to C and H₂ | gone, by ruling (2026-11-03): dropped from the product scope at every setting |
The hydrogen-maximum setting therefore removes about half of the catalog's gross elemental value to close an energy balance that the carbon route plus the heat cascade can close by other means.
Ruled by the Architect, 2026-11-03: "Yes, carbon route." The carbon route W1 is the design point;
hydrogen-maximum is the energy-emergency setting only. Amended the same day, "Yes, drop
aromatics": the ARM family is dropped from the Module's product scope (retired catalog-wide at Release 126); the CRSRU runs at full
dissociation severity at every setting; no aromatic pass-through setting in the simulator sweep; the
trace cold-gas condensate is a return-to-feed stream through the separator of §19, not a product; the
aromatics' carbon and hydrogen report to carbon black and hydrogen. Consequences carried in this package: §1 operating
setting; §3 and §15.5 read on the carbon-route column; the fuel cells stay sized at target plus swing
(16 to 22 MW) because the emergency setting still has to run; graphitisation is rostered as the
deferrable load; the RC3 finishing frames of §17.1 go to the Doc Portal for D-FME-01. The Q2 record
(decision form, operating setting) is amended in ARCHITECT_ANSWERS_2026-11-02.md.
17.4 What changes if RC3 finishing is included
- Roster: +6 to 9 frames (graphitiser, activation, carbon classification, three hydromet frames, glass sort, ASU, water polish), Module count 42 to 55.
- Halls: the finishing frames fit in Hall 2's MAX bays with a 15 m extension, or in a fourth hall (finishing, 50 × 40 m) between Hall 2 and Hall 3 on the spine; the graphitiser is a hot frame and wants the Hall 2 extraction.
- Interfaces: reagent supply and spent-reagent return (hydromet) are a new utility family; the ASU adds air intake and vent lines.
- Product storage: finished RC3 products in 20 ft bulk units and big-bag frames, 2 days, on the tiered pad or in Hall 2.
- The catalog session owns the product definitions and yields; mapping to frame IDs is the Doc Portal's under D-FME-01. This section is the flag, not the ruling.
17.5 Refining lines defined, by family, and the RC tier each reaches (Architect question, 2026-11-03) [INFERRED]
The five are the catalog's five families, each on its own refining line (Deployment Architecture Canon §7.10 as rewritten at Release 126): Water, Gas, Carbon, Metal (minerals merged) and Glass. Aromatics, dropped from the Module by ruling on 2026-11-03, left the catalog at Release 126. "Defined" means a frame in the roster of §4 or §10 with a rating; "placeholder" means rostered and not sized. RC tiers follow the catalog session's entry-point note of 2026-09-08; the product-ID mapping is the catalog session's to confirm.
| Family | Refining line defined in this package | Product it makes | RC tier reached | What RC3 needs |
|---|---|---|---|---|
| CRB carbon | MAX-CSP separation and bagging of pristine carbon black (candle filter) and bed char; MAX-ACT activation and MAX-GRA graphitisation as placeholders |
carbon black CRB-002; bed char CRB-001 | RC2 (carbon black), RC1 (char) | graphitisation sized (MAX-GRA, 1.1 to 1.9 MW, the deferrable load) → high-purity graphite CRB-008 RC3, which feeds the RC4 graphene and spheroidised products; activation sized → CRB-003 RC2 and CRB-020 RC4 |
| MTL metals and minerals (MIN merged) | PRE-SEP ferrous magnet and eddy-current; MAX-CSP density and magnetic separation of the Mineral Phase; grading and bagging |
recovered ferrous and non-ferrous MTL-001/002; mineral aggregate and SCM MIN-003/004 | RC1 for metals; RC3 for the mineral aggregate and SCM, which is the one RC3 reached today | doré, REE-oxide and minor-metal concentrates (leach, solvent extraction, precipitation; 2 to 3 frames, 0.3 to 0.5 MW) → the seven MTL RC3 products |
| GLS glass | none; glass stays in the Mineral Phase | glass feedstock GLS-001 at best | RC1 | optical and density sort, cullet wash, silica polish; 1 frame, 0.1 MW → GLS-005/006/007/012 |
| GAS industrial gases | MAX-GAS liquefaction of the SOFC anode-outlet CO₂ (by absorption refrigeration on recovered heat, §16); membrane N₂ for the loop only |
liquid industrial CO₂, 51 to 140 t/d | RC2, industrial grade (tier to be confirmed by the catalog session); not the RC3 GAS products, which are air-separation products | an ASU frame (0.3 to 0.6 MW) for GAS-006/007/008/016/017; CO₂ purification to beverage or medical grade if an RC3 CO₂ product is wanted |
| WTR water | UTL-WTR 125 t/d polishing of fuel-cell water (the SOFC anode outlet condensate) and product water; membrane and resin polish per §17.1 |
fuel-cell water WTR-FC-001; product water | RC3 with the polish; RC1 without | nothing beyond the polish already in §17.1 (0.05 MW); WTR-FC-002 semiconductor grade is a 97-percent-yield RC4 pull-in |
Reading. Of the five families, the package defines refining to RC3 for water and the mineral
aggregate; to RC2 for carbon black and CO₂; and to RC1 for metals and glass.
The carbon line is the one that matters: it is the only family where the RC3 step (graphitisation) is
already on the roster as a placeholder, carries most of the catalog's value, and is the Module's
deferrable load. Sizing MAX-GRA and MAX-ACT moves CRB from RC2 to RC3 and opens the RC4 carbon
products; the hydromet, glass-sort and ASU frames are the rest of the 6 to 9 frames of §17.1.
18. Batchable loads and parasitic energy (Architect question, 2026-11-03) [INFERRED]
Question: what else can we batch to modulate power, what parasitic energy can we harvest. Per Module at 100 TPD on the carbon-route design point. The short answer: about a third of the electric load can be moved within the day, which is the modulation lever that matters; the parasitic heat pool is 1.4 to 2.5 MW more than §16.1 counts, but it is low grade and worth a few hundred kilowatts, not megawatts.
18.1 Deferrable loads, ranked by the swing they give
| # | Load | Average MW | Buffer that lets it batch | Batch window | Swing available |
|---|---|---|---|---|---|
| 1 | Graphitisation of the pristine carbon (§17) | 1.1 to 1.9 | product keeps; 2-day carbon buffer | hours to days | the whole load, sized at 2× and run half the hours: up to 3.8 MW |
| 2 | Shredder and hammermill (PRE-SHR), already a 16-hour duty at 200 TPD capability |
0.3 to 0.5 | 24 h dried-feed buffer (PRE-SIL) plus the receiving bay |
hours | 0.6 to 1.0 MW when run at full rate in the H₂-rich hours |
| 3 | Hydromet metals finishing (§17, leach, SX, precipitation) | 0.3 to 0.5 | Mineral Phase 2-day buffer; liquor tanks | days | the whole load |
| 4 | CO₂ liquefaction, where it stays electric | 0.3 to 0.7 | a low-pressure CO₂ gas holder gives 1 to 2 h; with absorption refrigeration (§16) it becomes thermal and batches against the thermal store instead | 1 to 2 h | 0.3 to 0.7 MW |
| 5 | H₂ buffer compression to the 250 bar MEGC (only the buffer flow is compressed; the fuel cells take low-pressure H₂) | 0.15 to 0.3 | the buffer itself | hours | the whole load, and it is the natural sink when H₂ inventory is high |
| 6 | Admix pulveriser (PRE-ADX VRM) |
0.15 to 0.25 | 2-day admix buffer | days | the whole load |
| 7 | N₂ generator (membrane) | 0.1 to 0.2 | liquid T75 and the loop receiver | hours | the whole load |
| 8 | Carbon activation, classification, pelletising | 0.1 to 0.2 | 2-day solids buffers | days | the whole load |
| 9 | Water treatment and DI polishing (UTL-WTR) |
0.05 to 0.1 | T11 tanks, 1 day | hours | the whole load |
| 10 | Dry-cooler and condenser fans | 0.2 to 0.4 | none; but ambient sets the duty, so the condenser gives more at night and the fans draw less | continuous | ±0.1 MW, and it argues for night batching |
| Deferrable within the day | 2.7 to 4.9 MW of a 9.8 MW load | 25 to 40 percent of load movable, hours-scale |
Items 1 and 3 do not exist until RC3 finishing is rostered (§17); without them the deferrable share is 1.3 to 2.4 MW, 13 to 25 percent, which is still more than most industrial plants can offer and is why the Module can be run like a data centre at all.
18.2 The modulation hierarchy that results
| Timescale | What moves | Range | Signal |
|---|---|---|---|
| Seconds | BESS (2 MW, 5 MWh); fan speeds | ±2 MW | bus voltage, HVIL |
| Minutes | Recyclotron throughput and the torches that follow the vapour (the 24:1 reactor envelope, the Line floor at 15 percent) | 5 to 7 MW between the Line floor and target | H₂ inventory first, feed inventory second (§9.2) |
| Minutes to an hour | SOFC fuel cells, electrochemically fast but thermally limited to about 2 to 5 percent per minute; the steam cycle via the thermal store (§16) | 3 to 5 MW | H₂ inventory |
| Hours | the deferrable loads of §18.1 | 2.7 to 4.9 MW | a day-ahead schedule against the H₂ and feed inventories and the ambient forecast |
| Days | feed buffer (24 h), admix, solids and CO₂ buffers (2 days) | throughput ±20 percent across the week | feedstock arrivals |
The control law of §9.2 gains one line: batch loads run when the H₂ buffer is above its setpoint and stop when it is below, before the throughput setpoint is touched, so the reactors and torches see the slowest and smallest excursions.
18.3 Parasitic energy not yet in the ledger
Heat the Module makes as a by-product of doing work and currently sends to the dry coolers without being counted in §16.1:
| Source | Grade | MW at 100 TPD | What it is worth | Harvest |
|---|---|---|---|---|
| Magnetron anode cooling, Gen 1 at 60 to 70 percent efficiency, 4 reactors | 50 to 70 °C | 0.4 to 1.0 | feed pre-conditioning, hall heat; too cool for the chiller unless the return is run at 80 °C, which costs magnetron life | one loop with the torch cooling; feed-buffer warm air and the receiving-bay slab |
Dryer vapour latent heat: 19 t/d of water evaporated in PRE-DRY |
100 °C condensing | 0.5 | the one parasitic stream warm enough for the absorption chiller; or hall heat in winter | condensing coil on the dryer off-gas to the 85 to 95 °C loop; mechanical vapour recompression does not pay on a steam-rich Module |
| DC-DC converters, drives, BESS round trip (2 to 4 percent of 10 to 13 MW) | 40 to 60 °C | 0.2 to 0.5 | low; same sink as the magnetrons | liquid-cooled electronics on the same loop |
| Reflected microwave power in the circulator loads, EAF 0.10 to 0.15 | 60 °C | 0.1 to 0.3 | best harvested by not making it: the reflected-power tuning loop of RECYCLOTRON_OPTIMIZATION.md |
tuning first; dummy-load coolant to the same loop |
| Hot solids: bed char and Mineral Phase leaving the reactors at 600 °C, carbon black at 250 °C | 250 to 600 °C | 0.15 | small but high grade: a solids cooler preheats the admix or the N₂ torch gas | screw cooler on the bottom-solids outlet |
| H₂ buffer let-down, 250 bar to fuel-cell pressure through an expander | — | 0.02 to 0.05 | not worth a frame | leave |
| Thermoelectric generators on the hot-frame shells | 200 to 300 °C | 0.03 to 0.05 at 3 to 5 percent | not worth a frame; the water-cooled wall already takes it | leave |
| Total new to the ledger | 40 to 100 °C | 1.4 to 2.5 MW of heat | about 0.15 to 0.3 MW electric-equivalent (drying offset, chiller feed, hall heat) |
Two honest notes. First, the parasitic pool is real but low grade: it roughly doubles the 40 to 70 °C
heat the Module has, and the only sinks for that grade are the feed, the halls and, through the
dryer vapour, the chiller. Second, the largest single "parasitic" item is not a heat stream but the
reflected microwave power and the water in the feed: the parasitic ledger of
RECYCLOTRON_OPTIMIZATION.md shows most of the microwave energy on as-received feed going to water
and inerts, which is why the Module dries to 5 percent and doses admix by the reflected-power loop.
Those two levers are worth more than every harvest in this table.
18.4 What this adds to the package
- §9.2 control law: the batch-load line.
UTL-CTLscope: a day-ahead batch scheduler against H₂, feed and ambient.NXS-Z2: one 50 to 70 °C loop collecting magnetron, electronics, BESS and torch cooling, feeding the feed buffer, the receiving-bay slab and the halls; a condensing coil on the dryer off-gas into the 85 to 95 °C loop.REG-MCRbottom-solids outlet: a screw cooler with the heat to admix or N₂ preheat.- A CO₂ gas holder (1 to 2 h) if liquefaction stays electric; none if it goes to absorption.
19. Oils caught through oil-water separation (Architect question, 2026-11-03) [INFERRED]
Question: any oils we catch through OWS? Yes, in two places, and on the closed-loop basis the oil caught is returned to the process as feed, not sent out as a residue.
19.1 Where oily water arises, per Module at 100 TPD
| Stream | Source | Flow | What is in it | Oil caught |
|---|---|---|---|---|
| Dryer condensate | PRE-DRY paddle dryers evaporate 19 t/d of feed moisture at 100 to 150 °C; the condensing coil of §18.3 recovers the latent heat and condenses the vapour |
19 t/d | water with the steam-distillable organics of the feed: fats, oils and greases from the food fraction, terpenes, light hydrocarbons, dissolved VOCs | 50 to 300 kg/d of light oil and grease, floating; the one stream large enough to need a separator |
| Receiving-bay liquids | receiving-bay leachate from as-received feed, floor wash-down, the loader's area | 1 to 3 m³/d | leachate (organic acids, dissolved organics), suspended solids, fats, oils and greases, drips from the trucks and the loader | 5 to 30 kg/d |
| Drive-through lane and fire-lane drainage | rain on the lane through Hall 1 and the paved lanes | rain events | road hydrocarbons from trucks | trace; a standard interceptor |
| Cold-gas condensate | the quench and gas-conditioning train, on the dissociation basis | <1 t/d | trace aromatics (BTX, naphthalene) that survive the CRSRU; water | with aromatics dropped from scope (2026-11-03) this is a return-to-feed stream: through the separator, the organic phase to PRE-ADX, the water to the polish; the condensate T11 of §6 is its buffer |
| Machinery | shredder hydraulics, N₂ loop compressors, drives | none by design | specify oil-free compressors on the N₂ loop and the H₂ buffer; hydraulic units with drip trays | maintenance only |
19.2 Where the separator sits and what it does with the oil
| Item | Proposal |
|---|---|
| Separator | one coalescing-plate oil-water separator, 2 to 5 m³/h, with a sump and a dissolved-air flotation stage for the fats and greases, as an Assembly inside UTL-WTR (§4.4) with a collection sump and lift in Hall 1 under the dryers and the feedstock receiving bay; the lane interceptor is site drainage, outside the frames |
| Oil and grease caught | to the feed: the skimmed oil and the flotation float go to PRE-ADX with the admix and back into the Recyclotrons, where they are hydrocarbons like the rest of the feed and are dissociated to carbon and hydrogen; 50 to 300 kg/d against 81 t/d of dried feed is 0.1 to 0.4 percent and changes nothing in the balances |
| Water | to UTL-WTR polishing with the fuel-cell water and out as product water, or to the steam loop; the dissolved organics in the dryer condensate are the reason the polish of §17.1 has a biological or activated-carbon stage ahead of the membranes, with the activated carbon from MAX-ACT |
| Separator sludge and solids | to PRE-ADX with the oil; nothing leaves the fence from the separator |
| Near-zero accounting | the oil is feed returned, the water is product water; the separator has no outlet other than the process and the water register |
19.3 Roster and ruling
UTL-WTRgains the separator and flotation Assembly (no new frame); Hall 1 gains a sump and lift; the activated-carbon polish stage is a specification line tyingUTL-WTRtoMAX-ACT.- The dryer off-gas condensing coil (§18.3) is what makes the dryer condensate a liquid stream to separate rather than a vapour to vent; the two decisions go together.
- Oil-free compressors on the N₂ loop and H₂ buffer are a specification line for
REG-CRSandUTL. - The receiving-floor leachate collection is a site item for the Hall 1 slab design (§14.1).
20. Excess hydrogen — how much, and what to do with it (Architect question, 2026-11-03) [INFERRED]
Question: as we accumulate excess hydrogen can we not use it to increase capacities, or what is your call; a table of excesses and a matrix of uses. Standing rule: hydrogen is Island-Mode internal fuel, never a product (Engineering Doctrine Canon); nothing below sells, exports or derivatises it.
20.1 Table of excesses, per Module
Conversion used: 1 t of H₂ is 33.3 MWh LHV and about 20.6 MWh electric through the fuel cells at 62 percent; a 1 MW electric surplus for a day is therefore about 1.2 t of H₂ not needed.
| Setting, 100 TPD | H₂ made | Electric balance (§15.5, §16.3, §17.2) | H₂ surplus (+) or deficit (−) | Share of H₂ made |
|---|---|---|---|---|
| Carbon route, design point, no cascade | 7.8 to 8.9 t/d | −0.5 MW | −0.6 t/d | −7 % |
| Carbon route, with the heat cascade (§16) | 7.8 to 8.9 t/d | +0.3 MW | +0.35 t/d | +4 % |
| Carbon route, cascade, RC3 finishing on (§17.2, graphitisation as the deferrable load) | 7.8 to 8.9 t/d | about −1 MW | −1.2 t/d | −14 % |
| Mixed, cascade | ~11 t/d | +1.1 MW | +1.3 t/d | +12 % |
| Mixed, cascade, RC3 finishing on | ~11 t/d | about 0 | ≈ 0 | — |
| Hydrogen-maximum (emergency), cascade | ~14 t/d | +1.7 MW | +2.0 t/d | +14 % |
| At 200 TPD surge, carbon route, cascade | 15.6 to 17.8 t/d | +1.5 MW | +1.8 t/d | +11 %, for the 1 to 2 h the frames allow |
Within the day, under batch scheduling (§18): on the carbon route with the cascade and graphitisation sized at 2× and run 12 hours, the Module runs about +1.4 MW surplus in the off-hours and about −0.8 MW in the on-hours. Surplus accumulates at 70 kg/h for 12 hours, 0.8 to 1.1 t, and is drawn down in the next 12. The two MEGC buffer (1 to 1.6 t, §6) is therefore just large enough for the batch cycle and leaves nothing for black start or a surge; two more MEGC, tiered, give the 4 h buffer the batch posture wants.
Reading. The steady-state excess is a few percent of production in every column, and it is negative on the design point once RC3 finishing runs. The Module's supply-to-load ratio is fixed at 0.95 to 1.08 (§12.7), so an extra tonne of feed brings its own load with it: a 0.35 t/d surplus of hydrogen supports about 3 TPD more throughput, not 30. Excess hydrogen does not buy tonnage. It buys the things in the matrix.
20.2 Matrix of uses, ranked
| # | Use | H₂ it takes | What it yields | In fence, no oxidation, not a product | Verdict |
|---|---|---|---|---|---|
| 1 | Refining depth: electricity for the RC3 finishing loads (graphitisation 1.1 to 1.9 MW, hydromet 0.3 to 0.5, ASU, activation), run as the batch loads of §18 | the whole surplus and more | 1 t of surplus H₂ is 20.6 MWh, which graphitises 4 to 7 t of pristine carbon to high-purity graphite CRB-008 (RC3) and feeds the RC4 carbon products | yes | first call. The surplus is worth more as graphite than as anything else, and the sink is deferrable so it absorbs the surplus when it exists |
| 2 | Replenish the black-start reserve (600 kg, §6) from the Module's own hydrogen, instead of supplied H₂ | 0.6 t once, then top-ups | removes an external supply from the no-grid Module; the supplied reserve becomes a commissioning item only | yes | do it; the first 0.6 t of any surplus goes here |
| 3 | Derate the fuel cells: at a given electric output, run more frames at lower current density, consuming slightly more H₂ per kWh | 0.2 to 0.4 t/d at 100 TPD | fuel-cell efficiency 62 → 64 to 65 percent at the lower current density, and a longer life (degradation scales with current density); the data-centre "run at 50 percent" play applied to the PowerBlock | yes | do it with the headroom of §9.5; it turns a surplus into frame life |
| 4 | Extend the buffer to 4 h with two more tiered MEGC, and schedule the batch loads against it | 0.15 to 0.3 MW of compression (§18.1) | deeper load-following, a surge that outlasts the BESS, a black start that does not touch the reserve | yes | do it; it is the enabler of item 1 |
| 5 | Hydrogen as the Recyclotron™ bed carrier and sweep gas instead of N₂ (the recycled-H₂ carrier of RECYCLOTRON_OPTIMIZATION.md) |
circulates; not consumed | suppresses tar, cuts N₂ make-up and the inert fraction in the syngas, raises vapour quality to the CRSRU | yes | adopt as the carrier; it is a circulation, not a sink, and it is already in the optimisation file |
| 6 | Hydrogen as the CRSRU plasma gas instead of the N₂ loop (Gen 2) | circulates; joins the syngas | deletes the N₂ loop, the 27 percent inert fraction at the GPU, the N₂ generator and the T75; hydrogen plasma reforms harder than nitrogen plasma; electrode erosion in H₂ plasma is the risk to test | yes | Gen 2 test target alongside A2; D-65-C confirmed N₂ for the first Modules and this does not reopen it |
| 7 | Direct hydrogen reduction of the Mineral Phase oxides (iron, copper, nickel oxides at 700 to 900 °C) as the front end of the MTL finishing line | 0.1 to 0.3 t/d | metal from oxide inside the fence with water as the only by-product; lifts the MTL line from RC1 toward the RC3 refined metals with less hydromet reagent | yes | worth a line in the §17.1 hydromet frame; the catalog session to say which MTL products it reaches |
| 8 | Raise throughput | all of it | about +3 TPD per 0.35 t/d, because every tonne brings its own load | yes | not a use; the ratio is fixed |
| 9 | Catalytic hydrogen heaters for process heat | — | water only, but it is oxidation equipment and the fuel cell already does the job at twice the value | no | rejected |
| 10 | Ammonia from loop N₂, methane from captured CO₂ (Sabatier), hydrogenated products | — | marketed hydrogen derivatives | no: hydrogen as a product in disguise; methanation also returns captured CO₂ to a fuel | rejected under the hydrogen rule and the CO₂ capture basis |
| 11 | Export to a neighbouring Module through a facility H₂ header | pooled | at York, four Modules pool their surplus into one finishing hall (one graphitiser line at 4×), which is item 1 at facility scale | yes | the facility form of item 1; a NEXUS Z3 facility header is the interface |
| 12 | Grid, sale, pipeline | — | — | no | never |
20.3 The call — adopted by the Architect, 2026-11-03 ("Yes, adopt")
Excess hydrogen does not increase capacity in tonnes; it increases capacity in refining depth. Send it to the RC3 finishing loads as the deferrable load, with a 4 h buffer so the batch cycle and a black start both fit, and let the fuel cells run derated on the headroom in between. Use hydrogen as the Recyclotron carrier now and test it as the CRSRU plasma gas for Gen 2, which is a circulation gain rather than a sink. Replenish the black-start reserve from the Module's own hydrogen so the no-grid Module has no external energy supply at all after commissioning. Everything that makes hydrogen a product or a derivative, or oxidises it outside the fuel cell, stays rejected.
Roster effect, now carried in this package: 4 MEGC per Module (4 h buffer, §6 corrected); the H₂
buffer compressor rated for the batch cycle (0.3 MW, oil-free); the fuel cells dispatched derated on
the headroom of §9.5 (a control line for UTL-CTL beside the batch scheduler); the black-start
reserve replenished from the Module's own hydrogen after commissioning; hydrogen as the Recyclotron™
carrier gas (a specification line for REG-MCR and REG-FDS, from RECYCLOTRON_OPTIMIZATION.md);
hydrogen as the CRSRU plasma gas carried as a Gen 2 test target beside A2 in the D-65-C memo; a
facility Z3 H₂ header as a NEXUS interface item at York; the MTL hydrogen-reduction step as a line
in the §17.1 hydromet frame. Items 8 to 10 and 12 of §20.2 are closed as rejected.
20.4 Graphitisation batch cycle schedule (Architect question, 2026-11-03) [INFERRED]
Basis: carbon route design point, 100 TPD, both Lines equal (§9.6); pristine carbon black 8.9 t/d from
the candle filters; one continuous vertical induction graphitiser (MAX-GRA) at 2,800 to 3,000 °C,
residence 1 to 3 h, sized at 2× the average duty: 750 kg/h, 2.6 to 3.8 MW at the bus; the H₂
buffer at 4 MEGC (4 h); BESS 2 MW / 5 MWh for the block transients.
Why a block, not a cycle to cold. An induction graphitiser cycled from 2,800 °C to ambient every day destroys its graphite susceptor and insulation in months. The schedule is therefore one production block per day with the hot zone held at about 1,200 °C between blocks on 0.1 to 0.15 MW (4 to 5 percent of rated). That hold is the running state of a deferrable load, not a standby unit under §9.5: the graphitiser is the Module's batch sink and has no duplicate.
| Time | Block | Graphitiser | Other batch loads | Module balance | H₂ buffer |
|---|---|---|---|---|---|
| 22:00 to 06:00 | Production, first 8 h | 750 kg/h, 2.6 to 3.8 MW; feed from the 2-day carbon buffer | shredder off (22:00 to 06:00); hydromet off; dryers and reactors steady; fans at night duty | about −2.2 MW | discharging, 1.3 t over the block |
| 06:00 to 10:00 | Production, last 4 h, or stop early on the gate | as above | shredder on at 06:00 (0.6 to 1.0 MW at full rate) | about −2.8 MW | discharging to the 25 percent gate |
| 10:00 to 18:00 | Hold | 1,200 °C hold, 0.1 to 0.15 MW; lot cooling and classification | shredder on; hydromet day shift (0.3 to 0.5 MW); activation block 10:00 to 18:00 on steam | about +0.8 MW | charging |
| 18:00 to 22:00 | Hold | hold; next lot staged | shredder on to 22:00; hydromet off at 18:00 | about +1.4 MW | charging to the 60 percent gate |
Quota and block length are the control variables. The gate is in the §9.2 control law: a block starts at 22:00 if the H₂ buffer is above 60 percent and the dried-feed buffer above 12 h, and ends at 10:00 or when the buffer falls to 25 percent, whichever is first. The block length then sets how much of the day's carbon reaches RC3:
| Energy available for graphitisation | Block | Graphitised per day | Of the 8.9 t/d |
|---|---|---|---|
| Surplus of the design point with the cascade alone, +0.3 MW (7 MWh/d) | 3 h | 1.5 to 2 t | 20 percent; the rest leaves as carbon black at RC2 |
| Plus 65-percent fuel cells and the graphitiser's own heat recovery to the steam cycle (+0.4 and +0.3 MW, §17.2) | 7 to 8 h | 5 to 6 t | 60 to 70 percent |
| Full 12 h block, all 8.9 t/d to RC3 | 12 h | 8.9 t | 100 percent; needs about 1 MW more than the Module makes at 100 TPD: the calorific floor on the feed, or a Module running above target in the swing band (§12.7), where the same ratio gives the same deficit but the carbon buffer lets blocks be skipped on low-feed days |
So at 100 TPD on the design point the Module graphitises roughly two-thirds of its pristine carbon from its own energy and ships the rest at RC2, unless the feed carries the calorific floor. That is the honest position; §17.2 already carries the −1 MW.
Week. Six blocks and one 24 h maintenance window (susceptor inspection, lot QC), with the 2-day carbon buffer absorbing the gap. The block is the first load shed in surge and in Line failover (§9.6), and the hold state means it restarts in under an hour when the gate reopens.
Roster and control lines. MAX-GRA as a continuous vertical induction graphitiser, 750 kg/h,
hold state specified; its off-gas heat to the 40 bar header (§17.2); lot handling by the 2-day carbon
buffer and a classification step after cooling; the block gate and the hold setpoint in UTL-CTL's
batch scheduler (§18.4).
21. Overall energy Sankey and the feed-energy reconciliation (Architect request, 2026-11-03) [COMPUTED]
The Architect asked for one Sankey combining materials, energy and the utilities. The only basis that carries all of them is energy, so the combined diagram (HTML page, section 3, first figure) draws every mass stream at its chemical energy on the lower-heating-value basis and every utility at its heat or electric power, in MW, at the design point.
21.1 The closed ledger behind it, carbon route at 100 TPD with the cascade
| Node | In | Out |
|---|---|---|
| Recyclotrons™ | feed chemical 19.4; electric 1.5 | bed char 3.6; vapour 16.8; magnetron cooling 0.5 |
| CRSRU and quench | vapour 16.8; torch electric 6.4; preheat 0.4 | carbon black 3.4; syngas 13.2; quench heat and torch cooling 6.6 (3.7 recovered to steam, 2.7 cooling, 0.2 shell and solids) |
| Fuel cells | syngas 13.2 | electric 8.2; heat 5.0 |
| Heat pool and cascade | 5.0 + 6.6 + 0.5 + 0.8 (drives) + 1.1 (electronics) + 0.55 (dryer vapour) = 14.55 | process heat 1.1; electric 1.95 (steam cycle 1.0, topping 0.15, cascade 0.8); rejected to air 11.3 |
| 1,500 VDC bus | 8.2 + 1.95 = 10.15 | reactors 1.5; torches 6.4; gas conditioning and CO₂ 0.8; APS, controls, Pregenesis™ 1.1; margin 0.35 |
| Products | carbon 6.9 MW of chemical energy kept (char 3.6, carbon black 3.4); CO₂, water and Mineral Phase carry none |
Electricity put into the reactors and the torches is stored in the syngas as chemical energy by the endothermic dissociation, which is why the syngas (13.2) carries more than the feed's share after the carbon is taken out.
21.2 The finding
Closing the ledger needs 19.4 MW of feed chemical energy, which is 25 MJ/kg on the 66.1 t/d of
dry, ash-free organics. The reference feed of 00_DESIGN_BASIS_COMMON.md (DAF C57 H7.8 O32.9) sits
at 20 to 23 MJ/kg by the usual correlations. The energy ledger of §3 therefore assumes a feed 10 to
25 percent richer than the elemental basis supports, or equivalently it credits the hydrogen yield of
§2 in full while the oxygen in the organics takes some of that hydrogen to water in the CRSRU.
| Feed LHV, DAF | Feed chemical energy | Syngas to the fuel cells | Fuel-cell electric | Design-point balance with the cascade |
|---|---|---|---|---|
| 25 MJ/kg (the ledger as it stands) | 19.4 MW | 13.2 MW | 8.2 MW | +0.3 MW |
| 23 MJ/kg | 17.6 MW | 12.0 MW | 7.5 MW | −0.4 MW |
| 22 MJ/kg | 16.8 MW | 11.4 MW | 7.1 MW | −0.8 MW |
| 20 MJ/kg | 15.3 MW | 10.2 MW | 6.3 MW | −1.6 MW |
This is the calorific floor on the feed in numbers. The design point closes at +0.3 MW only if the feed carries about 25 MJ/kg DAF; at the reference 22 MJ/kg it is −0.8 MW before RC3 finishing and about −2 MW with it. The levers already in the package carry it: 65-percent fuel cells (+0.4 MW), the graphitiser's heat recovery (+0.3), the parasitic harvest (+0.15 to 0.3), and the feed specification itself (admix of char-rich recycled bottom solids raises the DAF heating value of the blend). It goes to the simulator sweep as the first thing to settle: the CRSRU zone's hydrogen yield against the feed's oxygen, which decides whether §2's hydrogen or §3's electric figure is the one to trust. Until then the carbon-route balance should be read as −0.8 to +0.3 MW, not +0.3.
22. Minimum product set — the Day-1 slate (Architect question, 2026-11-03) [RULED — direction, record pending]
Question: should we do a minimum set of products to deliver? We have not defined all the modules to handle metals, glass, etc.; we will probably be selling a concentrate. Yes, and the answer falls out of the roster as it stands: the Module as rostered delivers eight products, two of them concentrates, with no finishing frame added. Everything beyond the eight is a frame decision, and the first of those is the graphitiser.
22.1 The eight
| # | Product (catalog ID) | Tier | t/d at 100 TPD, design point | Made by | Form sold |
|---|---|---|---|---|---|
| 1 | Carbon black, pristine (CRB-002) | RC2 | 8.9 | candle filters on the quench outlet; MAX-CSP classification and bagging |
bulk bags or 20 ft bulk unit |
| 2 | Bed char (CRB-001) | RC1 | 9.4 | Recyclotron™ bottom solids after MAX-CSP density and magnetic separation |
bulk; part recycled as admix, the rest sold |
| 3 | Liquid CO₂, industrial (GAS-003) | RC2 | 51 to 71 | fuel-cell anode outlet, absorption liquefaction | tiered ISO T50, swapped with the off-taker |
| 4 | Ferrous (MTL-001) | RC1 | 2 to 7 (feed-dependent) | PRE-SEP magnet |
baled or bulk, to a steel mill |
| 5 | Non-ferrous metal concentrate (MTL-002, the catalog's MTL-CON concentrates) |
RC1 | 1 to 3 (feed-dependent) | PRE-SEP eddy-current plus the heavy fraction of the Mineral Phase from MAX-CSP density separation |
bulk bags, to a refiner on a payables basis |
| 6 | Mineral concentrate, aggregate grade (MIN-001) | RC1 | 6 to 8 | light fraction of the Mineral Phase, screened | bulk, to cement or construction |
| 7 | Pozzolanic SCM powder (MIN-002) | RC2 | 2 to 4 | fines of the Mineral Phase, milled in the admix VRM (PRE-ADX) |
bulk, to cement |
| 8 | Industrial DI water (WTR-FC-001) | RC3 | 20 to 75 | fuel-cell water through UTL-WTR polish |
tanker or pipe |
Hydrogen is made and consumed; it is not on the list and never will be.
22.2 Why concentrates, not metals and glass products
- Scale. At 100 TPD the refined-metal volumes are tiny: chromium 0.5 t/d, silver 0.75 kg/d, gold 75 g/d, platinum 10 g/d. A hydromet train (leach, solvent extraction, precipitation, reagents, water treatment of its own) is a chemical plant with operators; it does not pay at one Module and is marginal at four. A refiner pays for the metal in a concentrate at 60 to 90 percent payables with no plant on our side.
- Feed. The 13 mm hammermill puts glass into the mineral fraction as grit; separating glass as a product at that top size is sorting sand. Glass goes to the aggregate-grade concentrate, where it is a valid pozzolanic and aggregate component, and the GLS family is left to the catalog.
- Chemistry. The Mineral Phase leaves the Recyclotron at 600 °C, not vitrified; density and
magnetic separation is enough to split it into a heavy, metal-bearing concentrate and a light
aggregate fraction. That is exactly what
MAX-CSPis rostered to do; nothing is missing for the concentrate route. - Rare earths and heavies. The catalog's REE and heavy-metal products are sourced from legacy ash and electronics fractions, not from the reference feed; they stay out of scope until a feed with those fractions is contracted.
22.3 What it costs and what it leaves
| Day-1 slate (eight) | With the graphitiser (Phase 2) | Full RC3 finishing (§17) | |
|---|---|---|---|
| Frames added | 0 (a bagging and baling line inside MAX-CSP) |
+1 to 2 (MAX-GRA and classification) |
+6 to 9 |
| Added load | 0 | 1.1 to 1.9 MW, the deferrable load | 2 to 3.5 MW |
| Balance on the design point | −0.8 to +0.3 MW (§21) | about −1 MW | −1.7 to −3.2 MW |
| Catalog tiers reached | RC1 and RC2, water at RC3 | adds CRB-005 and CRB-008 at RC3 and opens the RC4 carbon products | the RC3 floor less the ash-derived products |
| Products | 8 | 10 | about 50 |
Ruled by the Architect, 2026-11-03: "Yes, rule it." The eight products of §22.1 are the Module's
product scope at Day 1; metals and glass are sold as concentrates; the graphitiser (MAX-GRA with
its classification step) is Phase 2, the one finishing decision carried forward, as the Module's
deferrable load; the remaining RC3 finishing frames of §17.1 (hydromet, glass sort, ASU, activation
beyond char) are out of the Module's scope until a four-Module facility and a feed that justifies
them are contracted. Consequences in this package: §1 products row; §17.5 reads with the slate; the
RC3 finishing load of §17.2 is replaced by the Phase 2 column above; §20 and §20.4 (hydrogen and the
graphitisation schedule) stand as the Phase 2 plan; the product table on the HTML page outlines the
eight.
22.4 For the catalog session and Corpus Zone
The Day-1 slate sells concentrates where the catalog lists refined products: the non-ferrous concentrate replaces the MTL RC2 and RC3 metals, the aggregate concentrate absorbs the GLS family, and the catalog's per-facility revenue needs a concentrate line priced on payables, not product prices. That is a commercial model change and it is theirs; the engineering package is consistent either way.
23. Evolution in stages (Architect direction, 2026-11-03: "we need to show evolution in stages") [PROPOSED]
The package is one design read at four points in time. Each stage is reached by a decision already on the record or named below; nothing in a later stage is assumed by an earlier one.
| Stage 1 — Day-1 Module | Stage 2 — Phase 2, graphitiser | Stage 3 — four-Module facility (York) | Stage 4 — Gen 2 heat source | |
|---|---|---|---|---|
| Trigger | the rulings of 2 and 3 November (§1) | the Phase 2 ruling of §22; MAX-GRA sized | the 400 TPD contract at York; a finishing hall shared by four Modules | the Gen 2 tests: H₂ as plasma gas, A2 microwave, 65-percent fuel cells |
| Throughput | 100 TPD target, both Lines equal; 120 to 165 TPD sustained on the swing rating; 200 TPD peak | same | 400 TPD target; 480 to 660 TPD sustained on the same frames and land | same frames, higher margin |
| Products | 8 (§22.1): carbon black, bed char, industrial CO₂, ferrous, non-ferrous concentrate, aggregate concentrate, SCM powder, industrial DI water | 12: adds standard and high-purity graphite (CRB-005, CRB-008) and the classified carbon-black grades (CRB-006, CRB-007) | about 50: the RC3 floor less the ash-derived products, through a shared finishing hall (hydromet, glass sort, ASU, activation, water grades) | same slate; the RC4 carbon products become reachable from the graphite line when a market justifies them |
| Catalog tiers | RC1 and RC2; water at RC3 | adds carbon at RC3 | RC3 floor across five families | — |
| Frames per Module | 36 to 46 | +1 to 2 (MAX-GRA, classification) |
+6 to 9 in the finishing hall, shared, so +2 per Module-equivalent | −2 to −3 (N₂ loop, generator and T75 deleted) |
| Added electric load | 0 | +1.1 to 1.9 MW, deferrable (§18, §20.4) | +2 to 3.5 MW per Module-equivalent, batched | −0.3 MW (no N₂ compression) and +0.4 MW of fuel-cell output |
| Balance on the design point (§21 range) | −0.8 to +0.3 MW | about −1 MW; closed by 65-percent fuel cells or the calorific floor on the feed | −1.7 to −3.2 MW per Module-equivalent; needs the Stage 4 levers or the calorific floor | about +0.5 to +1 MW with H₂ plasma, 65-percent cells and the cascade |
| Hydrogen | internal fuel; 4 MEGC, 4 h; surplus to the black-start reserve and derated fuel cells | surplus to the graphitisation block, 22:00 to 10:00 | facility Z3 H₂ header pooling four Modules into the finishing hall | H₂ as Recyclotron™ carrier and as the CRSRU plasma gas; no N₂ loop |
| Heat | cascade items 1 to 7 (§16) | plus the graphitiser's recovery to the 40 bar header (+0.3 MW) | shared steam header and thermal store across Modules | — |
| Buildings | three sprung halls per Module, tiered tank pad, 1.64 ha | the graphitiser in Hall 2's MAX bays | four Modules in line sharing fire lanes, one tiered pad, one finishing hall; about 4.8 to 5.5 ha of 7.7 | — |
| What it needs ruled | D-65-C, Q2 amendments, D-REG-SCOPE-02, PowerBlock re-basing, D-ACM-EMS-01, product-scope record | MAX-GRA specification (continuous induction, hold state) under D-FME-01 |
finishing-hall frames under D-FME-01; the concentrate-to-refined decision per family; catalog concentrate pricing | D-65-C Gen 2 addendum; fuel-cell specification at 65 percent |
Reading the stages. Stage 1 is complete on paper and is what this package defines. Stage 2 is one frame and one control line, and it is where the hydrogen surplus and the batch posture go to work. Stage 3 is a facility decision, not a Module decision: the finishing frames only pay when four Modules feed one hall. Stage 4 is the heat-source programme already in the D-65-C memo, and it is the stage that turns the design-point balance positive without a calorific floor on the feed. Stages 5 and 6, the RC4 and RC5 tiers, are facility stages on the shared finishing hall and are set out in §24.
24. Advanced stages — reaching RevCon™ RC4 and RC5 (Architect direction, 2026-11-03) [PROPOSED]
Stages 1 to 4 (§23) take the Module to the RC3 floor. Two further stages reach the catalog's RC4 "Specialized
Circular Material" and RC5 "Premium Circular Product" tiers. Both are facility stages built on the shared finishing
hall of Stage 3; neither changes the Module, its balances or its halls. Product IDs, chains and volumes are the
catalog's (E:/revcon/data/products.json, 100 TPD basis); the lines, units and loads are this package's estimates.
24.1 Stage 5 — RC4 Specialized Circular Material (34 products, 24.2 t/d on the catalog basis)
| Line | Products | Built on | Unit operations added | Load, frames | Dependence |
|---|---|---|---|---|---|
| Advanced carbon | spheroidised graphite CRB-018, synthetic graphite grades CRB-012, graphene oxide CRB-010, carbon-fibre precursor CRB-009, multi-walled CNTs CRB-011, nanoporous activated carbon CRB-020, mesoporous templated carbon CRB-021 | Stage 2 high-purity graphite and conductive carbon; Stage 3 activation | spheroidisation mills and carbon coating; graphite grade classification; a graphene-oxide chemical line (controlled exfoliation of HPG, reagent recovery); a CVD line for CNTs with the Module's own CO as the carbon source (CO disproportionation, in fence); chemical activation (KOH) and silica-templating (the template from the glass line) | 1.2 to 1.8 MW; 5 to 7 units in the finishing hall | none beyond Stage 2; the catalog session's figures put the RC4 carbon products at about $85 M/yr at 400 TPD, most of the catalog's upgrade value |
| Battery metals | black-mass concentrate MTL-045, lithium carbonate MTL-044, lithium hydroxide MTL-048, cobalt sulfate MTL-046, nickel sulfate MTL-047, battery-grade lead MTL-051 | Stage 3 hydromet frame | a battery pick in the receiving bay ahead of the hammermill (a safety line, not only a product line), black-mass leach and crystallisation, lead refining | 0.2 to 0.3 MW; 1 to 2 units | feed-fraction dependent: a battery fraction in the feed contract; the reference feed carries little |
| Ash-derived REE and heavies | cerium, lanthanum, neodymium, yttrium, praseodymium, gadolinium MTL-016 to 021; mercury, cadmium, arsenic, antimony, boron MTL-028 to 032 | the Mineral Phase, when WTE-derived Enhancement Admix is run at up to 25 percent (§RECYCLOTRON_OPTIMIZATION) | a REE-oxide concentrate step and a heavies capture step on the hydromet frame; the heavies step is an environmental duty on the Mineral Phase product in any case, so "capture, then sell" | 0.1 to 0.2 MW; 1 unit | admix dependent; grams per day, sold as concentrates to a refiner |
| Glass and silica | high-quality cullet GLS-008, specialty glass powder GLS-009, photocatalytic silica-TiO₂ GLS-011 | Stage 3 glass sort | optical re-sort, fine milling, a coating step | 0.1 MW; 1 unit | none |
| Water, deeper polish | deionised WTR-007, semiconductor-grade WTR-008 and WTR-FC-002 | Stage 3 polish | electrodeionisation, ultrafiltration, UV; the cheapest pull-ins in the catalog (95 to 97 percent yield) | 0.1 to 0.2 MW | none |
| Specialty gases and CO₂ | specialty mixtures GAS-010, beverage-grade CO₂ GAS-017, neon GAS-011 | the Stage 1 CO₂ product and the Stage 3 ASU | CO₂ purification to beverage grade (the one RC product that sits on a Day-1 stream), a gas blending panel; neon only from a facility-scale ASU residual | 0.1 to 0.2 MW; 1 to 2 units | neon is ASU-scale dependent |
| Minerals | specialty mineral filler MIN-005 | Stage 1 SCM powder | air classification and milling | 0.05 MW | none |
| Stage 5 total | 34 | +8 to 12 units in the shared hall | +1.8 to 2.7 MW at Module scale, shared across four Modules |
24.2 Stage 6 — RC5 Premium Circular Product (17 products, 5.8 t/d on the catalog basis)
| Line | Products | Built on | Unit operations added | Load, frames | Dependence |
|---|---|---|---|---|---|
| Graphene and nanocarbon | reduced graphene oxide CRB-013, multi-layer CRB-014 and single-layer graphene CRB-015, single-walled CNTs CRB-016, fullerenes CRB-017 | Stage 5 graphene oxide and CVD line | hydrogen-assisted thermal reduction of GO (the Module's hydrogen as the reductant, internal use); exfoliation and substrate CVD for graphene; precision CVD for SWCNT; fullerenes from a plasma slipstream of the CRSRU vapour, the one RC5 product that comes straight from the heat source and belongs to the Gen 2 programme | 0.4 to 0.6 MW; 2 to 3 units | kilograms per day; research and specialty scale on the catalog's own basis |
| Ultra-pure metals | tungsten MTL-040, bismuth MTL-041, gallium MTL-042, indium MTL-043 | Stage 5 battery and electronics fractions | zone refining and electro-refining at grams per day | 0.1 MW; 1 unit | feed-fraction dependent (electronics, LED and LCD, pharma fractions); a facility toll line with a dedicated feed, not a Module line |
| Ultra-pure silica and aggregate | ultra-pure silica GLS-010, low-activation aggregate MIN-006 | Stage 5 glass line and SCM | acid leach and classification; aggregate selection by composition | 0.1 MW; 1 unit | none |
| Ultra-high-purity gases | UHP nitrogen GAS-013, xenon GAS-014, krypton GAS-015 | Stage 3 ASU | purification train and rare-gas recovery columns; xenon and krypton are parts-per-million of the air processed and only pay on a facility ASU | 0.2 MW; 1 unit | ASU-scale dependent |
| Pharmaceutical and ultra-pure water | WTR-009, WTR-010, WTR-FC-003 | Stage 5 polish | cleanroom-class final polish, validation and QC | 0.1 MW; 1 unit | certification, not engineering |
| Stage 6 total | 17 | +6 to 8 units, a cleanroom-class bay in the finishing hall, QC laboratory | +0.9 to 1.1 MW at Module scale, shared |
24.3 What the advanced stages do and do not change
- The Module is unchanged. Stages 5 and 6 draw from Stage 1 to 3 streams; the halls, the balances of §15, the dispatch rule and the hydrogen rule stand. Hydrogen is used in fence as a reductant and a CVD atmosphere; it is still never a product.
- Energy. Together the two stages add about 2.7 to 3.8 MW at Module scale, shared across four Modules; the facility's hydrogen surplus (§20) and the Stage 4 levers carry it, with the calorific floor on the feed as the fallback already recorded in §21.
- Feed decides the metals. The battery, electronics and ash-derived lines are only as real as the feed fractions and the admix setting behind them; on the reference feed they are concentrate volumes in grams to tens of kilograms per day. The carbon, water, glass and gas lines do not depend on feed.
- Never delivered, whatever the stage: the mixed gas GAS-001 and pure CO GAS-016, which are the Module's fuel and would cost electricity to sell.
- What needs ruling before either stage is drawn as frames: the facility finishing-hall partition under D-FME-01, the battery pick in the receiving bay as a safety specification, the admix setting that brings ash REE into scope, and a market pull for each RC5 line before its unit is bought; the catalog session to confirm tiers and the per-unit yields.